Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 26 of 53  Not logged in ELOG logo
Entry  Monday, December 02, 2019, 16:01, Fernando Maldonado, , , , , , , In progress, Ferran irradiation copper end plate tests (aka MIST) 
Friday: Test to validate Ferran's assembly. The plan is to ramp up to operating current, apply high voltage, and possibly extract beam.
Turbos on. IG1. Power on.

Monday, December 02, 2019, 15:59: Auto-ramp to 230/600 A for TBHT/TGHT @ 2A/min and 4A/min  (0.5A/15 s 1 A/15s.)
Entry  Tuesday, January 21, 2020, 09:38, Aaron Schmidt, SiC#40, LP-SIS, , , 43044-8, 43515-8, In progress, Conditioning SiC#40 HS SiC#40.docxSiC#40_-_HS_Out_gassing.docxTS-2020-01-21-11-10.rga
Was intended for UC#31 - Now used for SiC#40*
PEEK SEAL Test piece attached.
Tuesday, January 21, 2020, 09:34: BV1A open Roughing.
Entry  Thursday, January 30, 2020, 15:25, Aaron Schmidt, C(#1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C(#1) HS C#1_-_Short.docx
Was for UC# 32* - Schedule change, now for C#1
Thursday, January 30, 2020, 15:13: Roughing.
Thursday, January 30, 2020, 15:46: Turbo pumps on.
Entry  Friday, February 07, 2020, 14:02, Aaron Schmidt, C#(1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C#(1) HS C#1_-_2.docx
Was for UC# 32* - Schedule change, now for C#1* - Last HS conditioning revealed a TGHT to HS lid short. Milled the lid back 1/8" - Aaron S.
Friday, February 07, 2020, 14:00: Roughing.
Friday, February 07, 2020, 14:33: Turbo pumps on.
Entry  Wednesday, February 12, 2020, 11:04, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-1, In progress, Conditioning HS UC#31.docx
Using a broken LP-FEBIAD oven for out gassing. Tentative UC#31*
Wednesday, February 12, 2020, 10:57: Roughing.
Wednesday, February 12, 2020, 11:30: Turbo pumps on.
Entry  Thursday, February 20, 2020, 11:41, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing 20200221_134828.jpg20200221_134939.jpgTa#60_-_TS_Pre-condition_-_EE_test_-_1.docx
 Ta#60 (Unconditioned) - Salts in.
Thursday, February 20, 2020, 14:04: Roughing.
Thursday, February 20, 2020, 14:38: Turbo pumps on (Leak check in am).
Entry  Monday, March 02, 2020, 14:42, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Full TS testing w/ HV using Ta#60 
Monday, March 02, 2020, 14:36: Roughing.
Monday, March 02, 2020, 15:08: Turbo pumps on.

Remove HV cage (top). Reroute FS#3 back to cool EE
Entry  Wednesday, March 11, 2020, 13:31, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing - 2 Ta#60_-_TS_Pre-condition_-_EE_Test_-_2.docx
Thermocouples installed on EE. Double checked continuity & used a heat gun.
Wednesday, March 11, 2020, 13:30: Roughing.
Wednesday, March 11, 2020, 15:03: Turbo pumps on, interlocks by-passed (No water at
Entry  Tuesday, March 17, 2020, 11:40, Aaron Schmidt, SiC#40, HP-SIS, ITW, TM2, 42218-8, 43515-8, In progress, Conditioning SiC#40 SiC#40_-_Conditioning.docxER-580-230-30kV-m7.txtER-580-230-30kV-m23.txtER-580-230-30kV-m38.txtITW-TM2-SiC#40-HP-SIS_Test_Stand.docx
Tuesday, March 17, 2020, 11:37: Roughing.
FS# 3 re-connected. All waterlines re-opened except FS#5 (HS cooling).
Tuesday, March 17, 2020, 12:08: Turbo pumps on.
Entry  Wednesday, June 10, 2020, 08:23, Aaron Schmidt, C#1, LP-SIS, ITW, TM2, 43044-8, 43515-3, In progress, Conditioning C#1 7x
Salts: 
Li - 10 uL
Na - 10 uL
Entry  Tuesday, June 16, 2020, 11:03, Aaron Schmidt, Ta#60, LP-SIS, ITW, TM2, 44139-13, 43515-5, In progress, Conditioning Ta#60  Ta#60_Conditioning.docxITW-TM2-Ta#60-LP-SIS_Test_Stand.docxER-580-230-30kV-m8.txtER-580-230-30kV-m40.txt
Tuesday, June 16, 2020, 11:01: Turbo pumps on.

Wednesday, June 17, 2020, 07:49: HS waterlines opened. Vacuum stable @ 2.07e-06T.
Wednesday, June 17, 2020, 07:51: Power / Sources on.
Entry  Monday, June 22, 2020, 07:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, Test FEBIAD (Fernando) FEBIAD_Testing_-_June_22_-_23.docxER-580-280-30kV-m28.txt
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
Monday, June 22, 2020, 08:45: Roughing.
Monday, June 22, 2020, 09:17: Turbo pumps on.
Entry  Monday, July 20, 2020, 11:40, Aaron Schmidt, (Empty-Test), , , , 44160-1, 43822-2, In progress, Conditioning Test P2N P2N_-_1_-_July-20-22-2020.docx
Salts added: 
Cs - 15 uL
Li - 10 uL
Entry  Wednesday, July 22, 2020, 08:56, Luca Egoriti, P2N test, HP-SIS, ITE, TM4, , , In progress, p2n heating test - electrical feedthrough configuration ISACteststand_TMwiring.pptxP2N-TestStand_20200722.pngP2N-TestStand_1200A.png
 The electrical feedthroughs at the top of the test stand module were reconfigured to deliver up to 1200A to the p2n target.
1) The two COIL lines (one + and one -) were disconnected from their terminals E and F
2) The TBHT terminals (two + and two -) were disconnected from A and B
Entry  Tuesday, August 04, 2020, 15:07, Aaron Schmidt, UCx, LP-SIS, , , 44139-10, 43515-4, In progress, UCx HS conditioning with PEEK assembly UCx_-_HS_w-PEEK_Assy_-_43515-4.docx
 Tuesday, August 04, 2020, 15:04: Roughing.

Wednesday, August 05, 2020, 06:08: Turbo pumps on. 

Thursday, August 06, 2020, 06:58: Vacuum @ 1.52e-06T
Entry  Tuesday, August 11, 2020, 12:04, Aaron Schmidt, UCx, LP-SIS, , , 44139-10, 43515-4, In progress, UCx HS conditioning with PEEK assembly 
HS target leg openings were milled. Short from previous test by the look of it. TBHT insulator on source side is cracked.
Wiring up top adjusted for better clearance. EE (K) Cap appears ok.
Tuesday, August 11, 2020, 12:03: Roughing.
Entry  Tuesday, August 18, 2020, 12:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, RP check & Mass magnet check. 
Tuesday, August 18, 2020, 12:05: RP1 on
Tuesday, August 18, 2020, 12:10: RP1 off
Install Gas Ballast vapour port w/ filter.
Entry  Thursday, September 03, 2020, 11:28, Aaron Schmidt, -, HP-FEBIAD, , , 38295-8, 42752-5, In progress, Leak check 2.0 
Out Gas & MB1 check (Or leak check 2.0)
Ref: https://elog.triumf.ca/TIS/Test-Stand/809 - Leak Checks
Ref: https://elog.triumf.ca/TIS/Test-Stand/803 - Fault
Entry  Wednesday, September 30, 2020, 06:23, Aaron Schmidt, C#2, LP-SIS, ITW, TM2, 44139-9, 43515-2, In progress, Conditioning C#2 C#2_-_Short_-_EZL.docxC#2_Conditioning.docxITW-TM2-C#2-LP-SIS_Test_Stand.docx
Wednesday, September 30, 2020, 06:14: Power / sources on.
Wednesday, September 30, 2020, 06:17: Auto-ramping TGHT / TBHT to 300 / 150 A @ 3 A per min.
Wednesday, September 30, 2020, 06:22: Optics set (minus MB1).
Entry  Tuesday, October 13, 2020, 12:34, Aaron Schmidt, , HP-FEBIAD, , , 38295-8, 42752-5, In progress, MB1 Check. MB1_Check_Oct_-_2020.docx
He & Ar calibrated leak bottles in.
Tuesday, October 13, 2020, 12:33: Roughing.
Tuesday, October 13, 2020, 13:17: TP1B on.
ELOG V2.9.2-2455