658
|
Wednesday, April 25, 2018, 09:50 |
Aaron Schmidt | Ta (test) | LP-SIS | | | 41177-3 | | In progress | Ta test and window change | Window changed on view port. Ta target
prepared for Aurelia's tests.
***Note*** No Ta window foils |
|
659
|
Monday, April 30, 2018, 12:07 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test ready | Ready for C-seals or FEBIAD work
Monday, April 30, 2018, 12:05: Roughing.
Monday, April 30, 2018, 13:11: Turbo |
|
660
|
Tuesday, May 08, 2018, 10:36 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | C-seal Test | 2 C-Seals installed with SS springs
on water blocks. The SS springs are also
used in the module. |
|
664
|
Monday, May 28, 2018, 08:46 |
Aaron Schmidt | | LP-FEBIAD | | TM2 | 41790-9 | 42752-5 | In progress | New TM source tray swap out. | Monday, May 28, 2018, 08:45: Venting. Prep
For removal.
Close FS#8. Clean up water |
|
668
|
Tuesday, June 12, 2018, 11:38 |
Aaron Schmidt | | | | | | | In progress | Source Tray re-installation | Re-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect |
|
670
|
Thursday, June 21, 2018, 16:32 |
Anders Mjos | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Heating target | Thursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping |
|
671
|
Tuesday, July 03, 2018, 12:46 |
Aaron Schmidt | Ta#56 | HP-SIS | ITE | TM4 | 42218-9 | 42752-3 | In progress | Conditioning Ta#56 | Tuesday, July 03, 2018, 12:44: Roughing
Tuesday, July 03, 2018, 13:32: Turbo
pumps started. |
8x |
672
|
Monday, July 09, 2018, 10:44 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test July | Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on. |
|
673
|
Thursday, July 12, 2018, 08:24 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Power outage / restart | Power outage (07/11/2018 @ approx 21:53)
shut down the test stand.
|
|
674
|
Thursday, July 12, 2018, 10:11 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test #5 | *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened |
|
675
|
Monday, July 23, 2018, 14:25 |
Aaron Schmidt | UC#23 | LP-FEBIAD-CTL | ITE | TM2 | | | In progress | Conditioning Heat Shield for UC#23 | Monday, July 23, 2018, 14:20: Roughing.
Monday, July 23, 2018, 14:54: Turbo
pumps on. |
|
676
|
Friday, July 27, 2018, 14:44 |
Aaron Schmidt | UC#24 | LP-SIS | ITE | TM4 | 41177-3 | 42752-6 | In progress | Conditioning Heat Shield for UC#24 & voltage test prep | 4 Kapton wire routed into the 9-pin connector.
Unused pins are grounded on the bracket.
Friday, July 27, 2018, 14:25: Roughing |
|
683
|
Friday, August 31, 2018, 12:27 |
Aaron Schmidt | nSiC#1 | LP-SIS | ITW | TM2 | 43044-1 | 42752-4 | In progress | Conditioning nSiC#1 | Friday, August 31, 2018, 12:27: Roughing.
Friday, August 31, 2018, 13:19: Turbo
pumps started. |
15x |
684
|
Wednesday, September 12, 2018, 11:19 |
Aaron Schmidt | Ta#57 | LP-SIS | ITE | TM4 | 41177-3 | 42752-6 | In progress | Conditioning Ta#57 | Wednesday, September 12, 2018, 11:06: Roughing.
Help req'd. Doors wouldn't seal.
Wednesday, September 12, 2018, 11:52: |
9x |
685
|
Monday, September 17, 2018, 11:52 |
Aaron Schmidt | UC#25 | LP-SIS | ITW | TM2 | | 42752-9 | In progress | Conditioning Heat Shield for UC#25 | Monday, September 17, 2018, 11:47: Roughing*.
Doors not sealing, help acq'd
Monday, September 17, 2018, 11:51: |
|
686
|
Friday, September 21, 2018, 11:41 |
Aaron Schmidt | UC#26 | LP-IG-LIS | ITE | TM4 | | 42132-1 | In progress | Conditioning Heat Shield for UC#26 | Friday, September 21, 2018, 11:40: Roughing
Friday, September 21, 2018, 11:41:
Doors sealed for roughing. |
|
687
|
Tuesday, October 02, 2018, 13:39 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps w/ stoppage | Silver bolts used on Coil, TGHT, &
TBHT.
End caps in target |
|
688
|
Monday, October 15, 2018, 14:23 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps | Anode / Cathode BIAS PS polarity reversed
by John Chow. PS: Negative
Monday, October 15, 2018, 14:12: |
|
691
|
Monday, October 22, 2018, 11:07 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps | Restarted post power outage.
Water & Turbos on.
Monday, October 22, 2018, 10:55: |
|
694
|
Tuesday, November 06, 2018, 08:52 |
Aaron Schmidt | | | | | | | In progress | Pump down empty chamber | Tuesday, November 06, 2018, 08:50: Roughing
Tuesday, November 06, 2018, 08:51:
Doors sealed. |
|
|