Tuda logbooks General E1104 ISACII E1195 E1103 E1147 S1287 S1203 S1233 S1284 S1447 23Na(a,p) S1540 S1381  S1847 Catania
  S1287, all entries  ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Type Categorydown Subject Text Attachments
  55   Mon Sep 24 07:16:18 2012 Jessica TomlinsonOtherOtherAnalysis update Energy vs Time plots

I updated
 S21evst_data.pdfS21evst_mc.pdfS22evst_data.pdfS22EvsT_mc.pdf 
  59   Tue Dec 4 05:40:10 2012 Jessica TomlinsonOtherOtheranalysis - single strip E vs t  I have attached some single strip
energy vs time plots to show that the structure
seen in the collective E vs t plots is in
 6x 
  1   Mon Apr 4 01:34:54 2011 Jamie BrownRoutineGeneralProposalSee attached.  S1287_201007S_merged.pdf 
  31   Mon May 23 09:59:23 2011 Mike BentleyRoutineGeneralEnd/Dtart of Run Summary (BRF/MAB)Ran all night OK, currently 14epA, H2 stable,
DAQ stable
ISSUES:
  
  32   Mon May 23 15:58:30 2011 Mike BentleyRoutineGeneralEnd of Shift summary OK - summary of events during this
shift.
 
  
  34   Tue May 24 01:16:37 2011 Tom DavinsonRoutineGeneralRe: End of Shift summary
1.TDCs. We have been sorting offline, and
we have now established that between run
  
  36   Tue May 24 08:18:23 2011 Mike BentleyRoutineGeneralend of shift summary We have been running smoothly all
night. Only problem is that the DAQ occasionally
does not start properly after a stop-go.
  
  37   Tue May 24 20:45:12 2011 Mike BentleyOtherGeneralUpdate for during the day 24th May, wednesday Update: 
W decided at 8.00 to stop, check
the tune, retune and get back going. This
 photo-7.pngphoto-8.png 
  38   Tue May 24 23:59:16 2011 Jennifer Fallis, Lars MartinRoutineGeneralShift summaryBuncher problem was resolved around 22:00
(driver module needed to be replaced).
Checked current on FC0 and trigger rate,
  
  39   Wed May 25 03:15:44 2011 BrianRoutineGeneralStart of run summary and TDC problemsSummary at start of run
Read through the runbook and end
of run summar and the situation appears to
  
  40   Wed May 25 07:09:17 2011 BrianRoutineGeneralEnd of run summary (yes, a bit early, but done all I can think of!)Running status
Everything seems to be running OK. 
ADC and TDC spectra look OK.  Chamber
  
  41   Wed May 25 18:05:55 2011 Mike BentleyRoutineGeneralReport on day shift and changed energy - now at 3.98 MeV/u All ran smoothly.
As a test, ran for a short period
at 1200 midday to run without S2-2 in the
 photo.png 
  44   Thu May 26 02:54:10 2011 Derek and NaomiRoutineGeneralThu 0-8am shift summary 
For run 123:
Beam outage for ~15 min but not stopping
  
  46   Thu May 26 23:46:40 2011 Sarah and BrianRoutineGeneralThu 16:00-00:00 summaryRun139

Started 19:05:03
  
  47   Thu May 26 23:57:34 2011 DerekRoutineGeneralFriday 00:00 - 08:00 SummarySarah informed me that Jamie was performing
the sorting and saving of spectra differently
and didn't know what exactly to do so I will
  
  49   Fri May 27 23:13:01 2011 Alex RojasRoutineGeneralShift summaryNo major problems presented, A pluser walk
was performed at the begining of the shift
run161 S2-1 front, run162 S2-2 front, run163
  
  50   Sat May 28 07:46:09 2011 Lars MartinRoutineGeneral Beam current dropped to 85 epA at the start
of the shift, operator checked for reasons
and decided to change
  
  54   Wed Jul 18 08:29:03 2012 Jessica TomlinsonOtherGeneralAnalysis update Energy calibration for S2-2 was done
using the pulser data (set 6 of the pulser
runs) to calculate the offsets and alpha
  
  57   Fri Nov 16 07:12:32 2012 Jessica TomlinsonOtherGeneral4.11 MeV/u analysisI have sorted the 4.11MeV/u data runs (the
ones which had the common stop mode on the
TDCs) and applied the following cuts:
 6x 
  58   Fri Nov 16 07:23:26 2012 Jessica TomlinsonOtherGeneralS2-1 plot that would fit on previous elog Attachment 1 shows S2-1 energy vs
time with a gate on energy in S2-2 being
greater than 9MeV i.e. See previous elog
 S2-1-evst-9mevcut.001.png 
  60   Fri Jan 11 06:56:01 2013 Jessica TomlinsonOtherGeneralmultiplicities, hit patterns and good hits in an eventI have attached a pdf of a series of slides
with some multiplicity and hit pattern plots
on, also a list of cuts. As well as this
 411mev-multiplicities-and-hitpat.pdf 
  61   Fri Jan 11 09:48:58 2013 Tom DavinsonOtherGeneralRe: multiplicities, hit patterns and good hits in an event
  
  2   Sat Apr 9 11:35:14 2011 Tom Davinson  TUDA configuration & setup
Nominal detector configuration for S1287
is as follows:
 GasTUDA-7.png 
  3   Sat Apr 9 14:57:30 2011 Tom Davinson  MIDAS DAQ configuration
tuda2 (by TUDA chamber, SEBT1) was powered
off on arrival
 11x 
  4   Mon Apr 11 14:57:08 2011 Tom Davinson  SEBT1 & HERACLES wipe tests
Work permit (2011-4-11-3) was requested to
vent SEBT1 upstream of TUDA chamber
  
  5   Mon Apr 11 18:39:17 2011 Tom Davinson  Monday 11 April
TUDA was successfully re-installed on SEBT1
by LB, TD, AML and PM.
 2.png3.png4.png 
  6   Tue Apr 12 11:21:38 2011 Tom Davinson  Tuesday 12 April The TUDA @ ISAC-II grounding test was successfully
completed this am
per work permit 2011-04-12-2.
 1.png 
  7   Wed Apr 13 03:43:42 2011 Jamie  Ni window leak tests 12um x 8 mm Ni windows leaked tested on
TUDA gas cell. With window placed on the
outside of the cell, cell was evacuated and
 Screenshot.pngScreenshot-1.png 
  8   Wed Apr 13 03:55:21 2011 Jamie  Safety Reportattached
 
note. s2 position in fig. 1 is wrong,
 S1287-Revised_Safety_Report.pdfrevised.pdf 
  9   Wed Apr 13 09:37:51 2011 Tom Davinson  Wednesday 13 April
09.20 TUDA2.PNG5 1.04E-06Torr
      See attachments 1 & 2 for EPICS log
 3.png2.png4.png 
  10   Thu Apr 14 10:06:34 2011 Tom Davinson  Thursday 14 April
10.02 See attachment 1 for overnight EPICS
log of TUDA2.CG5
 1.png5.png 
  11   Fri Apr 15 11:00:17 2011 Tom Davinson  Friday 15 April11.15 See attachment 1 for overnight EPICS
log of TUDA2.CG5
      Downstream flange *not* secured by
 2.png6.png 
  12   Sat Apr 16 09:31:56 2011 Tom Davinson  Saturday 16 AprilContinuation of yesterday's test with c. 300mBar
of He
in the TUDA chamber.
  
  13   Sun Apr 17 09:47:04 2011 Tom Davinson  Sunday 17 AprilContinuation of yesterday's test with c. 300mBar
of He
in the TUDA chamber.
 He_test.png 
  14   Thu May 5 11:31:13 2011 JB  Tom's ToDo List 

  
  15   Fri May 6 06:03:00 2011 Tom Davinson  Sort programs, spectra titles & calibration procedureA summary of online sort programs can be found
at:
  
  16   Fri May 6 15:08:00 2011 JB  New TUDA EPICS layout   gas_handling-3.png 
  17   Sat May 7 17:29:13 2011 JB  Window leak tests on TUDAAttached plot shows rate of pressure increase
in ~2l volume upstream of TUDA with Ni window
#2 installed on reentrant flange. Comparison
 window2-leaktest.png 
  18   Wed May 11 17:59:12 2011 JB  Re-entrant flange alignmentAlignments checks revealed that downstream
end of TUDA was ~1mm off (can't remember
which way).
  
  19   Thu May 12 03:04:44 2011 Tom Davinson  Re: Re-entrant flange alignment> Alignments checks revealed that downstream
end of
> TUDA was ~1mm off (can't remember which
  
  20   Sun May 15 13:07:12 2011 JB  W detector V-I curveYork W detector 2635-19
1037um
 W_detector_V-I_curve.png 
  21   Mon May 16 21:14:19 2011 Jamie Brown  Broken solder on PD2As you can see...  PD2-broken_solder.png 
  22   Tue May 17 12:32:13 2011 Jamie Brown  Thick carbon targetThe thick carbon target, to be used for
background runs for the thick CH2 measurement
was supplied by Marek.
  
  23   Wed May 18 08:54:08 2011 Alex Murphy  Photodiode data from target thickness measurements In attachment are the peak position
in the photodiodes (with high gain setting)
for the target thickness measurements.
 pdruns.xls 
  24   Wed May 18 08:58:53 2011 Alex Murphy  Foil energy lossesI've analysed
data from runs 4 to 12, which were the alpha
  
  25   Wed May 18 09:09:02 2011 Alison Laird  Status update Wednesday morning:
4 new windows were tested last night.
2 very good.
  
  26   Fri May 20 05:47:08 2011 Tom Davinson  3.25MeV/u 21Ne(5+)   22.grab.y17428.png 
  27   Sat May 21 18:25:36 2011 Jamie Brown  Beam spot   DSC05470.JPG 
  28   Sun May 22 11:45:03 2011 Tom Davinson  4.11MeV/u 21Ne(5+)   30.grab.h25527.png 
  29   Mon May 23 02:12:14 2011 BrianRoutine Start of Run summaryHandover from last shift was...
1. Running at 4.11 MeV/u at about
15enA (5+)
  
  30   Mon May 23 02:16:32 2011 Jamie Brown  End of run summaryPlan for shift was to increase trigger
thresholds on S2-1 and S2-2 to cut out the
low energy "stuff" which is dominating
  
  33   Tue May 24 00:01:03 2011 Oliver and HichamRoutine end of shift summaryThings have been running smoothly from
4 pm to midnight.
Reading in FC0 = 120-130 epA
  
  35   Tue May 24 01:47:17 2011 Anonymous  Shift schedule, as of 1am Tuesday 24th   Screenshot.png 
  42   Wed May 25 22:45:42 2011 Jamie Brown  Leakage current in S2-1At approximately 7pm, noted that trigger
rate in S2-1 had dropped by factor of ~20.
Detector had tripped off due to leakage current
  
  43   Thu May 26 00:15:18 2011 Hicham and SarahRoutine End of run summarystill running at 3.98 MeV/u
19:08
S2-1 had tripped off due to leakge
  
  45   Thu May 26 12:53:48 2011 Jamie Brown  H2 fill and vent proceduresPlease note that these procedures are not
perfect and other small operations not listed
may need to be carried out. Some mistakes
 H2_filling_procedure.pdfH2_venting_procedure.pdf 
  48   Fri May 27 14:24:00 2011 Tom Davinson  S1287 data transfer
S1287 data files R1_*.gz to R100_*.gz transferred
from directory
  
  51   Sat May 28 10:07:44 2011 Jamie Brown, and Mike Bentley  Plan for last day1) PD run with gas (250Torr) - done
2) Pump down to 50 Torr - done
3) PD run - done
  
  52   Mon Jun 20 05:58:21 2011 Jamie Brown  Run logAttached is a spreadsheet summarizing all
the run information from the experiment.
 run_log.xls 
  53   Tue Jun 21 02:58:31 2011 Jamie Brown  Run Books 13 and 14Attached. Book 13 is split into 4 sections
as otherwise the file is too big for the
elog to accept.
 tuda_book13_1-47.pdftuda_book13_48-95.pdftuda_book13_96-143.pdftuda_book13_144-191.pdftuda_book14.pdf 
  62   Wed Feb 4 17:27:55 2015 Anonymous   This is reachable and change-able via outside
Internet
  
ELOG V2.9.2-2455