Easy recovery after power outage, just had to power cycle the ground PLC IOC and the BiRa IOC.
Test stand vacuum currently pumping down again. Water and HV elements still off.
Tuesday, January 03, 2023, 11:13: Reset IG6 - Filament 2. Vacuum 7.22e-06T - AS
Tuesday, January 03, 2023, 14:00: Both Turbo pumps on.
Tuesday, January 03, 2023, 14:27: Vacuum @ 2.32e-06T
Tuesday, January 03, 2023, 14:28: FS#2 opened. Vacuum ok.
Tuesday, January 03, 2023, 14:29: FS#3 opened. Vacuum ok.
Tuesday, January 03, 2023, 14:30: FS#4 opened. Vacuum ok.
Tuesday, January 03, 2023, 14:31: FS#5 opened. Vacuum ok. Stable @ (2.24-2.32)e-06T. - AS |