|
ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
|
301
|
Wednesday, April 17, 2013, 09:26 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical check | Electrical check was performed on TM#3
with no target nothing was wrong was found,
but our megger does not go above 1000 volts |
|
|
300
|
Wednesday, April 17, 2013, 09:02 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 ready for conditioning station | The heat shield circuit blank offs have
been re-installed and front cover replaced.
TM3 is ready to move to the conditioning |
|
|
299
|
Tuesday, April 16, 2013, 11:20 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 Referb. start | Front containment box cover has been removed
and heat shield circuit blank offs removed
in preparation for installation of dummy |
|
|
298
|
Tuesday, April 16, 2013, 11:10 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 has been moved from the NE Silo to
the south hot cell, move went well. |
|
|
297
|
Monday, April 15, 2013, 11:00 |
chad fisher | South Hot-Cell | Standard Operation | TM3 | | Items for TM3 dummy target installation | New gaskets and fasteners have been inserted
into the south hot cell in preparation for
installing the dummy target onto TM3 tomorrow. |
|
|
296
|
Friday, April 12, 2013, 10:32 |
David Wang | ITW | Repair | TM1 | | ITW EXIT1 tank to module o-ring leak check. | I leak checked new installed ITW EXIT1
tank to module o-ring.No leak had been found
. Also ,TM1 primary vessel air to vacuum |
|
|
295
|
Friday, April 12, 2013, 10:27 |
David Wang | ITW | Standard Operation | TM1 | | I reconnected TM1 to ITW. | TM1 has been reconnected in ITW. Water
interlock check for TM1 is done. |
|
|
294
|
Thursday, April 11, 2013, 07:18 |
David Wang | Conditioning Station | Maintenance | TM1 | Ta#29 | helium pressure tested all water lines in TM1 at CS | On April 08th, all water lines in TM1 had
been helium pressure tested(70psi) at conditioning
station. No leak had been found. |
|
|
293
|
Tuesday, April 09, 2013, 09:06 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Ta#39 | Electrical check | TM#1 with Ta#39 has not passed it electrical
check again, while sitting at the conditioning
station at air. The readings have not been |
|
|
292
|
Monday, April 08, 2013, 16:16 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Ta #39 | Venting with Argon | TM1 started venting at 4:15 pm with
Argon. I will leave the valve open over night. |
|
|
291
|
Monday, April 08, 2013, 12:10 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Ta#39 | Electrical check | TM#1 with Ta#39 had the electrical check
done on it again it passed, changes this
time were the water lines were purged and |
|
|
290
|
Monday, April 08, 2013, 09:01 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Ta#39 | Electrical check | TM#1 with Ta#39 at the conditioning station,
has failed its electrical test see attached
pdf for details. Also while setting up for |
|
|
289
|
Thursday, April 04, 2013, 14:31 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Ta #39 | Roughing started |
|
|
|
288
|
Thursday, April 04, 2013, 12:07 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Ta #39 | Roughing started | Roughing started at 12:06. It was
believed there was a problem with the compressed
air but there was none, TM1 doesn't leak |
|
|
287
|
Thursday, April 04, 2013, 11:06 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#39 | module move | TM#1 with Ta#39 has been moved from the
south hot cell to the conditioning station
move went well. |
|
|
286
|
Wednesday, April 03, 2013, 14:39 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Electrical check | Electrical check on TM#1 with Ta#39 installed
at the south hot cell. Target passed the
electrical checks, see attached pdf for details. |
|
|
285
|
Wednesday, April 03, 2013, 13:28 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 installed | Ta#39 has been installed onto TM1. |
|
|
284
|
Wednesday, April 03, 2013, 12:26 |
David Wang | ITE | Maintenance | TM4 | Sic LIS/RFQ | Leak check on ITE TM4. | TM 4 had been leak check in ITE due to
relatively high PNG1 and IG1 readings.All
TM4 primary and secondary vessel air |
|
|
283
|
Wednesday, April 03, 2013, 10:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south west
silo to the south hot cell, move went well. |
|
|
282
|
Tuesday, April 02, 2013, 10:07 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 inserted into hot cell | Ta#39 has been inserted into the hot cell
in preparation for TM1 target change. |
|