73
|
Thursday, November 28, 2024, 09:04 |
Adam Newsome | Hot Cell 1 | Repair | Hot Cell turntables not rotating, access hatch not moving | It was reported that the hot cell turntables
would not rotate and the access hatch could
not be operated. The turntables' elevation |
|
74
|
Friday, November 29, 2024, 15:23 |
Adam Newsome | Hot Cell 1 | Maintenance | 1000 kg crane: y axis position display not functioning | After a recent power cycle, the y-axis
referencing was lost for the 1000 kg crane.
The position readout was also incorrect, |
|
75
|
Wednesday, December 11, 2024, 11:45 |
Albert Kong | Hot Cell 1 | Development | APTW Front End Service Tray and Associated Component Testing | Dec 10, 2024
Testing completed: |
16x |
76
|
Thursday, December 12, 2024, 15:57 |
Aaron Tam | Hot Cell 1 | Development | Pistons Gas lines exchange | December 12, 2024 - Chad Fisher,
Albert Kong, Aaron Tam
Tests: |
13x |
77
|
Thursday, December 12, 2024, 16:20 |
Aaron Tam | Hot Cell 1 | Development | Extraction Electrode Banana Plug (Show and Tell) | December 12, 2024 - Chad
Fisher, Albert Kong, Aaron Tam, Austin Hagen
Tests: |
6x |
33
|
Tuesday, May 02, 2017, 16:52 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand hardened parts tested | Hardness testing was performed on
1 sample each of parts TBP1822 and TBP1823
(part of the 35-deg magnet stand assembly |
|
35
|
Thursday, June 01, 2017, 15:25 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender adjustment blocks modified to fit magnet | Adjustment blocks were installed on the
second dipole bender today (labeled "No.
03" "C15-III-57/15"). The |
|
36
|
Monday, June 05, 2017, 16:16 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand assembly complete | Assembly
of two complete bender stands was completed |
14x |
37
|
Wednesday, June 28, 2017, 17:37 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender "No. 1" installed on magnet stand | BL4N 35-deg bender magnet "No.
1" has been installed onto the magnet
stand with "stand leg" configuration |
|
1
|
Tuesday, November 04, 2014, 16:58 |
John Wong | 100KW Beam Dump | Maintenance | Testing Elog | Tuesday, November 04, 2014, 16:58
This is a test.
|
|
2
|
Wednesday, November 19, 2014, 13:49 |
Isaac Earle | 100KW Beam Dump | Development | Decision on Modifications to Lower Center Block (TSH0225) | I received a call today from Jim Adamson
at Kaltech regarding modifications to shielding
block TSH0225. |
|
3
|
Friday, November 21, 2014, 13:37 |
Isaac Earle | 100KW Beam Dump | Development | Destructive Testing of 1" MDC Ceramic Breaks | Testing was performed on the ceramic water
breaks to be used on the beam dump water
hose assemblies. The ceramic breaks |
|
4
|
Wednesday, November 26, 2014, 17:50 |
Isaac Earle | 100KW Beam Dump | Development | Installation of Lower Center Block (TSH0461) | Painting and relabeling of the modified
lower center block (TSH0461) was completed
on Monday Nov 24. |
|
5
|
Wednesday, December 03, 2014, 10:16 |
Isaac Earle | 100KW Beam Dump | Development | Installation of Lower Lead Block and Beam Dump Insert | On November 28th the lower lead shield
was installed with 3/8" shimming at
the front end, and 11/32" shimming at |
|
6
|
Wednesday, December 03, 2014, 10:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper half of BD water blocks installed; Bypass loops installed | On December 2 the upper half of the RH
water blocks were installed (4 total) using
a 0.030" thick 6061-T6 Al shim torqued |
|
7
|
Wednesday, December 03, 2014, 10:45 |
Isaac Earle | 100KW Beam Dump | Development | BD Signals Traced from Service Stand to Junction Box | On Dec 2 the cables from the BD service
stand area to the junction box were traced
to establish which sensors correspond to |
|
8
|
Friday, December 05, 2014, 10:43 |
Isaac Earle | 100KW Beam Dump | Development | Lower Lead Shield Drain Line Installed | A 1/8" SS tube was routed from the
Swagelok fitting on the front of the lower
lead shield to the service stand water catch |
|
9
|
Tuesday, December 16, 2014, 16:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper Pb Shield and Water Hoses Installed | The upper lead shield was installed
this morning. Also the water hoses
for lower lead shield, beam dump, and upper |
|
10
|
Friday, December 19, 2014, 14:05 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump & Lead Shielding Design Documentation | As there likely won't be an opportunity
to properly document the design of the beam
dump insert and cooled lead shielding in |
|
11
|
Monday, December 22, 2014, 14:21 |
Isaac Earle | 100KW Beam Dump | Development | Water System Leak Checked | This morning Bill Richert pressurized the
beam dump water cooling system with 30psi
air and held for 2 hours. He reported |
|