Friday, November 06, 2020, 12:53, Aaron Schmidt, Nb#9, LP-SIS, ITW, TM2, 44508-2, 43515-4, In progress, Conditioning Nb#9 w/ P/S Target & Bracket 7x
|
Attached end plate parasitic / symbiotic target & PEEK assembly bracket.
Friday, November 06, 2020, 12:24: Roughing.
Friday, November 06, 2020, 12:53: TP1B on. |
Wednesday, May 26, 2021, 14:29, Aaron Schmidt, UC#33 (HS), LP-SIS, ITW, TM2, , 44378-3, In progress, UC#33 HS conditioning
|
HS waterlines were very tight to line up.
Wednesday, May 26, 2021, 14:29: Roughing.
Wednesday, May 26, 2021, 15:09: TP1B on. |
Wednesday, June 02, 2021, 10:45, Aaron Schmidt, UC#34 HS, LP-SIS, , TM2, 43044-13, 44378-1, In progress, UC#34 HS conditioning
|
Straight tube target / TGHT for outgassing.
Wednesday, June 02, 2021, 11:06: Roughing.
Wednesday, June 02, 2021, 12:15: TP1B on. |
Tuesday, September 14, 2021, 17:12, Aaron Schmidt, C#3, LP-SIS, ITW, TM2, 44691-7, 44378-11, In progress, C#3 Conditioning 6x
|
Tuesday, September 14, 2021, 17:00: Roughing
Tuesday, September 14, 2021, 17:37: TP1B on.
Tuesday, September 14, 2021, 17:47: TP1A on. |
Thursday, October 14, 2021, 10:13, Aaron Schmidt, , LP-SIS, ITW, TM2, , 44378-22, In progress, Conditioning UC#36 HS
|
Tube / TGHT only.
Thursday, October 14, 2021, 10:11: Roughing.
Thursday, October 14, 2021, 12:05: TP1B on. |
Tuesday, April 05, 2022, 14:01, Aaron Schmidt, Test FEBIAD TM2-2022, LP-FEBIAD, ITW, TM2, , 42752-5, , Test FEBIAD & TS operation
|
Tuesday, April 05, 2022, 13:57: Roughing. BV1B.
Tuesday, April 05, 2022, 14:04: BV1A on.
Tuesday, April 05, 2022, 14:28: TP1B on. |
Thursday, April 07, 2022, 11:19, Aaron Schmidt, Test FEBIAD TM2-2022, , ITW, TM2, , 42752-5, , Test FEBAID & TS operation
|
Gas system switched on manually to use Ar & calibrated leak.
Thursday, April 07, 2022, 10:25: Roughing.
Thursday, April 07, 2022, 11:17: TP1B on. |
Wednesday, May 25, 2022, 15:48, Aaron Schmidt, SiC#42, HP-FEBIAD, ITW, TM2, 44692-9, 44378-5, In progress, Conditioning SiC#42
|
Wednesday, May 25, 2022, 15:46: Roughing.
Wednesday, May 25, 2022, 16:21: TP1B on.
Wednesday, May 25, 2022, 16:38: TP1A on. |
Tuesday, May 31, 2022, 13:35, Aaron Schmidt, UCx HS, , ITW, TM2, , 44378-19, In progress, Conditioning UC#38 assembly
|
Using a broken LP-FEBIAD source. TGHT only.
Tuesday, May 31, 2022, 13:24: Roughing.
Tuesday, May 31, 2022, 13:54: TP1B on. |
Saturday, June 18, 2022, 10:04, Aaron Schmidt, SiC#43, HP-FEBIAD, ITW, TM2, 42464-1, 44378-16, In progress, Conditioning SiC#43
|
Note: SiC#42 replacement.
Saturday, June 18, 2022, 09:54: Roughing.
Saturday, June 18, 2022, 10:08: Data logger removed. Pins 4 & 5 grounded. Power on. |
Thursday, July 07, 2022, 16:52, Aaron Schmidt, , LP-IG-LIS, ITW, TM2, , 42132-3, In progress, Conditioning UC#39 assembly
|
No UCx target installed. Straight / blank oven in use for out gassing.
Thursday, July 07, 2022, 16:50: Roughing.
Thursday, July 07, 2022, 16:53: BV1A Open. |
Monday, April 17, 2023, 14:08, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6
|
Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on. |
Friday, May 05, 2023, 06:49, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6
|
Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B on. |
Thursday, July 06, 2023, 16:55, Aaron Schmidt, Nb#10, LP-IG-LIS, ITW, TM2, 45447-7, 42132-2, In progress, Conditioning Nb#10
|
Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B on.
Thursday, July 06, 2023, 16:47: TP1A on. |
Friday, August 25, 2023, 17:21, Aaron Schmidt, Nb#11, LP-IG-LIS, ITW, TM2, 45447-9, 42132-4, In progress, Conditioning Nb#11
|
Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum taking a while to rough down. Vacuum @ 1.034T. Opened FS#5. |
Monday, September 25, 2023, 16:31, Aaron Schmidt, Ta#66, LP-SIS, ITW, TM2, 45220-5, 45235-9, Done, Conditioning Ta#66 & HV Tests.
|
Thermocouples installed on the left end plate x 2.
Monday, September 25, 2023, 16:23: Roughing.
Monday, September 25, 2023, 16:51: TP1B on. |
Friday, September 20, 2024, 14:22, Aaron Schmidt, Ta#, LP-SIS, ITE, TM2, 45447-18, 45235-13, , Conditioning Ta#
|
https://elog.triumf.ca/TIS/Target+Production/146
Has not run through EVAP2.
Friday, September 20, 2024, 14:04: Roughing. |
Thursday, October 03, 2024, 16:26, Aaron Schmidt, Ta#68, HP-SIS, ITE, TM2, 45447-26, 45235-16 *, , Conditioning Ta#68
|
HS note:
Base# 45235-16
Lid# 39956-8 |
Wednesday, September 14, 2011, 15:33, John Wong, Test#1, HP-SIS, ITW, TM1, test, test, In progress, testing elog for test stand
|
Wednesday, September 14, 2011, 15:33
blah blah blah... |
Wednesday, September 14, 2011, 15:40, Anders Mjos, TaC#1, LP-SIS, ITE, TM1, 38634-6, 36833-6, In progress, TaC#1 installed and pumping down.
|
Wednesday, September 14, 2011, 15:39: Vacuum at 1.3e-5 torr
Thursday, September 15, 2011, 08:59: Vacuum at 2.9e-7 torr. Water flowing and vacuum stable. |
|