Entry  Wednesday, October 07, 2015, 11:16, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32.docx
Wednesday, October 07, 2015, 11:15: roughing
Wednesday, October 07, 2015, 12:09 Turbos started
Wednesday, October 07, 2015, 12:18: Turbos at speed. Vacuum at 1.7E-5 T
    Reply  Tuesday, October 13, 2015, 07:47, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32-2.docx
Target was pumped down on Friday.

Tuesday, October 13, 2015, 07:47: Opened water for HS. No response on RGA. Vacuum stable at 2.2E-7 T
Tuesday, October 13, 2015, 07:59: Gas lines open.
    Reply  Tuesday, October 13, 2015, 17:23, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32 SiC#32-3.docxEmittance.zipNeEfficiecy.xlsx
Tuesday, October 13, 2015, 17:22: Roughing
Tuesday, October 13, 2015, 18:07: Started turbos.
Tuesday, October 13, 2015, 18:15: Turbos at speed. Vacuum at 1.9E-5 T
Entry  Monday, May 12, 2014, 14:20, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, In progress, Conditioning SiC#30 SiC#30_Conditioning.docx
Monday, May 12, 2014, 14:14 : Roughing
Monday, May 12, 2014, 14:34: Starting turbos
Monday, May 12, 2014, 14:42 : Turbos at speed
Entry  Wednesday, May 31, 2023, 15:19, Aaron Schmidt, SiC#46, HP-SIS, , , 44692-2, 45235-6, In progress, Conditioning SiC#2023A (Spare, renamed SiC-23B) - No salts SiC#2023A_-_No_Salts.docx
(Spare HP-SIS SiC SiC-23B)
Wednesday, May 31, 2023, 15:18: Roughing.

Thursday, June 01, 2023, 07:30: TP1B on.  
Entry  Friday, September 02, 2016, 15:47, Aaron Schmidt, SiC#34, LP-IG-LIS, ITE, TM4, 39814-V2-1, 41751-9, , Conditioning SiC# 34 ER-580-270-m40.txtITE-TM4-SiC#34-LP-IG-LIS_Test_Stand.docxSiC#34.docxTS-2016-09-06-08-12.rga
Friday, September 02, 2016, 15:47: Roughing.
Friday, September 02, 2016, 16:18: Turbos started -AM
Friday, September 02, 2016, 16:28: Turbos at speed. Vacuum at 2.0E-5 T.
Entry  Monday, September 16, 2013, 17:07, Anders Mjos, NiO#2, HP-FEBIAD, ITE, TM3, 39530-6, 39069-4, Done, Conditioning NiO#2 take 2 
The GE on the Source tray and EE on the target was cleaned. The target will be conditioned again to verify if sparking has been reduced. Torque 120 in
lbs
Monday, September 16, 2013, 17:05: Roughing. The roughing pump is somewhat noisy.
Entry  Friday, November 06, 2020, 12:53, Aaron Schmidt, Nb#9, LP-SIS, ITW, TM2, 44508-2, 43515-4, In progress, Conditioning Nb#9 w/ P/S Target & Bracket 7x
Attached end plate parasitic / symbiotic target & PEEK assembly bracket.
Friday, November 06, 2020, 12:24: Roughing.
Friday, November 06, 2020, 12:53: TP1B on.
Entry  Friday, August 25, 2023, 17:21, Aaron Schmidt, Nb#11, LP-IG-LIS, ITW, TM2, 45447-9, 42132-4, In progress, Conditioning Nb#11 Nb#11_Conditioning.docx
Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum taking a while to rough down. Vacuum @ 1.034T. Opened FS#5.
Entry  Thursday, July 06, 2023, 16:55, Aaron Schmidt, Nb#10, LP-IG-LIS, ITW, TM2, 45447-7, 42132-2, In progress, Conditioning Nb#10 Nb#10_Conditioning.docx
Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B on.
Thursday, July 06, 2023, 16:47: TP1A on.
Entry  Friday, March 16, 2018, 08:15, Aaron Schmidt, Nb#8, HP-SIS, ITW, TM2, 38817-2, 42738-12, In progress, Conditioning Nb#08 6x
Friday, March 16, 2018, 08:42: Roughing.
Friday, March 16, 2018, 10:34: Turbo pumps started.
Friday, March 16, 2018, 10:40: Ion gauge on.
Entry  Friday, April 04, 2014, 17:01, Rick Maharaj, UC#9, LP-SIS, ITW, TM1, , 39230-3, Done, Conditioning Heatshield for UCx#9 
Friday, April 04, 2014, 16:26: Heatshield/Ionsource assembly for UC LP SIS  installed in test stand with Ta tube as heat load.
Friday, April 04, 2014, 16:29: Chamber roughing started
Friday, April 04, 2014, 16:51: Turbos started
Entry  Friday, May 05, 2017, 14:28, Aaron Schmidt, UC#20, LP-IG-LIS, , , , , , Conditioning Heat shield for UC#20 (2)  UC#20_Heat_shield_conditioning-2.docxTS-2017-05-05-17-11.rgaTS-2017-05-11-07-50.rga
New O-rings installed on FS#3.
Friday, May 05, 2017, 14:24: Roughing.
Friday, May 05, 2017, 14:34: Waterlines reconnected to air lines. He likely still in lines. May show in RGA if there's an issue prior to opening
Entry  Thursday, May 04, 2017, 13:49, Aaron Schmidt, UC#20, LP-IG-LIS, , , , , , Conditioning Heat shield for UC#20 (1) UC#20_Heat_shield_conditioning-1.docxTS-2017-05-05-07-35.rga
Thursday, May 04, 2017, 13:48: Roughing.
Thursday, May 04, 2017, 14:09: Turbos on.

Friday, May 05, 2017, 07:35: RGA on. Vacuum @ 1.56e-06T
Entry  Friday, March 10, 2017, 15:42, Aaron Schmidt, UC#19, , , , 41882-4, 41751-2, In progress, Conditioning Heat shield for UC#19 TS-2017-03-10-16-20.rgaOMEGA_OM-DAQPRO-5300_22-Mar-17_09.05.23.dlp
Friday, March 10, 2017, 15:40: Roughing.
Friday, March 10, 2017, 15:58: Turbo pumps started.
Friday, March 10, 2017, 16:19: Ion gauge on.
Entry  Thursday, October 27, 2016, 13:37, Aaron Schmidt, UC#18, LP-SIS, ITW, TM2, , 41751-3, In progress, Conditioning Heat shield for UC#18 UC#18_Heat_shield_conditioning.docxTS-2016-10-27-16-00.rga
Thursday, October 27, 2016, 13:36: Roughing.
Thursday, October 27, 2016, 14:27: Turbo pumps started.
Thursday, October 27, 2016, 14:33: Ion gauge on.
Entry  Wednesday, June 01, 2016, 10:02, Aaron Schmidt, UC#16, LP-IG-LIS, ITE, TM4, 39814-V2-1, , , Conditioning Heat shield for UC#16 OMEGA_OM-DAQPRO-5300_03-Jun-16_08.14.47.dlpTS-2016-06-02_UC#16.rgaTS-2016-06-02-13-46_UC#16.rgaUC#16.docx
Wednesday, June 01, 2016, 10:02: Begin roughing.
Wednesday, June 01, 2016, 10:44: Turbo pumps started.
Wednesday, June 01, 2016, 10:47: Ion Gauge IG1 ON.
Entry  Friday, September 21, 2018, 11:41, Aaron Schmidt, UC#26, LP-IG-LIS, ITE, TM4, , 42132-1, In progress, Conditioning Heat Shield for UC#26 TS-2018-09-21-14-53.rgaUC#26.docx
Friday, September 21, 2018, 11:40: Roughing
Friday, September 21, 2018, 11:41: Doors sealed for roughing.
Friday, September 21, 2018, 14:02: Turbos on.
Entry  Monday, September 17, 2018, 11:52, Aaron Schmidt, UC#25, LP-SIS, ITW, TM2, , 42752-9, In progress, Conditioning Heat Shield for UC#25 OMEGA_OM-DAQPRO-5300_24-Sep-18_08.08.26.dlpTS-2018-09-17-14-10.rgaUC#25.docx
Monday, September 17, 2018, 11:47: Roughing*. Doors not sealing, help acq'd 
Monday, September 17, 2018, 11:51: Roughing. Doors sealed
Monday, September 17, 2018, 12:30: Turbo pumps started.
Entry  Friday, July 27, 2018, 14:44, Aaron Schmidt, UC#24, LP-SIS, ITE, TM4, 41177-3, 42752-6, In progress, Conditioning Heat Shield for UC#24 & voltage test prep 
4 Kapton wire routed into the 9-pin connector. Unused pins are grounded on the bracket.
Friday, July 27, 2018, 14:25: Roughing
Friday, July 27, 2018, 14:41: Turbo pumps on.
ELOG V2.9.2-2455