  Test-Stand, Page 24 of 53  Not logged in ELOG logo
  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  658   Wednesday, April 25, 2018, 09:50 Aaron SchmidtTa (test)LP-SIS  41177-3 In progressTa test and window changeWindow changed on view port. Ta target
prepared for Aurelia's tests.
***Note*** No Ta window foils
 TS-2018-04-25-14-55.rgaTa_target_heating_test_-_Test_stand.docx 
  659   Monday, April 30, 2018, 12:07 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest readyReady for C-seals or FEBIAD work
Monday, April 30, 2018, 12:05: Roughing.
Monday, April 30, 2018, 13:11: Turbo
  
  660   Tuesday, May 08, 2018, 10:36 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressC-seal Test2 C-Seals installed with SS springs
on water blocks. The SS springs are also
used in the module.
  
  664   Monday, May 28, 2018, 08:46 Aaron Schmidt LP-FEBIAD TM241790-942752-5In progressNew TM source tray swap out. Monday, May 28, 2018, 08:45: Venting. Prep
For removal.
Close FS#8. Clean up water
 New_TM_Source_Tray_2018.docxTS-2018-05-30-06-30.rgaER-580-310-30kV-m28.txtER-580-320-30kV-M39.txt2018_TM2_Source_Tray_in_Test_Stand_-_Test_Results.docx 
  668   Tuesday, June 12, 2018, 11:38 Aaron Schmidt      In progressSource Tray re-installationRe-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect
 TS_Source_Tray_re-installed_2018_-_(Leak_found).docx 
  670   Thursday, June 21, 2018, 16:32 Anders Mjos LP-FEBIAD  41790-942752-5In progressHeating targetThursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping
 TS-2018-06-19-10-30.rgaTS_Source_tray_2018_-_Check_2.docx 
  671   Tuesday, July 03, 2018, 12:46 Aaron SchmidtTa#56HP-SISITETM442218-942752-3In progressConditioning Ta#56Tuesday, July 03, 2018, 12:44: Roughing
Tuesday, July 03, 2018, 13:32: Turbo
pumps started.
 8x 
  672   Monday, July 09, 2018, 10:44 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test July Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on.
  
  673   Thursday, July 12, 2018, 08:24 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressPower outage / restartPower outage (07/11/2018 @ approx 21:53)
shut down the test stand.
  
  674   Thursday, July 12, 2018, 10:11 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test #5 *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened
  
  675   Monday, July 23, 2018, 14:25 Aaron SchmidtUC#23LP-FEBIAD-CTLITETM2  In progressConditioning Heat Shield for UC#23Monday, July 23, 2018, 14:20: Roughing.
Monday, July 23, 2018, 14:54: Turbo
pumps on. 
 UC#23_emit.dat_error.docxTS-2018-07-2-08-07.rgaTS-2018-07-24-07-20.rgaUC#23.docx 
  676   Friday, July 27, 2018, 14:44 Aaron SchmidtUC#24LP-SISITETM441177-342752-6In progressConditioning Heat Shield for UC#24 & voltage test prep4 Kapton wire routed into the 9-pin connector.
Unused pins are grounded on the bracket.
Friday, July 27, 2018, 14:25: Roughing
  
  683   Friday, August 31, 2018, 12:27 Aaron SchmidtnSiC#1LP-SISITWTM243044-142752-4In progressConditioning nSiC#1Friday, August 31, 2018, 12:27: Roughing.
Friday, August 31, 2018, 13:19: Turbo
pumps started.
 15x 
  684   Wednesday, September 12, 2018, 11:19 Aaron SchmidtTa#57LP-SISITETM441177-342752-6In progressConditioning Ta#57Wednesday, September 12, 2018, 11:06: Roughing.
Help req'd. Doors wouldn't seal.
Wednesday, September 12, 2018, 11:52:
 9x 
  685   Monday, September 17, 2018, 11:52 Aaron SchmidtUC#25LP-SISITWTM2 42752-9In progressConditioning Heat Shield for UC#25Monday, September 17, 2018, 11:47: Roughing*.
Doors not sealing, help acq'd 
Monday, September 17, 2018, 11:51:
 OMEGA_OM-DAQPRO-5300_24-Sep-18_08.08.26.dlpTS-2018-09-17-14-10.rgaUC#25.docx 
  686   Friday, September 21, 2018, 11:41 Aaron SchmidtUC#26LP-IG-LISITETM4 42132-1In progressConditioning Heat Shield for UC#26Friday, September 21, 2018, 11:40: Roughing
Friday, September 21, 2018, 11:41:
Doors sealed for roughing.
 TS-2018-09-21-14-53.rgaUC#26.docx 
  687   Tuesday, October 02, 2018, 13:39 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps w/ stoppageSilver bolts used on Coil, TGHT, &
TBHT.
End caps in target
 FEBIAD_Coil_Test_6_-_POS_Cathode.docxTS-2018-10-11-10-37.rga 
  688   Monday, October 15, 2018, 14:23 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps Anode / Cathode BIAS PS polarity reversed
by John Chow. PS: Negative
Monday, October 15, 2018, 14:12:
 FEBIAD_Coil_Test_6-2_-_Neg_Cathode.docxTS-2018-10-15-14-15.rga 
  691   Monday, October 22, 2018, 11:07 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps Restarted post power outage.
Water & Turbos on.
Monday, October 22, 2018, 10:55:
 epics-plot-whiteout-181028_1322.PNGepics-whiteout-181028_1322.PNGFEBIAD_COIL_Test_6-3_Caps_in.docxTS-2018-10-22-09-47.rga 
  694   Tuesday, November 06, 2018, 08:52 Aaron Schmidt      In progressPump down empty chamberTuesday, November 06, 2018, 08:50: Roughing
Tuesday, November 06, 2018, 08:51:
Doors sealed.
  