Test-Stand, Page 8 of 53 |
Not logged in |
|
|
Thursday, June 21, 2018, 16:32, Anders Mjos, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Heating target
|
Monday, July 09, 2018, 10:44, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Coil Test July
|
Thursday, July 12, 2018, 08:24, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Power outage / restart
|
Thursday, July 12, 2018, 10:11, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Coil Test #5
|
Tuesday, October 02, 2018, 13:39, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps w/ stoppage
|
Monday, October 15, 2018, 14:23, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps
|
Monday, October 22, 2018, 11:07, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps
|
Monday, October 29, 2018, 10:56, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Problems/Solutions, TS communications issues.
|
Monday, October 29, 2018, 11:03, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Done, Test FEBIAD w/ Silver bolts & sealed end caps
|
Friday, September 27, 2019, 11:54, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-6, , Conditioning UC#(29) HS
|
Wednesday, October 02, 2019, 13:42, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-9, In progress, Conditioning UC#(30) HS
|
Friday, November 01, 2019, 16:01, Fernando Maldonado, , LP-SIS, , , 41790-9, 43515-9 , In progress, Peek seal tests on UCx#30 HS
|
Friday, November 08, 2019, 14:21, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-9, In progress, Nitrogen Bottle leak test
|
Wednesday, February 12, 2020, 11:04, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-1, In progress, Conditioning HS
|
Monday, July 13, 2020, 14:52, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 43515-2, , UCx HS conditioning.
|
Tuesday, October 18, 2016, 13:29, Aaron Schmidt, Ta#50, LP-SIS, ITE, TM4, 41790-5, 41751-1, In progress, Conditioning Ta#50 9x
|
Friday, March 24, 2017, 14:43, Aaron Schmidt, Ta#51, LP-SIS, ITW, TM2, 41790-4, 41751-5, In progress, Conditioning Ta#51 9x
|
Monday, April 04, 2016, 11:33, Aaron Schmidt, , LP-SIS, , , 41790-2, 39956-8, In progress, Testing restraint insulator prototype
|
Wednesday, April 13, 2016, 13:03, Aaron Schmidt, , LP-SIS, , , 41790-2, 39956-8, , Testing restraint insulator prototype (2)
|
Thursday, July 22, 2021, 17:43, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD efficiency measurements
|
|