Message ID: 55     Entry time: Wednesday, April 10, 2013, 16:20
Author: Keith C Ng 
Category: M9 
Type: Repair 
Subject: M9 T2 flange blank off 

Continued with work on T2 M9 exit port and area; Vacuum started after 13:00 hours (due to vacuum pump issues at T2). He leak checked flange at 14:30, determined to be He leak tight. Vacuum pressure as of 14:45 in T2 volume (1ACG7) was at 36mT.