Message ID: 33     Entry time: Tuesday, February 05, 2013, 16:12
Author: Keith C Ng 
Category: Primary Beamlines 
Type: Maintenance 
Subject: 1A triplet repair (ground fault) (Completed) 

Today: D. Preddy completed another power test on 1A Q14, 15, 16 after all iron/steel shielding was restored. Magnet power and steering supplies were checked and O.K.ed. R. Kuramoto deems triplet repair job completed.

 

Tomorrow: B. Gasbarri and J. McKinnon want to take measurements of the T2 monolith to verify its position and compare with past data, no crane activities are to occur while this is being done.