Message ID: 457     Entry time: Monday, July 13, 2015, 17:19
Author: Anders Mjos 
Target/No.#:  
Source: LP-SIS 
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: In progress 
Subject: SIS Cup insulator clamping test 

Monday, July 13, 2015, 17:09: Roughing

Monday, July 13, 2015, 17:51: Turbos started

Monday, July 13, 2015, 18:01: Turbos at speed. Vacuum at 3.7E-5 T


Tuesday, July 14, 2015, 09:05: Opened HS water. No response on IG or RGA.

Tuesday, July 14, 2015, 09:12: Started auto-ramping to 300 / 150 A

Tuesday, July 14, 2015, 14:46: TGHT at 400 A, TBHT at 150 A. HS 27 C, SIS cup 76 C


Wednesday, July 15, 2015, 13:57: TGHT 580, TBHT 200. HS 20, SIS cup 120 C

Wednesday, July 15, 2015, 15:08: TBHT 220 A. HS 20, SIS Cup 133 C

Wednesday, July 15, 2015, 15:08: Started ramping down heaters.


Thursday, July 16, 2015, 08:52: Turbos stopped.

Thursday, July 16, 2015, 10:24: Venting

Reconfigured target to no clamping (standard SIS Cup configuration)

Thursday, July 16, 2015, 11:41: Roughing

Thursday, July 16, 2015, 13:40: Turbos started.


Friday, July 17, 2015, 08:47: Opened S water. No response on IG or RGA.

Friday, July 17, 2015, 08:51 : Started auto-ramping to 580 / 220 A

Friday, July 17, 2015, 13:30: TGHT at 560 A, TBHT at 220 A. HS 25 C, SIS cup 514 C

Friday, July 17, 2015, 14:10: TGHT at 580 A, TBHT at 220 A. HS 23 C, SIS cup 530 C

Friday, July 17, 2015, 15:56: Starting cool-down


 Monday, August 10, 2015, 08:43: Turbos stopped. Vacuum at 2.9E-7 T

Monday, August 10, 2015, 14:42: Venting