Window changed on view port. Ta target prepared for Aurelia's tests.
***Note*** No Ta window foils on the end plates. Initial ramping to on the TGHT to 300 A. Follow up in increments of 50 A and check the right door window temperature.
Wednesday, April 25, 2018, 09:47: Roughing both the Evap/box end and beam end.
Wednesday, April 25, 2018, 10:27: All 4 turbo pumps started.
Wednesday, April 25, 2018, 10:49: Both Ion gauges on.
Wednesday, April 25, 2018, 14:56: RGA on.
Thursday, April 26, 2018, 06:54: Water lines opened. No response on RGA. Vacuum stable @ 4.23e-07T
Thursday, April 26, 2018, 06:56: Power/sources on.
Thursday, April 26, 2018, 07:00: Auto ramping TGHT to 300 @ 2A per min.
Thursday, April 26, 2018, 07:05: IV4 opened.
Thursday, April 26, 2018, 08:50: Door temp @ 25 C @ left window.
Thursday, April 26, 2018, 09:30: 300A reached. Door temp @ 26 C @ left window.
Thursday, April 26, 2018, 13:01: 550A Reached. Door temp @ 29 C @ left window.
Monday, April 30, 2018, 07:05: IV4 closed, RGA off.
Monday, April 30, 2018, 07:10: Ion gauge off. Turbo pumps off.
Monday, April 30, 2018, 11:00: Venting. Purging water lines. |