Thursday, September 25, 2014, 15:44: Roughing
Thursday, September 25, 2014, 16:06: Starting turbos
Thursday, September 25, 2014, 16:14: Turbos at speed.
Thursday, September 25, 2014, 16:28: Vacuum at 1.9E-5 T
Vacuum was coming down slowly yesterday. Vented this morning to clean o-ring on door.
Friday, September 26, 2014, 08:40: Roughing
Friday, September 26, 2014, 09:02: Starting turbos
Friday, September 26, 2014, 09:10: Turbos at speed
Friday, September 26, 2014, 09:12: Vacuum at 9.7E-6 T
Monday, September 29, 2014, 08:40: Water opened for HS circuit. Vacuum stable at 1.8E-7 T
Monday, September 29, 2014, 13:51: Opened and closed IV4
Wednesday, October 01, 2014, 13:13 : Target cooled down.
Monday, October 06, 2014, 09:10: Turbos stopped. Vacuum at 1.3E-7 T
Monday, October 06, 2014, 10:49: Venting
Tuesday, October 07, 2014, 09:31: Heat Shield removed |