Message ID: 598     Entry time: Monday, July 17, 2017, 09:58
Author: Aaron Schmidt 
Target/No.#:  
Source: HP-SIS 
Station:  
Module:  
Target Oven W.O#: 42218-8 
Heat Shield W.O#: 42738-1 
Status:  
Subject: Target cleaning test (Long) HP-SIS CC Clean  

 Target Test (Fully Cleaned vs Crystal Clean only).

For all tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.

-Start Roughing by 10:10am +/- 1 minute.

-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A

ALL START TIMES MUST BE CONSISTENT.


***Pre-outgassed*** Heat Shield W.O# 42738-1: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.


HP-SIS Target # 42218-8: Crystal Clean only.


Monday, July 24, 2017, 09:46: HS removed from test stand. Exchange target.

Monday, July 24, 2017, 10:08: Target # 42218-8 placed into test stand. Door open for 22 minutes.

Monday, July 24, 2017, 10:10: Roughing.

Monday, July 24, 2017, 10:10: Doors sealed for roughing.

Monday, July 24, 2017, 10:11: BV1B OPEN. Opened @ 306T.

Monday, July 24, 2017, 10:29: Both Turbo pumps started.

Monday, July 24, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.

Monday, July 24, 2017, 10:38: TP1A @ speed 38 KRPM.

Monday, July 24, 2017, 10:40: RGA on. Vacuum @ 1.51E-05T.

Monday, July 24, 2017, 15:03: Vacuum @ 6.14e-07T


Tuesday, July 25, 2017, 08:02: Water lines opened. No response on RGA. Vacuum stable @ 1.97E-07T.

Tuesday, July 25, 2017, 08:05: Power/Sources on.

Tuesday, July 25, 2017, 08:23: Anode increased to 5, 10, 25, 50 V. Ok @ 0.000mA

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 27.3 3.77
 TBHT 27.3 3.02
 COIL + EE 27.1 4.91
 TGHT  27.3 5.53

Tuesday, July 25, 2017, 08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Tuesday, July 25, 2017, 09:00: Open back power supply panel. Using multimeter, 9-pin ground connection verified. Panel closed.

10:45: Check. Vacuum @ 2E-06T.

11:45: Check. Vacuum @ 3.33E-07T.

13:30: Check. Vacuum @ 2.78E-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP  33.5 3.78
 TBHT  28.1 3.03
 COIL + EE 27.2  4.92
 TGHT

29.4

4.48

Tuesday, July 25, 2017, 14:27: Open back power supply panel. Using multimeter, 9-pin ground connection verified. Panel closed


Wednesday, July 26, 2017, 08:15: Check. Vacuum @ 2.60E-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP  33.5 3.78
 TBHT  27.6 2.99
 COIL + EE 27.2  4.06
 TGHT

29.4

 5.52

 Wednesday, July 26, 2017, 15:00: Auto-Cooling @ 2A per min. Check. Vacuum @ @2.43e-07T


Thursday, July 27, 2017, 07:20: Check. Vacuum @ 1.44e-07T

Thursday, July 27, 2017, 07:22: Power/sources off.

Thursday, July 27, 2017, 07:24: Waterlines purged.

Thursday, July 27, 2017, 07:26: RGA off.

Thursday, July 27, 2017, 07:27: Ion gauge, Turbos off

Thursday, July 27, 2017, 09:13: Venting.

Attachment 1: HP-SIS_CC_Clean_(Long).docx  1.601 MB  Uploaded Thursday, July 27, 2017, 11:28
Attachment 2: OMEGA_OM-DAQPRO-5300_27-Jul-17_10.25.04.dlp  540 kB  Uploaded Thursday, July 27, 2017, 11:28
Attachment 3: TS-2017-07-24-10-40.rga  2.096 MB  Uploaded Thursday, July 27, 2017, 11:29