Entry  Monday, May 01, 2023, 14:31, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-5, 45235-20, In progress, Conditioning TiC#5 TiC#5_-_44692-5_Anode_&_Coil_checks.docxTiC#5_-_44692-5_Conditioning.docx
New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on 
Entry  Wednesday, April 26, 2023, 08:46, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-6, 45235-20, , Testing TiC#5 assembly w/ an empty target TiC#5_empty_container_run.docxScreenshot_from_2023-04-27_21-54-15.png
Anode remade with a ceramic "elbow-cube". Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: BV1B open. Roughing.
Wednesday, April 26, 2023, 08:46: BV1A open
Entry  Monday, April 17, 2023, 14:08, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6 
Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on.
Entry  Thursday, April 13, 2023, 11:07, Aaron Schmidt, , , , , , , In progress, Installation of new IDP-15 TMS:TP2 
IDP15 Scroll Pump, Std w/ inlet.
TMS:RP2
PN: X3815-64010
Entry  Wednesday, March 29, 2023, 12:22, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-7, 45235-20, Failed, Conditioning TiC#5 TiC#5_conditioning.docx
Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on.
Entry  Thursday, February 02, 2023, 12:44, Aaron Schmidt, , LP-SIS, , , 44062-1-SK , 45235-1, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Thursday, February 02, 2023, 12:41: Roughing.
Thursday, February 02, 2023, 12:43: BV1A open.
Entry  Tuesday, January 31, 2023, 10:42, Aaron Schmidt, , LP-SIS, , , 44062-1-SK, 45235-7, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Tuesday, January 31, 2023, 10:39: Roughing. (Took quite a bit of effort to get the doors to shut. It's colder than usual in here. The seals were
stiff)
Entry  Tuesday, January 17, 2023, 09:48, Aaron Schmidt, , , , , , , Problems/Solutions, TMS:RP2 Failure 
Tuesday, January 17, 2023, 09:48: TMS:RP2 off. Audible failure was in progress. Also observable on the strip tool. Vacuum group contacted.
Entry  Monday, January 16, 2023, 16:02, Aaron Schmidt, , HP-FEBIAD-CTL, , , , , In progress, HP-FEBIAD tests 
Extra wraps of foil around the center block (6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: Roughing.
Monday, January 16, 2023, 16:10: TP1B on.
Entry  Thursday, January 12, 2023, 09:04, Aaron Schmidt, , LP-SIS, , , 44691-14, 44378-20, In progress,  
Test for Aurelia L. Empty LP-SIS w/ end caps in. Right side expanded.
Thermocouples installed (R - L):
X & Y For the (V) checks.
Entry  Tuesday, January 03, 2023, 10:03, Carla Babcock, , , , , , , , Recovery from power outage 
Easy recovery after power outage, just had to power cycle the ground PLC IOC and the BiRa IOC.
Test stand vacuum currently pumping down again. Water and HV elements still off.
Tuesday, January 03, 2023, 11:13: Reset IG6 - Filament 2. Vacuum 7.22e-06T - AS
Entry  Wednesday, December 21, 2022, 17:06, Carla Babcock, , , , , , , , Prep for power outage 
Source and beamline power supplies turned off in EPICS
HV cage power off
Magnet ramped down and power supplies turned off manually (bira and tdk lambda)
Entry  Monday, December 19, 2022, 12:49, Carla Babcock, , HP-FEBIAD, , , , , , HP-FEBIAD tests 
Monday, December 19, 2022, 12:06 : Tomislav changed the polarity of the anode power supply last week and everything has been closed up again. The anode
wire was switched to feedthru J and the short there removed. Forgot to put the short on the tube before closing the top but it should be ok for these tests
since it has the resistor still installed to keep it at some potential. Pumping out gas lines.
Entry  Friday, December 16, 2022, 10:32, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 3 
Thermocouples installed (X):
O - O
O - Anode
Entry  Tuesday, December 13, 2022, 16:12, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 2 Re-routed_Anode_FEBIAD_12-2022_Test_2.docx
Thermocouples installed (X):
O - O
O - Anode
Entry  Tuesday, December 06, 2022, 11:20, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Tests Re-routed_Anode_FEBIAD_12-2022_Test_1.docxITS_FEBIAD_measurements_12-2022_Test_1.xlsx
Thermocouples installed:
O - O
O - Anode
Entry  Monday, December 05, 2022, 15:41, Aaron Schmidt, , , , , , , , Source tray insulator replacement 7x
 Monday, December 05, 2022, 15:38: Source Tray TGHT & TBHT insulators replaced. 
Torqued @ 75 in-lbs. (Reference image attached)
 
Entry  Wednesday, November 23, 2022, 13:52, Aaron Schmidt, , , , , , 44378-14, In progress, FEBIAD Coil Tests 
Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 FS#5 on (HS bypassed with a water loop)
Entry  Wednesday, November 16, 2022, 13:28, Aaron Schmidt, , , , , , , Problems/Solutions, TSG:TP1A Replaced 
 See elog 944
Wednesday, November 16, 2022, 13:23: TP1 A replaced
Wednesday, November 16, 2022, 13:25: Roughing.
Entry  Tuesday, November 15, 2022, 15:32, Sam Gupta, , , , , , , , ATTS tantalum Bracket Heating test 
Heated up sample 01 for the second time and measured the temperature with increasing current. Used pyrometre to measure temperature and calibrated it
with the emmissivity values from cassidy