Entry  Wednesday, January 25, 2017, 14:54, Aaron Schmidt, , , , , 42218-9, 41751-6, Done, Target cleaning test HP-SIS CC Clean HP-SIS_CC_Clean.docxTS-2017-01-30-11-00.rgaOMEGA_OM-DAQPRO-5300_01-Feb-17_15.36.02.dlp


v\:* {behavior:url(#default#VML);}
o\:* {behavior:url(#default#VML);}
w\:* {behavior:url(#default#VML);}
.shape {behavior:url(#default#VML);}


Target Test (Fully Cleaned vs Crystal Clean only).
Entry  Wednesday, January 25, 2017, 14:55, Aaron Schmidt, , , , , 42218-6, 41751-6, Done, Target cleaning test (Long) HP-SIS Full Clean HP-SIS_Full_Clean.docxOMEGA_OM-DAQPRO-5300_07-Feb-17_09.17.23.dlpTS-2017-02-01-10-40.rgaTS-2017-02-03-08-50.rga


v\:* {behavior:url(#default#VML);}
o\:* {behavior:url(#default#VML);}
w\:* {behavior:url(#default#VML);}
.shape {behavior:url(#default#VML);}








Normal
0




false
false
false
Entry  Monday, July 17, 2017, 09:58, Aaron Schmidt, , HP-SIS, , , 42218-8, 42738-1, , Target cleaning test (Long) HP-SIS CC Clean  HP-SIS_CC_Clean_(Long).docxOMEGA_OM-DAQPRO-5300_27-Jul-17_10.25.04.dlpTS-2017-07-24-10-40.rga
 Target
Test (Fully Cleaned vs Crystal Clean only).
Entry  Monday, November 05, 2012, 14:41, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , Done, Target Removed 
Target looks OK. The right leg was a bit much out of center and will be adjusted in the lab.
The torque required to loosen the bolts were measured (from left to right):
Target legs: 48 and 30 in lbs
Entry  Tuesday, October 22, 2013, 15:20, Rick Maharaj, , , , , , , Problems/Solutions, Target Heater Conductor Block Insulators Replaced Source_Tray_TGHT_and_COIL_insulators_replaced_2013-10.pdf
The Conductor insulating blocks - ITD053C and ITD054C - that secure the target heater and coil conductor blocks were replaced. The existing ones were
cracked and fell apart upon removal.
Entry  Wednesday, September 14, 2011, 15:40, Anders Mjos, TaC#1, LP-SIS, ITE, TM1, 38634-6, 36833-6, In progress, TaC#1 installed and pumping down. 
Wednesday, September 14, 2011, 15:39: Vacuum at 1.3e-5 torr 
Thursday, September 15, 2011, 08:59: Vacuum at 2.9e-7 torr. Water flowing and vacuum stable. 
Entry  Friday, August 09, 2024, 21:08, Ferran Boix Pamies, Ta#67 Thin foils , LP-SIS, ITE, TM4, 45447-14 , 45235-10, In progress, Ta#67 thin foil retesting ITE-TM4-Ta#67-LP-SIS_Thin_Foil.docx
Friday, August 09, 2024, 21:07 Insulators, retainer and Re foil have been replaced, source cup machined so the ion source does not short against it.
Venting TS now.
Friday, August 09, 2024, 22:17 Roughing.
Entry  Friday, June 25, 2021, 11:18, Aaron Schmidt, Ta#62, LP-SIS, ITE, TM4, 44691-4, 44378-4, Done, Ta#62 Conditioning - New Ta#62_44691-4_Conditioning_-_R.docxTa#62_44691-4_Conditioning..docxITE-TM4-Ta#62-LP-SIS_Test_Stand.docx
Replacement Ta target for the previous one (44139-10) https://elog.triumf.ca/TIS/Test-Stand/880
Friday, June 25, 2021, 11:16: Roughing.
Friday, June 25, 2021, 11:55: TP1B started.
Entry  Monday, June 21, 2021, 11:53, Aaron Schmidt, Ta#62, LP-SIS, ITE, TM4, 44139-10, 44378-4, Failed, Ta#62 Conditioning - 2 Ta#62_Conditioning_-_2.docx
Replace 9-pin back to normal grounded setup. Re-salt Ta#62. (Cu Gaskets in-use on FS#5)
Monday, June 21, 2021, 11:30: Roughing chamber.
Monday, June 21, 2021, 11:50: Removed backing window. Roughing beam line side.
Entry  Monday, June 07, 2021, 13:45, Aaron Schmidt, Ta#62, LP-SIS, ITE, TM4, 44139-10, 44378-4, In progress, Ta#62 Conditioning Ta#62_Conditioning_-_1.docx
Monday, June 07, 2021, 13:44: Roughing.
Monday, June 07, 2021, 14:16: TP1B on. (Tripped shortly after?)
Monday, June 07, 2021, 14:32: Unstable. Venting.
Entry  Wednesday, March 11, 2020, 13:31, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing - 2 Ta#60_-_TS_Pre-condition_-_EE_Test_-_2.docx
Thermocouples installed on EE. Double checked continuity & used a heat gun.
Wednesday, March 11, 2020, 13:30: Roughing.
Wednesday, March 11, 2020, 15:03: Turbo pumps on, interlocks by-passed (No water at
Entry  Thursday, February 20, 2020, 11:41, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing 20200221_134828.jpg20200221_134939.jpgTa#60_-_TS_Pre-condition_-_EE_test_-_1.docx
 Ta#60 (Unconditioned) - Salts in.
Thursday, February 20, 2020, 14:04: Roughing.
Thursday, February 20, 2020, 14:38: Turbo pumps on (Leak check in am).
Entry  Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning Ta#46.docx
EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0: Roughing
Friday, September 11, 2015, 12:12: Turbos started.
Entry  Friday, September 27, 2013, 11:41, Anders Mjos, Ta#41, HP-SIS, ITW, TM4, 39069-5, 38817-10, Done, Ta#41 Conditioning Ta#41_EE_After_Test_Stand.pdf
Friday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08: Turbos started
Friday, September 27, 2013, 12:16: Turbos at speed.
    Reply  Thursday, April 18, 2013, 13:50, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Ta#40 stored under vacuum 
Target installed at the Test Stand after an inspection in the lab. EE was cleand. All bolts torqued to 130 in lbs
Thursday, April 18, 2013, 13:48: Rouging
Thursday, April 18, 2013, 14:11: Starting turbos
Entry  Monday, March 25, 2013, 11:39, Anders Mjos, Ta#39, LP-SIS, ITW, TM1, , , Done, Ta#39 commissioning 
Target installed with 130 in lbs torque on all bolts.
Monday, March 25, 2013, 11:36: Roughing
Monday, March 25, 2013, 11:54: Starting turbos
Entry  Wednesday, April 25, 2018, 09:50, Aaron Schmidt, Ta (test), LP-SIS, , , 41177-3, , In progress, Ta test and window change TS-2018-04-25-14-55.rgaTa_target_heating_test_-_Test_stand.docx
Window changed on view port. Ta target prepared for Aurelia's tests.
***Note*** No Ta window foils on the end plates. Initial ramping to on the TGHT to 300 A. Follow up in increments of 50 A and check the right
door window temperature.
Entry  Tuesday, June 14, 2016, 10:46, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY - NO PLASMA ELECTRODE Tube_only_SIS_test-all-160615.zip2016-06-13.zip2016-06-15.zipre-em-plots.zip
Tuesday, June 14, 2016, 10:46: Begin roughing.
Tuesday, June 14, 2016, 11:16: Turbo pumps started.
Tuesday, June 14, 2016, 11:23: Ion gauge on.
Entry  Thursday, June 16, 2016, 14:34, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY (3) Tube_only-full-fernando_test-160617-PE-RPE.zipTube_only-full-fernando_test-160617-WPE.zip
Thursday, June 16, 2016, 14:33: Roughing. Plasma Electrode re-attached. Salts replaced.
Thursday, June 16, 2016, 15:12: Turbo pumps started.
Thursday, June 16, 2016, 15:22: Ion gauge on.
Entry  Thursday, June 09, 2016, 14:56, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY Tube_only_SIS_test.zip
Thursday, June 09, 2016, 14:50: Begin roughing.
Thursday, June 09, 2016, 15:34: Turbo pumps started.
Thursday, June 09, 2016, 15:42: Ion gauge on.