232
|
Wednesday, January 10, 2018, 17:45 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 beam spot photos, M20BB moved to storage pit | The T2-MK2 target was moved from
the beamline to the hot cell on January 8th.
The field at 0.5m was 130mSv/hr. Photographs |
|
233
|
Thursday, March 22, 2018, 17:24 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Lab active sump released | The RH Lab active sump level reached
the high limit yesterday due to an overflow
of the ultrasonic cleaner in the Rad Waste |
|
234
|
Wednesday, March 28, 2018, 10:12 |
Isaac Earle | Standard Operation | Other | Other | Five waste pails moved to East Vault Tunnel for storage | Five 5 gallon metal pails with active
waste were moved from the Warm Cell to the
Cyclotron East Vault Tunnel today for long |
|
235
|
Friday, April 06, 2018, 15:05 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 target MRO | The following is a summary of MRO work
done on the T2-MK2 target during the 2018
shutdown:
|
|
243
|
Tuesday, August 28, 2018, 11:16 |
Isaac Earle | Standard Operation | Other | Other | South TNF Holding Tank water released | The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3. The tank contained |
|
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
|
262
|
Monday, April 06, 2020, 15:02 |
Isaac Earle | Standard Operation | Target 2 | M9 | M9 beam blocker returned to beamline | The M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask. The top flange o-ring was replaced |
|
271
|
Tuesday, November 24, 2020, 15:10 |
Isaac Earle | Standard Operation | Target 2 | Target | Additional targets added to T2-MK1 ladder | The following work on the T2-MK1
target was completed sporadically over the
last few months: |
|
273
|
Wednesday, March 31, 2021, 16:15 |
Matthew Gareau | Standard Operation | Target 1 | Target | T1-MK1 target exchange | March 29 Monday
- moved T1-MK1 target from beamline
to hotcell (field from target 15mSv/hr |
|
275
|
Wednesday, April 14, 2021, 14:30 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Lab Active Sump pumped out | The RH Lab Active Sump reached the
high level sensor at some point overnight
before the April 8th work day. Maico |
|
285
|
Wednesday, March 16, 2022, 14:16 |
Matthew Gareau | Standard Operation | Other | Cooling | T1/T2 water packages drained to B1A AWHT, tested, and released. Also solenoid valve SV1 broken | The T1/T2 water packages were drained
into the B1AAWHT (280L), the water was sampled
and tested by RPG, results included in elog. |
|
286
|
Wednesday, April 13, 2022, 12:31 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 moved: from target station to storage | The T2-MK2 target was moved from the target
station to the storage area (position 3).
Upon removal, it was measured with a pole |
|
287
|
Wednesday, April 13, 2022, 12:33 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK1 moved: from storage area to target station | The T2-MK1 target was moved from the storage
area (formerly position 4) to the target
station. Services were reconnected in order |
|
289
|
Wednesday, May 04, 2022, 11:27 |
Adam Newsome | Standard Operation | Target 2 | M9 | M9 and M20 Beam Blocker Actuation Test | The beam blockers for M9 and M20 were actuated,
and vacuum was monitored to ensure no disruptions.
Both actuation tests were successful. Motion |
|
291
|
Thursday, May 05, 2022, 14:39 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK1 and T2-MK1 profile monitor actuation test | The profile monitor actuation tests were
completed for T1 and T2. No abnormalities
were noticed in vacuum during either test. |
|
292
|
Wednesday, May 25, 2022, 10:15 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK2 moved from hot cell to storage area | The T1-MK2 target was moved from the hot
cell to the storage area, in position 5.
Note: manual nudging of the flask was required |
|
293
|
Wednesday, May 25, 2022, 10:16 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 moved: from storage location to hot cell | Target T2-MK2 was moved from the storage
location (formerly position 3) to the hot
cell in preparation for replacement of end |
|
299
|
Monday, August 22, 2022, 09:01 |
Adam Newsome | Standard Operation | Other | Active Sump | Active Sump Draining | On Aug. 18, 2022, Operations informed RH
group that an alarm activated for the full
status of the MHESA B1 RCR1 Lab holding tank. |
|
300
|
Tuesday, August 23, 2022, 14:36 |
Adam Newsome | Standard Operation | Other | Other | BL1A Holding Tank - Level Check | The water level inside the BL1A active
water holding tank was checked today (Aug.
23, 2022). The tank is essentially empty |
|
302
|
Thursday, September 15, 2022, 14:34 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 target elevations measurement | The target elevations measurement and beam
spot checks were completed on Sept. 15, 2022.
This was done after a July 2022 target exchange |
|