Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand  Not logged in ELOG logo
Message ID: 431     Entry time: Monday, March 16, 2015, 18:53
Author: Anders Mjos 
Target/No.#: Ta#45 
Source: HP-SIS 
Station: ITE 
Module: TM4 
Target Oven W.O#: 38817-5 
Heat Shield W.O#:  
Status: In progress 
Subject: Conditioning Ta#45 

 Monday, March 16, 2015, 18:53: Started turbos

Monday, March 16, 2015, 19:00: Turbos at speed. Vacuum at 1.3E-5 T


Tuesday, March 17, 2015, 09:03: Opened cooling water. Vacuum stable at 1.9E-7 T

Tuesday, March 17, 2015, 09:12: Opened IV4. BIAS/EZL/EE to 30/14/1.5 kV

Tuesday, March 17, 2015, 09:20: Started heating TGHT/TBHT to 400/150 A at 2/1 A/min


Wednesday, March 18, 2015, 08:41: Continued heating TGHT/TBHT to 580/170 A at 2/1 A/min

Wednesday, March 18, 2015, 09:33: MB1 found tripped on water flow. Water pressure is low this morning as cyclotron main magnet was switched on, but not all water pumps. Expected to be resolved soon..

Some emittance scans at 170, 180, 190, 200 A TBHT were done


Thursday, March 19, 2015, 08:47: Heating TBHT to 220 A

Thursday, March 19, 2015, 08:56: Heating TBHT to 230 A

Thursday, March 19, 2015, 10:50: EE at -2000 V for 10 min

Thursday, March 19, 2015, 10:52: EE back at -1.5 kV

Thursday, March 19, 2015, 17:54: Started cool down of target


Friday, March 20, 2015, 08:47: Closed IV4

Friday, March 20, 2015, 08:47: RGA off.

Friday, March 20, 2015, 08:50: Stopped turbos

Friday, March 20, 2015, 10:24: Venting

Friday, March 20, 2015, 11:45: Target removed.

Attachment 1: Ta#45_Test_Stand.docx  1.985 MB  Uploaded Monday, March 23, 2015, 15:03
Attachment 2: Ta#45_2015-03-17_Mar_17_2015_09-05-31_AM.ana  1.650 MB  Uploaded Wednesday, March 25, 2015, 11:27