Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 10 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target/No.# Source Station Module Target Oven W.O#down Heat Shield W.O# Status Subject Text Attachments
  351   Wednesday, December 18, 2013, 12:04 Anders Mjos    40282-539230-1DoneHeating Test Wednesday, December 18, 2013, 12:04:
Turbos stopped
Wednesday, December 18, 2013, 13:19:
  
  354   Tuesday, January 14, 2014, 08:58 Anders Mjos    40282-539230-1DoneHeating TestTuesday, January 14, 2014, 08:57: Stopping
turbos. Vacuum at 1.2E-7 T
Tuesday, January 14, 2014, 13:32:
  
  394   Friday, July 18, 2014, 11:30 Anders MjosUC#10LP-SISITETM440282-540316-1DoneUC#10 Heat Shield ConditioningFriday, July 18, 2014, 11:30: Roughing
Friday, July 18, 2014, 11:51: Starting
turbos
  
  403   Monday, September 08, 2014, 16:23 Anders MjosUC#11  TM440282-5 DoneUC#11 Heat Shield ConditioningT/C installed
CH 1: Attached to TGHT outside middle
CH 2: Through HS outside TGHT right
 Thermocouples.xlsx 
  404   Thursday, September 25, 2014, 15:44 Anders MjosThO#1 ITWTM140282-5 DoneThO#1 Heat Shield ConditioningThursday, September 25, 2014, 15:44: Roughing
Thursday, September 25, 2014, 16:06:
Starting turbos
  
  397   Friday, August 08, 2014, 12:45 Anders MjosZrC#6LP-SISITWTM140282-339230-5DoneCondictioning ZrC#6Friday, August 08, 2014, 12:44: Stopped
turbos
Friday, August 08, 2014, 14:42: Venting 
  
  390   Thursday, June 26, 2014, 16:32 Anders MjosTa#43LP-SISITWTM140282-239230-6In progressConditioning Ta#43Thursday, June 26, 2014, 16:31: Roughing.
Thursday, June 26, 2014, 16:51: Starting
turbos. 
 Ta#43_Conditioning.docx 
  364   Monday, March 17, 2014, 19:10 Anders MjosTa#42LP-SISITWTM440282-139956-1 / 39956-9 (base / lid)In progressConditioningNOTE:
TBHT
Power Supply is 600A. EPICS thinks it is
 Ta#42_Test_Stand.docxOMEGA_OM-DAQPRO-5300_21-Mar-14_13.56.35.dlp 
  510   Wednesday, June 01, 2016, 10:02 Aaron SchmidtUC#16LP-IG-LISITETM439814-V2-1  Conditioning Heat shield for UC#16Wednesday, June 01, 2016, 10:02: Begin
roughing.
Wednesday, June 01, 2016, 10:44:
 OMEGA_OM-DAQPRO-5300_03-Jun-16_08.14.47.dlpTS-2016-06-02_UC#16.rgaTS-2016-06-02-13-46_UC#16.rgaUC#16.docx 
  537   Friday, September 02, 2016, 15:47 Aaron SchmidtSiC#34LP-IG-LISITETM439814-V2-141751-9 Conditioning SiC# 34Friday, September 02, 2016, 15:47: Roughing.
Friday, September 02, 2016, 16:18:
Turbos started -AM
 ER-580-270-m40.txtITE-TM4-SiC#34-LP-IG-LIS_Test_Stand.docxSiC#34.docxTS-2016-09-06-08-12.rga 
  651   Wednesday, March 21, 2018, 14:11 Fernando Maldonado LP-FEBIAD  395530-342752-2In progressTest FEBIAD Tests on coil, temperature and the use
of silver bolts.
(3) Vented silver bolts on the TBHT
 10x 
  695   Thursday, November 08, 2018, 10:54 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTest FEBIAD w/ Silver bolts & sealed end capsSilver bolts used on Coil, TGHT, &
TBHT. Back panel opened for new gas bottles.
Thursday, November 08, 2018, 10:52:
  
  700   Wednesday, December 12, 2018, 13:22 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressAnode leak current check.Wednesday, December 12, 2018, 13:15: Power
/ Sources on.
Wednesday, December 12, 2018, 13:20:
  
  701   Monday, December 17, 2018, 12:03 Aaron Schmidt LP-FEBIAD  395530-342752-5 Anode leak current check.Monday, December 17, 2018, 12:01: Connected
Multimeter through feedthroughs J & L.
Blue wire removed.
  
  702   Thursday, December 20, 2018, 13:55 Aaron Schmidt LP-FEBIAD  395530-342752-5 Holiday shut down.High winds caused a brief power outage
that completely shutoff the ISAC test stand.
Locked out the power.
  
  703   Tuesday, January 08, 2019, 08:11 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTS restart Tuesday, January 08, 2019, 08:00: Epics
white out fixed. Ref: Fault report 11981.
Tuesday, January 08, 2019, 08:10:
  
  716   Friday, April 05, 2019, 07:02 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTS operation test - LP FEBIADDue to previous issues, a full run / test
should be performed on the ISAC Test Stand.
Friday, April 05, 2019, 07:00: RGA
 TS_-_New_BIAS__EZL_Testing_-_2019.docxTS-2019-04-05-07-00.rga 
  724   Saturday, May 25, 2019, 12:43 Aaron SchmidtTest FEBIAD / TM4LP-FEBIAD TM4395530-342752-5In progressInstalled TM4 Source TraySilver bolts on TGHT & Coil Lines.
Oxide steel bolts on TBHT. Filed target to
suit / fit (Previously heated). Rubber O-rings
 TM4_Source_Tray_-_2019_-_Leak_Check.docxTM4_Source_Tray_-_2019.docxTS-2019-05-27-07-08.rga 
  725   Tuesday, May 28, 2019, 15:05 Aaron SchmidtTest FEBIAD / TM4LP-FEBIAD TM4395530-342752-5In progressTM4 Source Tray - Episode IISEE ELOG 724
Tuesday, May 28, 2019, 15:02: Roughing
Tuesday, May 28, 2019, 15:32: Turbos
 TM4_Source_Tray_-_2019_-_2.docxTS-2019-05-29-07-08.rgaTM4_Source_Tray_-_2019_-_3_-_HV_-_1.docxTM4_Source_Tray_-_2019_-_4_-_HV_-_2_-_Heat_on.docxTM4_Source_Tray_-_2019_-_5_-_HV_over_50_-Heat_on.docx 
  726   Monday, June 03, 2019, 11:35 Aaron Schmidt LP-SIS TM4395530-342752-5Problems/SolutionsTGHT PS Failed.Monday, June 03, 2019, 10:36: BIAS Near
55 kV, brought back down to  50 kV. Multiple
sparks. Optics tripped, wire scanners &
  
ELOG V2.9.2-2455