234
|
Wednesday, March 28, 2018, 10:12 |
Isaac Earle | Standard Operation | Other | Other | Five waste pails moved to East Vault Tunnel for storage | Five 5 gallon metal pails with active
waste were moved from the Warm Cell to the
Cyclotron East Vault Tunnel today for long |
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
243
|
Tuesday, August 28, 2018, 11:16 |
Isaac Earle | Standard Operation | Other | Other | South TNF Holding Tank water released | The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3. The tank contained |
|
245
|
Thursday, October 25, 2018, 08:58 |
Keith C Ng | Repair | Other | Other | T1 collimator valve solenoid coil replaced again | On
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after |
|
246
|
Thursday, November 01, 2018, 13:57 |
Keith C Ng | Other | Other | Other | nuclear venillation in hot cells not working | Randomly checked on the nuclear ventilation
for the Meson Hall Hotcells and discovered
they were not running again (both magnahelic |
|
248
|
Friday, January 25, 2019, 10:53 |
maicodallavalle | Repair | Other | Cyclotron electrical | Cyclotron Elevating system Motor electrical wire repairs | 2018 Cyclotron lid up problem. Station
#9 was found to have the motor
wires along the beam plain had damaged wire |
|
250
|
Tuesday, April 16, 2019, 15:35 |
Keith C Ng | Repair | Other | M9 | M9 project post shutdown summary | Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services. |
|
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
|
254
|
Monday, January 20, 2020, 16:07 |
Isaac Earle | Other | Other | Other | Second 55-gal drum moved to cyclotron east vault tunnel | The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today |
|
257
|
Monday, February 10, 2020, 14:51 |
Isaac Earle | Maintenance | Other | Other | T1-MK2 target and M9BB moved | The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit.
The M9 beam blocker was then moved from the |
|
258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
259
|
Wednesday, March 04, 2020, 13:42 |
Ron Kuramoto | Repair | Other | Other | B/L 1A vacuum air leak repair | A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This |
|
260
|
Wednesday, March 11, 2020, 10:29 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand foot plate installed | The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate. A nominal gap between the plates |
|
261
|
Monday, March 23, 2020, 16:13 |
Isaac Earle | Maintenance | Other | Other | M9 beam blocker MRO completed | M9 beam blocker MRO work was completed
in the hot cell today. This included
replacement of the main shaft seals and replacement |
|
263
|
Tuesday, June 09, 2020, 17:01 |
Isaac Earle | Development | Other | M9 | Cables and helium leak check line installed to M9 service stand | The 10-pin thermal switch wire, 2-pin
steering wire for Q2, and a 1/4" copper
tube for remote helium leak check were installed |
|
264
|
Wednesday, June 10, 2020, 08:58 |
Isaac Earle | Development | Other | M9 | T2-M9 and M9-B1 flange scan data | Laser tracker scan data from 2017
and 2019 attached as a backup. Original
files from Beamlines Group who also keep |
|
265
|
Friday, June 12, 2020, 13:54 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 water header installed | The Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400. |
|
266
|
Tuesday, July 07, 2020, 13:22 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 | The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401. The side-to-side as well as |
|
267
|
Tuesday, July 07, 2020, 15:13 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand Lemo connector wiring | The diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power |
|