Message ID: 686     Entry time: Friday, September 21, 2018, 11:41
Author: Aaron Schmidt 
Target/No.#: UC#26 
Source: LP-IG-LIS 
Station: ITE 
Module: TM4 
Target Oven W.O#:  
Heat Shield W.O#: 42132-1 
Status: In progress 
Subject: Conditioning Heat Shield for UC#26 

Friday, September 21, 2018, 11:40: Roughing

Friday, September 21, 2018, 11:41: Doors sealed for roughing.

Friday, September 21, 2018, 14:02: Turbos on.


Monday, September 24, 2018, 08:05: Waterlines opened. No response on RGA. Vacuum ok @ 4.23-e07T

Monday, September 24, 2018, 08:12: Power / sources on.

Monday, September 24, 2018, 08:15: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2A per min

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 24.3 3.92
 TBHT 24.2 3.11
 COIL + EE 24.1 5.15
 TGHT  24.3 5.80

 Monday, September 24, 2018, 13:45: Vacuum  ok @ 6.47e-07T

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 33.7 4.06
 TBHT 24.9 3.11
 COIL + EE 24.7 5.18
 TGHT  27.0 5.83

 


Friday, September 28, 2018, 09:59: Auto-cooling @ 2A per min.


Tuesday, October 02, 2018, 08:32: Power / Sources off.

Tuesday, October 02, 2018, 08:37: Purge waterlines & empty DI bucket.

Tuesday, October 02, 2018, 08:38: RGA off. Ion gauge, turbo pumps off.

Attachment 1: TS-2018-09-21-14-53.rga  7.805 MB  Uploaded Tuesday, October 02, 2018, 11:09
Attachment 2: UC#26.docx  763 kB  Uploaded Tuesday, October 02, 2018, 11:09