  210   Thursday, October 06, 2016, 12:16 Isaac EarleDevelopmentTarget 1ControlsExpansion Tank High Level Warning Added An expansion tank high level warning
has been added to the T1/T2 control system
under Work Request #4011.  The purpose
  
  217   Thursday, March 30, 2017, 09:48 Isaac EarleDevelopmentOtherControlsT1/T2 control system de-glitching & target ID changes The following changes were made to
the T1/T2 PLC control system:
- De-glitching system investigated
  
  218   Wednesday, April 05, 2017, 17:55 Isaac EarleDevelopmentOtherTargetT2 area devices alignment strategyA strategy for alignment of the T2 protect
monitor, T2 target, and T2 Collimator A was
discussed today and decided upon by Yuri
 Re__T2_target_and_protect_adjustment.pdf 
  220   Tuesday, April 11, 2017, 17:31 Isaac EarleDevelopmentTarget 2TargetT2-MK2 target MRO and alignment of T2 devicesThe following work was performed on
the T2-MK2 target assembly and the T2 Protect
assembly for maintenance purposes and to
 T2-MK2_-_2017.pdf 
  221   Friday, May 05, 2017, 15:09 Isaac EarleDevelopmentTarget 2TargetT2-MK2 beam spot check in hot cell On May 5th the T2-MK2 target was
moved to the hot cell for the purpose of
checking the beam spot on the Position 2
 T2MK2_Position_1_and_2_Exit.JPGT2MK2_Position_2_Entrance.JPGT2MK2_Position_2_Exit.JPGT2-MK2_profile_monitor_dislodged.JPG 
  227   Thursday, July 27, 2017, 09:34 Keith C NgDevelopmentOtherOthertest 2test 2   
  231   Thursday, December 07, 2017, 13:54 Isaac EarleDevelopmentOtherOtherWaste pails transferred from warm cell storage bunker to rad waste pitSix 5 gallon pails were transferred this
morning from a temporary storage bunker in
the Warm Cell to the Rad Waste Pit for long
 IMG_0102.JPGIMG_6285.JPGIMG_0102.JPGIMG_6285.JPG 
  252   Monday, June 24, 2019, 14:29 Isaac EarleDevelopmentTarget 1TargetT1 and T2 target alignment frames overhauledThe following work was completed on both
the T1 and T2 target alignment frames

    One of the short taper
 8x 
  258   Friday, February 28, 2020, 09:06 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand floor plate installed The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday. 
Prior to installation all 5 threaded inserts
 M9_service_stand_floor_plate_TB23351.png 
  260   Wednesday, March 11, 2020, 10:29 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand foot plate installed The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate.  A nominal gap between the plates
  
  263   Tuesday, June 09, 2020, 17:01 Isaac EarleDevelopmentOtherM9Cables and helium leak check line installed to M9 service stand The 10-pin thermal switch wire, 2-pin
steering wire for Q2, and a 1/4" copper
tube for remote helium leak check were installed
  
  264   Wednesday, June 10, 2020, 08:58 Isaac EarleDevelopmentOtherM9T2-M9 and M9-B1 flange scan data Laser tracker scan data from 2017
and 2019 attached as a backup.  Original
files from Beamlines Group who also keep
 2017-03-28_meson_hall_t2_with_import_of_2015_data.xit642019-25-01_meson_hall_t2_data.xit64 
  265   Friday, June 12, 2020, 13:54 Isaac EarleDevelopmentOtherM9M9 Q1Q2 water header installedThe Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400.
 2.jpg1.jpg 
  266   Tuesday, July 07, 2020, 13:22 Isaac EarleDevelopmentOtherM9M9 Q1Q2 The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401.  The side-to-side as well as
 8.jpg1.jpg4.jpg6.jpg 
  267   Tuesday, July 07, 2020, 15:13 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand Lemo connector wiringThe diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power
 Lemo_pin_wiring.PNG 
  268   Thursday, July 09, 2020, 06:44 Isaac EarleDevelopmentOtherM9Alignment of M9 Q1Q2 magnets complete Mike Vogel reported that alignment
of the Q1Q2 assembly w.r.t. the T2 and B1
flanges was completed on July 7.  This
  
  272   Wednesday, February 17, 2021, 10:39 Isaac EarleDevelopmentOtherUCNUCN Target Cask TestingA trial run of remote removal of the UCN
target was performed using the shielded target
cask (TTA0335) developed in 2020.  The
 8x 
  1   Wednesday, June 29, 2011, 15:27 John Wong   testblah blah blah....   