Entry  Thursday, March 07, 2013, 08:35, Keith C Ng, M9, Repair, M9 T2 flange blank off 
Work on blank off of M9 T2 started: Cleared away blocks making up bagging bunker. R. Kuramoto took some initial photos of the M9 T2 area post Q1Q2 removal;
See Remote Handling network drive for photos.
G. Morris posted photos of M9 Q1Q2 just after removal from beam line 1A. Click here for link: http://trshare.triumf.ca/~gmorris/BL1A/M9/2013.3.5/
Entry  Tuesday, March 05, 2013, 14:15, Keith C Ng, M9, Maintenance, M9 Q1, 2 removal 7x
Removed M9 Q1 Q2 from beam line 1A via crane and transferred from beam line to radiation waste storage.
Magnet craned out of position in front of T2 monolith and then placed into bunker next to work site.
- Bunker pre-lined with plastic enough to envelope magnet.
Entry  Monday, March 04, 2013, 16:48, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 6x
Preparing for M9 Q1,2 move:
1. Re-arranged/organized cables on top of magnet.
Entry  Friday, March 01, 2013, 15:28, Keith C Ng, M9, Maintenance, Radadioactive Waste Pit Organizing 20130301_radwastepit_P1020865.JPG20130301_radwastepit_P1020869.JPG20130301_radwastepit_P1020873.JPG
Successfully stacked old m20 q2 q2 magnet assembly on top of old M9 Q1 Q2 magnet and M11 septum magnet. See photos.
- Done to create room for current m9 Q1,2 magnet.
- Used 6' remote handling bridge on north end of open pit for shielding.
Entry  Wednesday, February 27, 2013, 16:15, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, rad waste pit prep 
Radioactive waste pit uncovered, red barrel with unknown contents taken out for assessment. R. Ralea from RPG determined barrel was too active to be
removed from pit and therefore replaced into storage pit.
M. Kinakin took the aluminum samples from the two indium test rings and the stainless steel bolt taken from Q1 for analysis. Will return the stainless
Entry  Monday, February 25, 2013, 16:37, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, Q2 seal disassembly 7x
Removed Q2 15" indium seal ring, discovered seal contained rubber on both sides instead of indium.
- Some kind of oil residue seen at the bottom of the sealing ring and inside of the Q2 vacuum box. (Note: Oil residue was from downstream vacuum
roughing pumps. They were connected when T2 M9 joint was leaking. Oil got into the vacuum pump back streamed into the beam line.)
Entry  Friday, February 22, 2013, 17:27, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, Q2 joint dissassembly 20130222_m9q1q2remove_P1020840.JPG20130222_m9q1q2remove_P1020832.JPG20130222_m9q1q2remove_P1020831.JPG
M9 Q2 15" pin drive was removed and disconnected.
- Pin drive retention screw had to be completely removed to be able to remove pin drive completely.
- Had to make tools to remove pin drive and retention screw, see photos.
Entry  Thursday, February 21, 2013, 17:02, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, joint dissassembly 
CUALCW system water loss was not from 1A triplet. Q15 Q16 held static  pressure at 90 psi since 9 am until 17:00. Holding with very minimal  change in
pressure. Q14 reading 64 psi as of 17:00. D. Preddy informs all other systems leak tight.
 
Entry  Tuesday, February 19, 2013, 16:46, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130219_m9q1q2remove_IMG_0206.JPG
Determined M9 Q2 service stand supply connector was slowly leaking.
- Ball valve to the supply was leaking through allowing trace amounts of water through.
- System was bled again and pressure relieved, leak appears to have stopped.
Entry  Monday, February 18, 2013, 16:24, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, electrical and water disconnected 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG
Today, re-arranged electrical wiring on Q1 Q2 magnet away from Q2 indium joint. Cable bundles were bundled as neatly as possible.
- One of the klixon thermal switch wires broke off while the cable bundles were being organized. See photo.
 
Entry  Friday, February 15, 2013, 14:29, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG
Beam lines group purged M9 Q1 Q2 magnets and water lines in preparation of disconnecting water services to those magnets, done in morning.
- Note: Q15 protueus paddle wheel was replaced after finding it was worn
 
Entry  Thursday, February 14, 2013, 15:43, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG
Removed 8" rubber test rings from M9 T2 joint. Rings moved to RH warm cell. Radiation levels were 70 µSv on contact 1.7 µSv @ 1/2 m.
Entry  Wednesday, February 13, 2013, 15:49, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 
Local and remote leak checks on M9 T2 area were done today to confirm leak; Leak was still present at T2 M9 joint. M9 Q1 and Q2 power supply leads were
disconnected (C. Yee). Next task is to find the ground fault on the Q1 magnet.
Indium one piece blank off plate (TB22267) for blanking off assembly (TB22265) was submitted into shop today.
Entry  Friday, February 08, 2013, 15:31, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, site prepration 20130208_m9q1q2remove_IMG_0172.JPG20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG
Completed remote handling/shielding setup over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were 1.2 mSv/h. Shielding was built up to 20' level, same as the opposite side to minimize exposure.
Entry  Thursday, February 07, 2013, 16:02, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, site prepration 20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG20130207_m9q1q2remove_IMG_0165.JPG20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG
Started work on removing M9 Q1 Q2 magnets; area clean up and preparation, removing shielding above Q1 and Q2 and remote handling setup over magnet (moving
blocks).
 
Entry  Wednesday, February 06, 2013, 16:33, Keith C Ng, Primary Beamlines, Maintenance, t2 monolith measurements 20130206_t2alignmeas_IMG_0140.JPG20130206_t2alignmeas_IMG_0139.JPG
Beam lines took measurements of top of T2 using Leica Total Station. Required no crane activities over 1A blocks.
Entry  Tuesday, February 05, 2013, 16:12, Keith C Ng, Primary Beamlines, Maintenance, 1A triplet repair (ground fault) (Completed) 
Today: D. Preddy completed another power test on 1A Q14, 15, 16 after all iron/steel shielding was restored. Magnet power and steering supplies were
checked and O.K.ed. R. Kuramoto deems triplet repair job completed.
 
Entry  Monday, February 04, 2013, 16:04, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130204_tripletrepair_IMG_0129.JPG20130204_tripletrepair_IMG_0130.JPG20130204_tripletrepair_IMG_0132.JPG20130204_tripletrepair_IMG_0134.JPG20130204_tripletrepair_IMG_0133.JPG
Restored 1A triplet shielding and removed RH shielding.
 
1. Moved severed asymmetric steering cable on Q14 so as not to touch the coils underneath and the cover plate above it.
Entry  Friday, February 01, 2013, 14:15, Keith C Ng, Primary Beamlines, Maintenance, M9 Q1 Q2; storage pit assessment 20130201_radwastepit_P1020704.JPG20130201_radwastepit_P1020720.JPG20130201_radwastepit_P1020736.JPG20130201_radwastepit_RHB_5449.JPG
Uncovered radioactive waste storage pit to see contents. Assessing viability of moving contents inside to facilitate storage of M9 Q1 Q2 magnet. See
below for some photos.
Entry  Wednesday, January 30, 2013, 16:46, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130130_tripletrepair_P1020683.JPG20130130_tripletrepair_IMG_0123.JPG20130130_tripletrepair_P1020686.JPG20130130_tripletrepair_IMG_0118.JPG20130130_tripletrepair_P1020697.JPG
Cut and removed asymmetric steering cables from Q14 and 16, cables are no longer resting on magnet power bus bars.
 
Cut short sections left on magnet and connector block. North connector block left in place. Short cable section on magnet insulated with fiber