Wednesday morning:
4 new windows were tested last night. 2 very good.
Now venting to install and test Faraday cup, install and test camera.
Remaining to do list:
Before beam -
beamline on SEBT back in and pumping upstream section
(measure C and C/Au target thicknesses if time)
replace 4mm collimator on plate with 10 mm for tuning
confirm PD0 problem just connector
install detector shields and pump down
walk round TUDA and check no grounding compromises
Before running -
runplan
procedures tick list for H2
runlog and detector current list
exclusion zone and Al plate before running H2 |