ID Date Author Category Typedown Subject Text Attachments
  9   Tuesday, December 16, 2014, 16:36 Isaac Earle100KW Beam DumpDevelopmentUpper Pb Shield and Water Hoses Installed The upper lead shield was installed
this morning.  Also the water hoses
for lower lead shield, beam dump, and upper
 BD_Hose_Install_Notes.pdfIMG_4407.JPGIMG_4408.JPGIMG_4410.JPG 
  10   Friday, December 19, 2014, 14:05 Isaac Earle100KW Beam DumpDevelopmentBeam Dump & Lead Shielding Design Documentation As there likely won't be an opportunity
to properly document the design of the beam
dump insert and cooled lead shielding in
 Cooled_Lead_Shielding_Scanned_Design_Notes_(Isaac_Earle).pdf 
  11   Monday, December 22, 2014, 14:21 Isaac Earle100KW Beam DumpDevelopmentWater System Leak CheckedThis morning Bill Richert pressurized the
beam dump water cooling system with 30psi
air and held for 2 hours.  He reported
  
  12   Friday, February 06, 2015, 13:32 Isaac Earle100KW Beam DumpDevelopmentTEL5079 Hose ModificationWhen the EHDT shielding service stand shield
plug was installed in January it was found
that the Beam Dump Outlet Hose (TEL5079)
  
  13   Friday, March 20, 2015, 11:45 Isaac Earle100KW Beam DumpDevelopmentLower Half of BD EHDT Shielding Installed The lower half of the beam dump EHDT
shielding was installed yesterday by Plant
Group.  After installation of the service
 IMG_4791.JPGIMG_4792.JPGIMG_4795.JPGBL_Group_Alignment_Report_-_steel_plug_for_beam_dump.pdfBL_Group_Alignment_Report_-_steel_shielding_block_for_beam_dump.pdf 
  14   Friday, April 17, 2015, 14:37 Isaac Earle100KW Beam DumpDevelopmentRH Clamp Delivered to Beamlines Group A 4" Remote Handling Marman
Flange Clamp was delivered to Doug Preddy
today to be used to clamp the EHDT beam pipe
  
  15   Wednesday, May 06, 2015, 14:19 Isaac Earle100KW Beam DumpDevelopmentEHDT Beam Pipe Section Installed- On May 4th the EHDT beam pipe section
was installed by Mike Vogel of Beamlines
Group
 IMG_4922.JPGIMG_4924.JPGIMG_4925.JPG 
  16   Thursday, May 07, 2015, 16:23 Isaac Earle100KW Beam DumpDevelopmentRH Clamp Installed with Used SealThe remote handling 4" marman flange
clamp was reinstalled today with a used seal.
 It is "Clamp B" as tested
  
  17   Friday, May 15, 2015, 11:06 Isaac Earle100KW Beam DumpDevelopmentBD and Upper Pb Shield Water Hoses Replaced The beam dump and upper lead shield
flexible hose assemblies have been replaced
with smaller diameter versions to allow for
  
  18   Thursday, May 28, 2015, 16:08 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Vac Seal RH Test & InstallationThe following work was performed on
May 27 & 28, 2015:
- The beam dump 10kW Remote Handling
 BD_Vac_Flange_RH_Test_Procedure_-_June_2_2015.docx 
  19   Tuesday, June 02, 2015, 16:42 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Water Block RH Test & InstallationBeam dump waterblocks #1 (BD
Inlet) and #3 (Upper Pb Inlet) were removed
 BD_Water_Block_RH_Test_Procedure_-_June_2_2015.docx 
  20   Monday, June 08, 2015, 15:15 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Vacuum Leak- On Thurdsay June 4th the EHDT beamline
section was vented by Vacuum Group so that
they could install a new pump
 BD_Flanges_and_Clamp_Jaws_Dimension_Check_-_Keith_Ng_-_June_5_2015.pdf 
  21   Monday, June 08, 2015, 15:23 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Seal Re-Install On Monday June 8 the following work
was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented
  
  22   Wednesday, June 10, 2015, 14:57 Isaac Earle100KW Beam DumpDevelopmentBD Water System Leak TestA leak test was performed on the beam dump
water system on June 9 in the afternoon.
- Pipe segments tested: The entire
  
  23   Friday, June 12, 2015, 10:16 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Vac Seal Vent & Test- Vacuum has been pumping steadily on the
EHDT section since June 8, reaching 3.2E-8
Torr at 8am today (June 12)
  
  24   Monday, June 15, 2015, 17:08 Isaac Earle100KW Beam DumpDevelopmentE-Dump Shielding Installation- The hoist rings were removed from the
upper lead shield
- Two standard lock-blocks were installed
  
  25   Wednesday, June 24, 2015, 15:19 Isaac Earle100KW Beam DumpDevelopmentRemainder of BD Shielding InstalledThe location of the already installed blocks
including the TSH0392 protruding lift bails
were remeasured, and it was found that modification
  
  26   Tuesday, November 03, 2015, 13:15 Isaac Earle100KW Beam DumpDevelopmentInitial tests of beam dump water system controlsDuring the maintenance period today the
E-Hall tunnel was accessed to begin controls
tests on the beam dump water system and initial
  
  28   Thursday, April 07, 2016, 11:25 Isaac Earle100KW Beam DumpDevelopmentResult of VCR Gasket Corrosion Test In August 2014 gasket corrosion tests
were prepared by placing a 1" Swagelok
VCR gasket in a 500mL beaker with de-ionized
 IMG_7003.JPGIMG_7004.JPGIMG_7005.JPGIMG_7006.JPGIMG_7007.JPG 
  29   Wednesday, February 15, 2017, 11:57 chad fisherT-Hall CraneDevelopmentJason's Remote Crane Test BoxesOn Tuesday, February 14th I finished modifying
Jason's boxes for the remote crane tests
by adding shelves to mount cameras... Apart
  