Tuesday, October 07, 2014, 09:32, Anders Mjos, , , , , , , In progress, Pumping down empty chamber
|
Tuesday, October 07, 2014, 09:30: Roughing
Tuesday, October 07, 2014, 10:24: Starting turbos
Tuesday, October 07, 2014, 10:32 : Turbos at speed. Vacuum at 3.3E-5 T |
Friday, October 31, 2014, 14:57, Anders Mjos, , LP-FEBIAD, , , Tube only, 38307-9, In progress, Test
|
Friday, October 31, 2014, 14:47: Starting turbos
Friday, October 31, 2014, 14:57: Turbos at speed. Vacuum at 2.9E-5 T
Monday, November 03, 2014, 10:08 : Opened HS water circuit. Vacuum stable at 1.7E-7 T
Monday, November 03, 2014, 10:22: Starting auto ramping to 228A on TBHT at 1 A/min
Monday, November 03, 2014, 13:44: Target at temperature. Opening IV4.
Monday, November 03, 2014, 14:45: IV4 closed
Monday, November 03, 2014, 15:00: Starting cool down. 1 A/min |
Friday, December 12, 2014, 14:09, Anders Mjos, , LP-FEBIAD, , , Tube only, , In progress, HV BIAS Test
|
BIAS current limit pot changed from 2.40 to 0.25
EZL current limit pot changed from 0.50 to 0.20
Testing max HV bias with Ray
Tested successfully to plc limit of 50kV.
Dave M updated limit to 59kV. the limit will reset to 50 kV if PLC is restarted
Friday, December 12, 2014, 14:43: BIAS at 59kV and 55 uA. EZL at 20kV and 73 uA. No sparking observed.
Tuesday, December 16, 2014, 09:12: BIAS and EZL to 40kV and 20kV
Tuesday, December 16, 2014, 09:53: BIAS at 50 kV. One spark w/vaccum response at 50 kV
Tuesday, December 16, 2014, 10:20: BIAS and EZL to 0 to try and restart TP1B TP6
Tuesday, December 16, 2014, 10:33: Both turbos restated. BIAS and EZL at 50 kV and 20 kV
Tuesday, December 16, 2014, 11:23: BIAS at 60 kV. One audible spark with vacuum response.
Tuesday, December 16, 2014, 11:37: Another spark took out TP1B and TP6 again.
Tuesday, December 16, 2014, 11:42: Restarted TP1B and TP6
EE power supply switched on
Wednesday, December 17, 2014, 10:19: BIAS at 60kV for 10 min. EZL at 20kV
Wednesday, December 17, 2014, 13:13 : 3h at 60 kV (see attached screen shot)
Wednesday, December 17, 2014, 13:24: BIAS off
Wednesday, December 17, 2014, 13:40: All power supplies ON. TBHT autoramping to 290 A (240 A0. 4A / min
Wednesday, December 17, 2014, 13:46: IV4 opened
Wednesday, December 17, 2014, 16:10: Source on at 30 kV (previously tested to 50 kV)
Thursday, December 18, 2014, 08:21 : Starget autoraming to 290 A (240 A). 4 A / min
Thursday, December 18, 2014, 08:48: 40 kV
Thursday, December 18, 2014, 08:57: 50 kV
Thursday, December 18, 2014, 09:18: 60 kV. Extracting 1E-7 A on FC0
Thursday, December 18, 2014, 09:29: Increased COIL and ANODE to 3.6 A and 60 V
Thursday, December 18, 2014, 10:11: Large spark? Vacuum in source box compromised 6E-4 T.
Thursday, December 18, 2014, 10:24: Closed IV4 (red, but closed - IG6 vacuum good). Stopping turbos. Vacuum is increasing on CG1.
Thursday, December 18, 2014, 10:26: Shutting off water supply.
Thursday, December 18, 2014, 10:29: Venting through turbo vent valves.
Thursday, December 18, 2014, 10:35: Closed turbo vent valves.
Thursday, December 18, 2014, 10:37: Roughing
Thursday, December 18, 2014, 10:42: Pumping curve changing slope abruptly around 30 T and again around 2.5 T
Thursday, December 18, 2014, 10:48: Stopped roughing
Thursday, December 18, 2014, 12:14 : Venting
Thursday, December 18, 2014, 13:43: Roughing
|
Wednesday, January 21, 2015, 13:40, Anders Mjos, , , , , , , In progress, HV BIAS Test
|
Wednesday, January 21, 2015, 13:34: Opened water flow.
Wednesday, January 21, 2015, 13:42: 30 / 15 kV (BIAS / EZL)
Wednesday, January 21, 2015, 13:4: 40 / 20 kV
Wednesday, January 21, 2015, 13:54: No sparks.
Wednesday, January 21, 2015, 13:56: 50 / 25 kV
Wednesday, January 21, 2015, 14:0: No sparks
Wednesday, January 21, 2015, 14:11: 55 / 30 kV
Wednesday, January 21, 2015, 14:45: No sparks
Wednesday, January 21, 2015, 14:47: 60 / 30 kV and 37 / 122 uA
Wednesday, January 21, 2015, 16:00: No sparks.
Wednesday, January 21, 2015, 16:02: PS off.
Thursday, January 22, 2015, 10:18 : Started TBHT heating
Thursday, January 22, 2015, 10:26: Opened isolation valve
Friday, January 23, 2015, 09:45: 30 / 15 kV
ANODE 200 V
COIL 0 A
EE -1400
Friday, January 23, 2015, 09:46: TBHT auto heating to 280 A (235)
Friday, January 23, 2015, 10:05
COIL 5.4 A 4.9 V
Friday, January 23, 2015, 10:13: 40 / 17 kV
Coil voltage limited. Reduced to 0 A - minimal impact on FC0 current.
Friday, January 23, 2015, 10:24: 50 / 22 kV
Friday, January 23, 2015, 10:42: 60 / 26 kV
Friday, January 23, 2015, 11:45: Sparking activity. Seen and heard by people in the area.
Friday, January 23, 2015, 12:00: Reduced current limit on BIAS PS to 0.10 (on the pot)
Friday, January 23, 2015, 12:04: A couple more sparks.
Friday, January 23, 2015, 12:05: Anode current limited since shortly after the large spark at 11:45
Friday, January 23, 2015, 12:11: 50 / 23 kV
Friday, January 23, 2015, 12:48 : Restarted turbos after the spark. TP1B and TP6
Friday, January 23, 2015, 13:16: 55 / 25 kV
Friday, January 23, 2015, 14:44: ~ 5 sparks / hour for the last 60 min
Friday, January 23, 2015, 15:49 : No sparks for the last 60 min. Cooling target.
Friday, January 23, 2015, 16:14: Source and HV off.
Monday, January 26, 2015, 11:15: TBHT at 235A set point
Tuesday, January 27, 2015, 10:13: Source on
Tuesday, January 27, 2015, 10:13: 30 / 15 kV
Tuesday, January 27, 2015, 10:59: COIL to 3.5 A
Tuesday, January 27, 2015, 11:15: 40 / 20 kV
Tuesday, January 27, 2015, 13:17: 50 / 23 kV
Tuesday, January 27, 2015, 16:56: No sparks for the last 3 h. 1 spark earlier.
Tuesday, January 27, 2015, 16:59 30 / 14 kV
Tuesday, January 27, 2015, 17:02: Cooling down target. Source and HV off. |
Tuesday, February 03, 2015, 14:33, Anders Mjos, Empty, LP-SIS, , , , , In progress, Target with new center block and new EE insulator
|
Also with newly installed RGA
Tuesday, February 03, 2015, 14:33: Roughing
Tuesday, February 03, 2015, 15:05: Turbos started
Tuesday, February 03, 2015, 15:15: Turbos at speed. Vacuum at 3.3E-5 T
Wednesday, February 04, 2015, 13:56: Cooling water on HS circuit on. No response on IG1 or on the RGA (water)
Thursday, February 05, 2015, 09:00: RGA started. Scan 1-100 every 5 min
Thursday, February 05, 2015, 09:02: Opened IV4
Thursday, February 05, 2015, 09:16: Started target heating to 500 / 150 A at 2 / 1 A/min
Thursday, February 05, 2015, 09:24: Opened electrical cage to switch on TGHT PS
Thursday, February 05, 2015, 09:26 : Started target heating to 500 / 150 A at 2 / 1 A/min
Thursday, February 05, 2015, 09:28: BIAS/EZL/EE on and at HV
Thursday, February 05, 2015, 13:21: TGHT voltage limited. Voltage limit increased to 7 V
Thursday, February 05, 2015, 13:53: Continue to 580 A
Thursday, February 05, 2015, 14:25: RGA stopped around 13:34. Started scanning again
Thursday, February 05, 2015, 15:08: Heating to 200 A on TBHT
Friday, February 06, 2015, 10:34: Heating TBHT to 220 A
Friday, February 06, 2015, 11:07: TBHT at 230 A. TGHT at 580 A
Friday, February 06, 2015, 11:50: Cooling down target
Friday, February 06, 2015, 11:56: RGA off
Friday, February 06, 2015, 11:5: BIAS/EZL/EE off
Tuesday, February 10, 2015, 11:34: BIAS/EZL/EE on. Started heating to 580 / 230 A at 4 / 2 A/min. RGA on
Monday, February 16, 2015, 08:46: BIAS/EZL/EE on
Monday, February 16, 2015, 09:13 : Started heating to 580 / 230 A at 4 / 2 A/min. RGA on
Monday, February 16, 2015, 10:10: Opened isolation valve
Monday, February 16, 2015, 14:23: TGHT was found voltage limiting at 7 V. Increased voltage limit to 7.2 V
Temperature read with digital optical pyrometer. Inside target 1800 - 1900 deg C. Outside 1900 - 2000 deg C
Monday, February 16, 2015, 15:50: Starting cool down
Tuesday, February 17, 2015, 08:30: RGA off
Tuesday, February 17, 2015, 08:32: BIAS/EZL/EE off. Isolation valve closed.
Tuesday, February 17, 2015, 08:34: Turbos off
Tuesday, February 17, 2015, 13:58: Venting |
Tuesday, February 17, 2015, 14:41, Anders Mjos, , , , , , , In progress, Pumping down empty chamber
|
Tuesday, February 17, 2015, 14:35: Roughing. Doors were difficult to get to seal.
Tuesday, February 17, 2015, 15:11: Started turbos
Tuesday, February 17, 2015, 15:34: Turbos at speed. Vacuum at 6.7E-6 T |
Thursday, February 26, 2015, 10:11, Anders Mjos, , , , , , , In progress, Installing FEBIAD test target for emittance rig tests
|
Thursday, February 26, 2015, 10:11: Stopped turbos
Thursday, February 26, 2015, 11:23: Venting
Thursday, February 26, 2015, 11:39: Stopped venting at 550 T. To be continued later
Thursday, February 26, 2015, 15:46: Started roughing. Doors needed a push.
Thursday, February 26, 2015, 16:23: Started turbos
Thursday, February 26, 2015, 16:39: Turbos at speed. Vacuum at 5.2E-6 T
Friday, February 27, 2015, 09:22: Water on. Vacuum stable at 1.6E-7 T
Friday, February 27, 2015, 09:30: RGA on
Friday, February 27, 2015, 10:32: HV on. Ramping to TBHT 250 A at 4A/min
Friday, February 27, 2015, 16:38: Source off
Monday, March 02, 2015, 14:00: Gas lines purged. Opening.
Fixed a air leak on one of the Swagelok joints.
Monday, March 02, 2015, 14:47: RGA with Ne Open
Total 3.5E0-7T, IG1 9.7E-8 T
20Ne 6.3E-10 T
22Ne 1.7E-10 T
Mass 18 1.6E-7 T
Tuesday, March 03, 2015, 09:58: Started heating
Tuesday, March 03, 2015, 16:33: Finished ER testing. First ER scans made on mass 4.
Wednesday, March 04, 2015, 14:32: TSG:CB1 found off. Switched back on.
Emittance vs EE voltage studied
Thursday, March 05, 2015, 09:02 : Ramping source back up to 285 A (TBHT)
Thursday, March 05, 2015, 15:12: The following devices were found off
TMS:Q6
TMSQ1
TPS:CBC
Friday, March 06, 2015, 08:51: Found TPS:Q3 off. Switched back on.
Friday, March 06, 2015, 10:51 : Ramping down source
Friday, March 06, 2015, 12:08 : Source and HV off. Closed IV.
Graham will be doing some controls work
Monday, March 09, 2015, 09:16: Ramping up the source. IV opened
Monday, March 09, 2015, 09:23: Source biased and optics tune recovered.
Monday, March 09, 2015, 16:51: Opened Ne leak
Wednesday, March 11, 2015, 09:06: Found TMS:Q6/Q1 and TPS:Q4 off. Switched back on.
Thursday, March 12, 2015, 16:57: Finished more ER data taking. See attached spreadsheet
Friday, March 13, 2015, 08:41 : TMS:CBC1, TMS:CB5, TMS:Q2, TPS:Q3, TPS:CB2 found off. Switched back on.
Monday, March 16, 2015, 09:13: TMS:CBC1, TMS:Q3, Q2, TMS:VCB1,CB1 found off.
Monday, March 16, 2015, 09:14: Bias off. Stopping turbos
Monday, March 16, 2015, 15:26: Venting |
Monday, March 16, 2015, 18:53, Anders Mjos, Ta#45, HP-SIS, ITE, TM4, 38817-5, , In progress, Conditioning Ta#45
|
Monday, March 16, 2015, 18:53: Started turbos
Monday, March 16, 2015, 19:00: Turbos at speed. Vacuum at 1.3E-5 T
Tuesday, March 17, 2015, 09:03: Opened cooling water. Vacuum stable at 1.9E-7 T
Tuesday, March 17, 2015, 09:12: Opened IV4. BIAS/EZL/EE to 30/14/1.5 kV
Tuesday, March 17, 2015, 09:20: Started heating TGHT/TBHT to 400/150 A at 2/1 A/min
Wednesday, March 18, 2015, 08:41: Continued heating TGHT/TBHT to 580/170 A at 2/1 A/min
Wednesday, March 18, 2015, 09:33: MB1 found tripped on water flow. Water pressure is low this morning as cyclotron main magnet was switched on, but not all water pumps. Expected to be resolved soon..
Some emittance scans at 170, 180, 190, 200 A TBHT were done
Thursday, March 19, 2015, 08:47: Heating TBHT to 220 A
Thursday, March 19, 2015, 08:56: Heating TBHT to 230 A
Thursday, March 19, 2015, 10:50: EE at -2000 V for 10 min
Thursday, March 19, 2015, 10:52: EE back at -1.5 kV
Thursday, March 19, 2015, 17:54: Started cool down of target
Friday, March 20, 2015, 08:47: Closed IV4
Friday, March 20, 2015, 08:47: RGA off.
Friday, March 20, 2015, 08:50: Stopped turbos
Friday, March 20, 2015, 10:24: Venting
Friday, March 20, 2015, 11:45: Target removed. |
Tuesday, March 24, 2015, 09:50, Anders Mjos, , , , , , , In progress, Empty chamber
|
Roughed down on Friday 20th
Tuesday, March 24, 2015, 09:49: Turbos started
Tuesday, March 24, 2015, 09:59: Turbos at speed. Vacuum at 2.8E-6 T
EPICS could not communicate with devices. Contacted controls (Dave M)
Thursday, April 02, 2015, 14:45: Stopped turbos.
Thursday, April 02, 2015, 15:10: Started venting through turbo pump (to 16 T)
Thursday, April 02, 2015, 15:12: Venting through VV1 |
Friday, April 24, 2015, 12:26, Anders Mjos, , LP-FEBIAD, , TM2, , 39230-1, In progress, Testing new TM2 Source Tray
|
Photos on DocuShare
Friday, April 24, 2015
The source tray has been installed and inspected.
Friday, April 24, 2015, 12:32: Roughing
Friday, April 24, 2015, 13:33: Starting turbos. Vacuum at 0.24 T
Friday, April 24, 2015, 13:42: Turbos at speed.
Friday, April 24, 2015, 13:43: 3.5E-5 T
Leak check performed with RGA and He pressurized on water line incl GE line to 50 psi. Doors and ANODE line blank off He sprayed. No response.
RGA response to He confirmed with FEBIAD gas leak.
Monday, April 27, 2015, 12:00: Ge water open.
Monday, April 27, 2015, 12:03: Water open
Monday, April 27, 2015, 15:07: Electrical check completed OK. Test results attached. Tested low voltage on EZL, CB1, VCB1, CBC, EE, ANODE and BIAS
Monday, April 27, 2015, 15:15: Turbos stopped. Colimator connected to HS lines (60 kV). Should be on GND potential.
Monday, April 27, 2015, 16:00: Roughing
Monday, April 27, 2015, 16:30: Starting turbos
Monday, April 27, 2015, 16:40: Turbos at speed. Vacuum at 1.8E-5 T
Tuesday, April 28, 2015, 09:46: Starting auto-ramping of heaters to 100 / 100 A at 2 A/min 3E-6 / 4E-6 T good/bad vacuum limits.
Tuesday, April 28, 2015, 10:38: Continue auto-ramping TGHT to 200 A
Tuesday, April 28, 2015, 11:15: Optics and steerers on.
Tuesday, April 28, 2015, 11:34: Continue auto-ramping TGHT to 250 A
Tuesday, April 28, 2015, 12:50: Continue auto-ramping TGHT/TBHT to 300 /150 A
Tuesday, April 28, 2015, 13:30: Continue auto-ramping TGHT/TBHT to 400 /200 A
Tuesday, April 28, 2015, 14:24: Continue auto-ramping TGHT/TBHT to 500 /250 A
Wednesday, April 29, 2015, 06:06: Starting auto-ramp down.
Wednesday, April 29, 2015, 09:09: ANODE to 200 V. No current.
Wednesday, April 29, 2015, 09:16 : ANODE to 300 V. No current.
Wednesday, April 29, 2015, 09:16: EE to 2kV. 691 uA
Wednesday, April 29, 2015, 09:17: ANODE off. EE to 1.5 kV
Wednesday, April 29, 2015, 09:20: BIAS/EZL at 5/5 kV
Wednesday, April 29, 2015, 09:26: BIAS/EZL at 7.5/5 kV
Wednesday, April 29, 2015, 09:32 : BIAS/EZL at 10/5 kV
Wednesday, April 29, 2015, 09:47: BIAS/EZL at 15/7.5 kV
Wednesday, April 29, 2015, 10:04: BIAS/EZL at 20/10 kV
Wednesday, April 29, 2015, 10:20: BIAS/EZL at 25/12.5 kV
Wednesday, April 29, 2015, 10:48: BIAS/EZL at 30/15 kV. 2 sparks in 10 min on BIAS
Wednesday, April 29, 2015, 10:54: No sparks for 10 min
Wednesday, April 29, 2015, 12:01: BIAS/EZL at 40/20 kV
Wednesday, April 29, 2015, 12:48: No spark for the last 15 min. 3 sparks in the last 30 min
Wednesday, April 29, 2015, 13:09: BIAS/EZL at 45/22.5 kV
Wednesday, April 29, 2015, 13:45: BIAS/EZL at 50/25 kV
Wednesday, April 29, 2015, 14:53: Sparking above 50 kV. Loosing EPICS communication.
Wednesday, April 29, 2015, 15:46: BIAS/EZL at 53/27.5 kV
Wednesday, April 29, 2015, 16:11: BIAS/EZL at 53/27.5 kV. No sparks for 15 min
Wednesday, April 29, 2015, 16:19: BIAS/EZL/EE off for today
Thursday, April 30, 2015, 08:37: BIAS/EZL at 40/20 kV. EE at 1.5 kV. IG1 at 7.1E-7 T
Thursday, April 30, 2015, 08:55: BIAS/EZL at 50/25 kV
Thursday, April 30, 2015, 09:10: 1 spark in the last 15 min
Thursday, April 30, 2015, 09:32: BIAS/EZL at 53/25 kV
Thursday, April 30, 2015, 09:42: No sparks for 10 min
Thursday, April 30, 2015, 09:53: BIAS/EZL at 54/25 kV
Thursday, April 30, 2015, 10:00: Sparking caused lost EPICS communication.Manually current limiting PS
Thursday, April 30, 2015, 10:25: BIAS/EZL at 53/25 kV
Thursday, April 30, 2015, 10:31: BIAS/EZL at 54/25 kV
Thursday, April 30, 2015, 10:47: BIAS/EZL at 55/25 kV
Thursday, April 30, 2015, 10:53: BIAS/EZL at 55/27.5 kV. No sparks for 5 min
Thursday, April 30, 2015, 10:57: No sparks for 10 min.
Thursday, April 30, 2015, 11:01: BIAS/EZL at 55/30 kV
Thursday, April 30, 2015, 11:17: No sparks for 30 min.
Thursday, April 30, 2015, 11:19: BIAS at 30 kV
Thursday, April 30, 2015, 11:36: ANODE to 200 V. COIL is limited in EPICS to 0A and 0V
Thursday, April 30, 2015, 11:41: Opened isolation valve
Thursday, April 30, 2015, 11:42: Autoramping heaters to 500 / 250 A at 4/2 A/min. Good vacuum 2E-6 T, bad vacuum 3E-6 T
Thursday, April 30, 2015, 12:01: No EZL sparks for 60 min
Thursday, April 30, 2015, 12:03: EZL to 14 kV
Thursday, April 30, 2015, 13:50: Continue ramping to 580 / 300 A at 1/1 A/min
Troubleshooting FEBIAD coil power supply
Thursday, April 30, 2015, 14:10: Pumping on gas lines.
Thursday, April 30, 2015, 14:18: Tripped heaters when opening gas line to vacuum.
Thursday, April 30, 2015, 14:20: Autoramping heaters 500 / 250 A at 6/3 A/min.
A large (water?) leak opened up with target close to max temperature. Water lines were pressurized in an attempt to identify the leaky line. The test yesterday were not conclusive and was repeated this morning with no He response. The vacuum did not improve over night.
Friday, May 01, 2015, 10:08: Venting
Left coil line removed.
Friday, May 01, 2015, 11:10: Roughing
Friday, May 01, 2015, 11:41: Started turbos
With the leak detector pumping on the left coil line, a large leak could be confirmed at the soldering site. |
Wednesday, May 13, 2015, 13:27, Anders Mjos, , LP-FEBIAD, , TM2, , 39230-1, In progress, Re-testing new TM2 Source Tray
|
NOTE: COIL PS is a 100 A supply, thus actual COIL current is 0.5x COIL set point.
Changed the FEBIAD connector blocks to have copper tubes exit below the block. Extended ANODE wire to allow it to be wrapped around Cu-tubes and keep it further away from the GE lines.
Wednesday, May 13, 2015, 13:45: Roughing
Wednesday, May 13, 2015, 14:13: Starting turbos
Wednesday, May 13, 2015, 14:23: Turbos at speed. Vacuum at 4.6E-5 T
Thursday, May 14, 2015, 09:27: He pressure tested waterlines to 70 psi He. No response on the RGA. Vacuum 3.3E-6 T
Thursday, May 14, 2015, 09:39: Opened water supply. No increase on the RGA or IG
Thursday, May 14, 2015, 10:04: Tested COIL to 50 A set point (= 25 A). Returned to 0 A.
Thursday, May 14, 2015, 10:09: Auto-ramping to 400 / 200 A at 4 / 2 A/min. Good/Bad vacuum 4E-6 / 5E-6 T
Thursday, May 14, 2015, 13:59: COIL at 50 A
Thursday, May 14, 2015, 21:57 : Starting cool down.
Friday, May 15, 2015, 06:25: Stopped turbos
Friday, May 15, 2015, 07:42 : Venting
C-seals installed.
Friday, May 15, 2015, 13:56: Roughing
Friday, May 15, 2015, 14:28 : Staring turbos
Friday, May 15, 2015, 14:38: Turbos ate speed. Vacuum at 3.9E-5 T
Tuesday, May 19, 2015, 07:31: Vacuum at 7.1E-7 T. Pumping on gas lines
Tuesday, May 19, 2015, 07:35: Water lines opened. Vacuum stable at 7.1E-7 T. No response on RGA
Tuesday, May 19, 2015, 07:43: Opened gas lines (SV5)
Tuesday, May 19, 2015, 07:47: Auto-ramping to 400 / 200 A at 4 / 2 A/min. Good/Bad vacuum 2E-6 / 4E-6 T
Tuesday, May 19, 2015, 08:46: ANODE and COIL to 200 V and 50 A
Tuesday, May 19, 2015, 09:39: Auto-ramping to 500 / 250 A at 2 / 1 A/min. Good/Bad vacuum 2E-6 / 4E-6 T
Tuesday, May 19, 2015, 10:54: Opened IV4
Tuesday, May 19, 2015, 11:14: Atuo-ramping to 270 A. BIAS/EZL/EE at 30 / 15 / 1.5 kV
Tuesday, May 19, 2015, 11:42: BIAS/EZL/EE to 20 / 10 / 1.5 kV
Wednesday, May 20, 2015, 09:55: Auto-ramping to 500 / 250 A at 4 / 2 A/min. Good/Bad vacuum 2E-6 / 4E-6 T
Wednesday, May 20, 2015, 09:57: BIAS/EZL/EE at 30 / 15 / 1.5 kV
Wednesday, May 20, 2015, 11:57: Auto-ramping to 580 / 290 A at 2 / 1 A/min.
Wednesday, May 20, 2015, 12:55: Vacuum excursion during beam tuning. Stopped turbos.
A leak was observed on the left coil conductor again. After inspecting the service cap, it was found that there was no water flow going through the left coil line due to differences in routing between the TM2 and the Test Stand source tray. A new coil line will be made and the water and electrical connections on the service cap will be reconfigured. |
Thursday, May 21, 2015, 17:26, Anders Mjos, , LP-FEBIAD, , TM2, , , In progress, Re-testing new TM2 Source Tray
|
Thursday, May 21, 2015, 17:26: Roughing
Thursday, May 21, 2015, 18:02: Turbos started
Thursday, May 21, 2015, 18:12: Turbos at speed. Vacuum at 4.7E-5 T
Friday, May 22, 2015, 08:00: Opened water. Vacuum stable at 3.4E-6 T. No response on RGA
Friday, May 22, 2015, 08:10: Pumping on gas line
Friday, May 22, 2015, 08:21: Opened gas line.
Friday, May 22, 2015, 08:30: Auto-ramping to 500 / 250 A at 4/2 A/min. Good/bad vacuum 4E-6 and 5E-6 T
Friday, May 22, 2015, 08:35: BIAS/EZL/EE to 10 / 10 / 1.5 kV. COIL 50 A, ANODE 200 V
Friday, May 22, 2015, 12:16: Opened IV4
Friday, May 22, 2015, 14:59: BIAS/EZL/EE to 30 / 15 / 1.5 kV
Friday, May 22, 2015, 15:29 : Auto-ramping to 580 / 270 A at 2/1 A/min.
Saturday May 23 15:10 TGHT: 7.51 V 580 A, TBHT: 2.23 V 270 A, ANODE 200 V 13.4 mA, FC0 1.5e-8 A, IG1 1.9e-6 T, COIL 0 V 0 A not responding, some bias sparking over last 7 hours
Monday, May 25, 2015, 09:07: EE current limiting. Started auto-cool down at 4/2 A/min. Vacuum 1.2E-6 T
Monday, May 25, 2015, 09:37: BIAS and EZL to 0
Monday, May 25, 2015, 10:34 : Closed IV4
Monday, May 25, 2015, 11:56 : Cool down complete. Stopped turbos.
Monday, May 25, 2015, 13:17: Venting
Monday, May 25, 2015, 13:25: HS cooling circuit purged.
Monday, May 25, 2015, 14:25: The EE water line was found to be touching the COIL lines on the source tray. |
Monday, May 25, 2015, 14:40, Anders Mjos, SiC#31, HP-SIS, ITW, TM4, 38817-7, , In progress, SiC#31 Conditioning
|
Monday, May 25, 2015, 14:35: Rouging
Monday, May 25, 2015, 15:05: Turbos started.
Monday, May 25, 2015, 15:15: Turbos at speed. Vacuum at 2.4E-5 T
Tuesday, May 26, 2015, 07:45: Opened water circuit for HS line. Vacuum stable at 6.3E-7 T. No response on RGA
Tuesday, May 26, 2015, 07:50: Autoramping to 500/200 A at 2/1 A/min. Good vacuum 2E-6, bad vacuum 4E-6 T
Tuesday, May 26, 2015, 07:52: IV4 open
Tuesday, May 26, 2015, 13:15: Continue auto-ramping to 580 A
Tuesday, May 26, 2015, 13:48: BIAS/EZL/EE 30 / 15 / 1.5 kV
Tuesday, May 26, 2015, 17:29: ~6 sparks/hour
Wednesday, May 27, 2015, 08:14: A couple of sparks over night.
Wednesday, May 27, 2015, 09:23: Autoramping TBHT to 220 A
Wednesday, May 27, 2015, 09:41: Found FC0 and FC6 bias to be off
Wednesday, May 27, 2015, 09:42: Autoramping TBHT to 230 A
Wednesday, May 27, 2015, 10:30: EE to 2 kV
Wednesday, May 27, 2015, 10:37: Starting cool down at 4/2 A/min
Wednesday, May 27, 2015, 10:40: EE to 1.5 kV
Wednesday, May 27, 2015, 12:37 : BIAS/EZL/EE OFF
Wednesday, May 27, 2015, 12:37 : IV4 closed
Wednesday, May 27, 2015, 13:02: Stopped turbos
Wednesday, May 27, 2015, 13:41: Venting |
Wednesday, May 27, 2015, 14:19, Anders Mjos, , LP-FEBIAD, , TM2, , , In progress, Re-testing new TM2 Source Tray
|
Wednesday, May 27, 2015, 14:19: Roughing
Wednesday, May 27, 2015, 14:50: Turbos started
Wednesday, May 27, 2015, 15:00: Turbos at speed. Vacuum at 1.6e-5 T
Thursday, May 28, 2015, 08:13: Water opened on HS line. Vacuum stable at 4.3E-7 T. No response on RGA
Thursday, May 28, 2015, 08:17: Pumping on gas line.
Thursday, May 28, 2015, 08:37: Open gas lines.
Thursday, May 28, 2015, 08:50: Started auto-ramping to 500 / 250 A at 4/2 A/min.
Thursday, May 28, 2015, 08:55: ANODE 200 V, COIL 50 A
Thursday, May 28, 2015, 08:52: Opened IV4
Thursday, May 28, 2015, 09:01: BIAS/EZL/EE to 30 / 15 / 1.5 kV
Thursday, May 28, 2015, 10:56: Continue auto-ramping to 580/290 A at 2/2 A/min
Thursday, May 28, 2015, 13:01: Ramping TBHT to 300 A
Friday, May 29, 2015, 08:23: ANODE current limited. Increased limit to 125 uA
Friday, May 29, 2015, 08:25: TPS:Q1 and Q4 found to be off. Switched back on
Friday, May 29, 2015, 14:38: Starting cool down of source.
Friday, May 29, 2015, 15:34: Close IV4
Friday, May 29, 2015, 15:36: BIAS/EZL/EE, COIL and ANODE off
Monday, June 01, 2015, 08:23: Vacuum at 2.8E-7 T. BIAS/EZL to 30 / 15 kV
Monday, June 01, 2015, 08:37: BIAS/EZL to 40 / 20 kV
Monday, June 01, 2015, 09:05: BIAS/EZL to 50 / 25 kV
Monday, June 01, 2015, 09:17: BIAS/EZL to 40 / 20 kV (target hand over to RH)
Monday, June 01, 2015, 09:50: BIAS/EZL to 50 / 25 kV
Monday, June 01, 2015, 10:08: BIAS/EZL to 55 / 25 kV. No sparks so far.
Monday, June 01, 2015, 10:28: EZL to 30 kV
Monday, June 01, 2015, 11:03: 2 sparks last 30 min
Monday, June 01, 2015, 11:48: 5 BIAS sparks last 80 min
Monday, June 01, 2015, 11:49: BIAS /EZL/ EE off
Monday, June 01, 2015, 15:38: Stopped TP1B for out-gassing measurement tomorrow.
Tuesday, June 02, 2015, 10:28: Stopped TP1A.
Tuesday, June 02, 2015, 13:57: Water lines purged. GE line closed (not purged).
Wednesday, June 03, 2015, 08:25: Venting |
Monday, June 15, 2015, 14:09, Anders Mjos, ZrC#7, LP-SIS, , TM2, 41177-1, , In progress, ZrC#7 Conditioning
|
Monday, June 15, 2015, 14:05 Roughing
Monday, June 15, 2015, 14:39: Turbos started.
Monday, June 15, 2015, 14:49: Turbos at speed. Vacuum at 5.3E-5 T
Tuesday, June 16, 2015, 10:14: Water lines leak checked and water opened.
TBHT p/s did not come on yesterday after PLC upgrade. Solved this morning by Dave M.
Wednesday, June 17, 2015, 09:56: BIAS/EZL/EE to 20 / 10 / 1 kV
Wednesday, June 17, 2015, 09:58: Atuo-ramping to 500 / 170 A at 2/1 A/min. Good/Bad Vac 4E-6 / 6E-6 T
Wednesday, June 17, 2015, 23:11 : Stopped auto-ramping at 342 / 170 A. Vacuum at 4E-6 T
Thursday, June 18, 2015, 08:59: Resuming auto-ramping. Vacuum at 3.3E-6 T
Thursday, June 18, 2015, 11:25: Good/Bad Vac 6E-6 / 8E-6 T.
Thursday, June 18, 2015, 14:59: TBHT to 180 A. BIAS/EZL/EE to 30 / 14 / 1.5 kV
Friday, June 19, 2015, 08:21: Ramping TBHT to 200 A
Friday, June 19, 2015, 08:40: EZL 13.4 kV
Friday, June 19, 2015, 11:30: Atuo-ramping to 580 A
Friday, June 19, 2015, 11:48: Stopped auto-ramping at 540 A. 8.4 V
Friday, June 19, 2015, 13:30: TGHT / TBHT at 580 / 220 A
Friday, June 19, 2015, 16:12: Cool down started. at 4 / 2 A/min
Friday, June 19, 2015, 17:57: BIAS / EZL / EE off
Friday, June 19, 2015, 17:57: Closed IV4. Timed out.
Monday, June 22, 2015, 08:57 : Stopped turbos
Monday, June 22, 2015, 13:02: Venting. Had to bypass interlocks as IV4 is timed out. |
Monday, June 22, 2015, 15:49, Anders Mjos, , , , , , , In progress, Installed new 9-pin feed through
|
No wires connected yet.
Monday, June 22, 2015, 15:48: Roughing
Tuesday, June 23, 2015, 09:05: Roughing vacuum does not go below 0.9 T. Venting to investigate.
Tuesday, June 23, 2015, 10:16: Turbos started at 0.9 T
Tuesday, June 23, 2015, 10:276: Turbos at speed. Vacuum at 7.5E-4 T
Tuesday, June 23, 2015, 10:32: Stopped turbos
Tuesday, June 23, 2015, 11:01: Venting
Tuesday, June 23, 2015, 11:22: Roughing
Tuesday, June 23, 2015, 13:37: Venting
Tuesday, June 23, 2015, 16:48: Leak found on the newly installed f/t.
Wednesday, June 24, 2015, 09:29: Venting
Replaced f/t with a blank off.Installed TM2 FEBIAD test target
Wednesday, June 24, 2015, 10:31: Roughing
Wednesday, June 24, 2015, 11:07: Started turbos.
Wednesday, June 24, 2015, 11:17: Turbos at speed. Vacuum at 3.3E-5 T
Thursday, July 09, 2015
Installed the fixed f/t. |
Tuesday, June 30, 2015, 14:51, Anders Mjos, ZrC#7, LP-SIS, , TM2, 41177-2, , In progress, ZrC#7 Conditioning 2
|
Tuesday, June 30, 2015, 14:51: Roughing
Tuesday, June 30, 2015, 16:14: Started turbos. CG1 at 0.075 T
Tuesday, June 30, 2015, 16:23 : Turbos at speed. Vacuum at 1.4E-5 T
Thursday, July 02, 2015, 09:05: RGA on. Opened water for HS line. Vacuum stable at 4.6E-7 T. No response on RGA
Thursday, July 02, 2015, 09:06: IV4 opened
Thursday, July 02, 2015, 09:08: Staring auto-ramping heaters to TGHT / TBHT 300 A / 100 A at 2 / 1 A/min
Thursday, July 02, 2015, 11:22 : BIAS/EZL/EE to 20 / 10 1.5 kV
Thursday, July 02, 2015, 11:46: Continue heating to 400 / 150 A
Thursday, July 02, 2015, 13:48 : BIAS/EZL to 30 / 13 kV. Heating continued from 13:05.
Thursday, July 02, 2015, 15:55: EE held at 2 kV for 10 min. Current stable at 684 uA
Thursday, July 02, 2015, 15:55: EE back to 1.5 kV at 510 uA
Thursday, July 02, 2015, 20:06 : Starting cool down
Friday, July 03, 2015, 08:31: Closed IV4
Friday, July 03, 2015, 08:33: HV and source off
Monday, July 06, 2015, 11:04: Turbos stopped
Monday, July 06, 2015, 14:01: Venting |
Monday, July 13, 2015, 17:19, Anders Mjos, , LP-SIS, , , , , In progress, SIS Cup insulator clamping test
|
Monday, July 13, 2015, 17:09: Roughing
Monday, July 13, 2015, 17:51: Turbos started
Monday, July 13, 2015, 18:01: Turbos at speed. Vacuum at 3.7E-5 T
Tuesday, July 14, 2015, 09:05: Opened HS water. No response on IG or RGA.
Tuesday, July 14, 2015, 09:12: Started auto-ramping to 300 / 150 A
Tuesday, July 14, 2015, 14:46: TGHT at 400 A, TBHT at 150 A. HS 27 C, SIS cup 76 C
Wednesday, July 15, 2015, 13:57: TGHT 580, TBHT 200. HS 20, SIS cup 120 C
Wednesday, July 15, 2015, 15:08: TBHT 220 A. HS 20, SIS Cup 133 C
Wednesday, July 15, 2015, 15:08: Started ramping down heaters.
Thursday, July 16, 2015, 08:52: Turbos stopped.
Thursday, July 16, 2015, 10:24: Venting
Reconfigured target to no clamping (standard SIS Cup configuration)
Thursday, July 16, 2015, 11:41: Roughing
Thursday, July 16, 2015, 13:40: Turbos started.
Friday, July 17, 2015, 08:47: Opened S water. No response on IG or RGA.
Friday, July 17, 2015, 08:51 : Started auto-ramping to 580 / 220 A
Friday, July 17, 2015, 13:30: TGHT at 560 A, TBHT at 220 A. HS 25 C, SIS cup 514 C
Friday, July 17, 2015, 14:10: TGHT at 580 A, TBHT at 220 A. HS 23 C, SIS cup 530 C
Friday, July 17, 2015, 15:56: Starting cool-down
Monday, August 10, 2015, 08:43: Turbos stopped. Vacuum at 2.9E-7 T
Monday, August 10, 2015, 14:42: Venting |
Monday, August 10, 2015, 18:01, Anders Mjos, , LP-SIS, , , , , In progress, Testing new center block target
|
Installed thermocouples:
T1: TGHT tube left side, inside
T2: TBHT restraint
T3: Centre block top, outside
Monday, August 10, 2015, 18:01: Turbos started
Monday, August 10, 2015, 18:11 : Turbos at speed. Vacuum at 1.5E-5 T
Tuesday, August 11, 2015, 09:04: Opened water for HS. Vacuum stable at 5.2E-7 T. No response on RGA
Tuesday, August 11, 2015, 09:09 : Started auto-ramping to 250/100 A at 2/1 A/min.
Tuesday, August 11, 2015, 11:45: T1 857 C, T3 206 C (T2 no signal)
Tuesday, August 11, 2015, 11:45: Continue auto-ramping to 580/200 A.
Tuesday, August 11, 2015, 15:30: T1 1467, T3 816 at 580/230 A
Tuesday, August 11, 2015, 15:40: Starting cool down.
Wednesday, August 12, 2015, 09:40: Stopped turbos.
Wednesday, August 12, 2015, 13:20: Venting
The Centre block t/c was touching the TBHT terminal. Bent the t/c away from the TBHT terminal
Wednesday, August 12, 2015, 14:05: roughing
Wednesday, August 12, 2015, 14:48: Started turbos
Thursday, August 13, 2015, 09:06: Opened water for HS. Vacuum stable at 3.8E-7 T. No response on RGA
Thursday, August 13, 2015, 09:06: Started auto-ramping to 250/100 A at 2/1 A/min.
Thursday, August 13, 2015, 10:09: Aborting auto-ramping. Starting cool down. T/C shorts centre block to HS and may affect TGHT/TBHT current.
Thursday, August 13, 2015, 11:17: Turbos stopped. |
Wednesday, September 09, 2015, 08:54, Anders Mjos, , , , , , , In progress, Venting
|
Wednesday, September 09, 2015, 08:53: Turbos stopped
Friday, September 11, 2015: Vented |
|