Monday, March 16, 2015, 18:53: Started turbos
Monday, March 16, 2015, 19:00: Turbos at speed. Vacuum at 1.3E-5 T
Tuesday, March 17, 2015, 09:03: Opened cooling water. Vacuum stable at 1.9E-7 T
Tuesday, March 17, 2015, 09:12: Opened IV4. BIAS/EZL/EE to 30/14/1.5 kV
Tuesday, March 17, 2015, 09:20: Started heating TGHT/TBHT to 400/150 A at 2/1 A/min
Wednesday, March 18, 2015, 08:41: Continued heating TGHT/TBHT to 580/170 A at 2/1 A/min
Wednesday, March 18, 2015, 09:33: MB1 found tripped on water flow. Water pressure is low this morning as cyclotron main magnet was switched on, but not all water pumps. Expected to be resolved soon..
Some emittance scans at 170, 180, 190, 200 A TBHT were done
Thursday, March 19, 2015, 08:47: Heating TBHT to 220 A
Thursday, March 19, 2015, 08:56: Heating TBHT to 230 A
Thursday, March 19, 2015, 10:50: EE at -2000 V for 10 min
Thursday, March 19, 2015, 10:52: EE back at -1.5 kV
Thursday, March 19, 2015, 17:54: Started cool down of target
Friday, March 20, 2015, 08:47: Closed IV4
Friday, March 20, 2015, 08:47: RGA off.
Friday, March 20, 2015, 08:50: Stopped turbos
Friday, March 20, 2015, 10:24: Venting
Friday, March 20, 2015, 11:45: Target removed. |