Entry  Wednesday, June 10, 2020, 08:58, Isaac Earle, Development, Other, M9, T2-M9 and M9-B1 flange scan data 2017-03-28_meson_hall_t2_with_import_of_2015_data.xit642019-25-01_meson_hall_t2_data.xit64
 Laser tracker scan data from 2017 and 2019 attached as a backup.  Original files from Beamlines Group who also keep copies on \\trwindata\experimental
support\alignment\T2-M9_data
Entry  Tuesday, June 09, 2020, 17:01, Isaac Earle, Development, Other, M9, Cables and helium leak check line installed to M9 service stand 
 The 10-pin thermal switch wire, 2-pin steering wire for Q2, and a 1/4" copper tube for remote helium leak check were installed through the
service chase with the power cables and connected to the M9 service stand.  Approximately 10m of extra cable (2-pin and 10-pin) was coiled and left
in the cooler section of the service chase after the first sharp bend.  The cables and the tubing are currently run as far as the vertical cable tray
Entry  Monday, April 06, 2020, 15:02, Isaac Earle, Standard Operation, Target 2, M9, M9 beam blocker returned to beamline 
The M9 beam blocker was returned to the beamline today using the RH shielded transport flask.  The top flange o-ring was replaced before installation.
After installation the "Lift T" assembly was removed, and electrical cable and air supply connected.  Correct functionality of the
limit switches was confirmed with the control room.  Actuation of the beam blocker could not be tested at this time because control takes place through
Entry  Monday, March 23, 2020, 16:13, Isaac Earle, Maintenance, Other, Other, M9 beam blocker MRO completed 
M9 beam blocker MRO work was completed in the hot cell today.  This included replacement of the main shaft seals and replacement of the air cylinders. 
Actuation was tested after replacement and the blocker moved smoothly through the full length of travel with approximately 45psi air pressure.  It
is ready for transport back to the beamline.
Entry  Wednesday, March 11, 2020, 10:29, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand foot plate installed 
 The M9 Q1Q2 "foot" plate (TB23363) has been installed over the floor plate.  A nominal gap between the plates of 1/2" was set
before lowering the plate, it was then leveled using the three adjustment bolts resulting in a larger gap.  After leveling, the plate was lifted to
remove the spirit levels and lock the position of the leveling bolts.  The plate was then re-lowered and the tiedown bolt assemblies (TB23383) were
Entry  Wednesday, March 04, 2020, 13:42, Ron Kuramoto, Repair, Other, Other, B/L 1A vacuum air leak repair 1AT1_Vacuum_Leak_Repair-Feb2020.pdf
 A 4” Marmon aluminum blank-off flange and o-ring were replaced on the south port of the T1 target monolith vacuum vessel. This port
was accessed from the 1A Service Tunnel were the repair took place.
Entry  Friday, February 28, 2020, 09:06, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand floor plate installed M9_service_stand_floor_plate_TB23351.png
 The M9 service stand floor plate (TB23351) was installed in the M9 pit yesterday.  Prior to installation all 5 threaded inserts were tested
using a 1/2"-13 stud tool on an RH pole.  The west most hole (shown in red below) had damaged threads and the stud could only be threaded in
2 turns.  All other locations (shown in green) had usable threads with 6-8 full turns possible with the stud tool.  The plate was installed using
Entry  Monday, February 10, 2020, 14:51, Isaac Earle, Maintenance, Other, Other, T1-MK2 target and M9BB moved 
 The T1-MK2 target was moved from the hot cell to Hole #5 in the storage pit.  The M9 beam blocker was then moved from the beamline to the
hot cell for MRO work.  A field of 14.4mSv/hr was measured at 0.5m from the beam blocker during removal.
Entry  Wednesday, February 05, 2020, 14:53, Isaac Earle, Maintenance, Target 1, Cooling, T1 & T2 cooling package MRO work completed 
 Annual MRO work on the T1 and T2 cooling packages is now complete.  The following tasks were performed:

    Water from both packages drained to the South TNF holding tank (samples taken)
    All Proteus paddle wheels, shafts, and
o-rings replaced (5 each at T1 and T2)
    All Cuno filters changed
    Archived data for all sensor readbacks inspected.  Only
Entry  Thursday, January 30, 2020, 17:55, Isaac Earle, Repair, Target 1, Target, T1-MK2 target assembly repair completed in hot cell T1-MK2_-_2020.pdfRHB_8901_Position_1_Entrance_Window.jpgDSC_0047_Position_1_Exit_Window.jpgRHB_8904_Position_4_Entrance_Window.jpgDSC_0022_Position_4_Exit_Window.jpg
The following work was done to the T1-MK2 target in the hotcell between the dates of May 24, 2019 - Jan 30, 2020 (See E-Log #251 for further information):

    May 24: Flushed position 2 with water, purged all positions with air.  Left air running through position 0 over the weekend

   May 27: Switched to position 5, left air running to dry out bellows
    May 28: Started pump out with cold-trap;  Reached "fine
Entry  Monday, January 20, 2020, 16:07, Isaac Earle, Other, Other, Other, Second 55-gal drum moved to cyclotron east vault tunnel RWC-55-02-2019_(after_move_to_cyc_vault_tunnel).pdf
 The second (and final) 55 gallon drum containing active items from the Meson Hall East Hot Cell was transported today from the Warm Cell to the
Cyclotron East Vault Tunnel.   The updated form is attached.
Entry  Tuesday, December 17, 2019, 12:39, Isaac Earle, Standard Operation, Other, Other, 55 gallon drum and old M9 service stand moved to Rad Waste Pit RWC-55-01-2019.pdfpit_-_before_move.jpgdrum_being_lifted.jpgpit_-_after_move_-_showing_drum.jpgpit_-_after_move_-_showing_service_stand_(bottom_right_with_green_sling).jpg
The following items were moved today from the Warm Cell to the Rad Waste Pit for long term storage:
1. A 55 gallon drum containing various active components from the East Hot Cell.  The drum was labelled on the body and lid with the identification
number RWC-55-01-2019.
Entry  Monday, June 24, 2019, 14:29, Isaac Earle, Development, Target 1, Target, T1 and T2 target alignment frames overhauled 8x
The following work was completed on both the T1 and T2 target alignment frames

    One of the short taper pins on the top of the frame was swapped for a longer version to simplify flask alignment to the frame (now one
pin can be aligned at a time instead of both concurrently)
    Three permanently mounted cameras installed to view east/west alignment, north/south
Entry  Wednesday, May 22, 2019, 14:25, Isaac Earle, Repair, Target 1, Target, T1-MK2 target moved to HC; T1-MK1 target moved to BL T1-MK1_target_info_sheet_-_Installed_May_21_2019.pdf
After extensive testing over the last 2 weeks it was determined that the protect monitor
on the T1-MK2 target had an issue with intermittent shorting between the high voltage line and ground (movement of the target ladder was causing the short
to come and go).
Entry  Tuesday, April 16, 2019, 15:35, Keith C Ng, Repair, Other, M9, M9 project post shutdown summary 
 Completed work at m9 beam line:
- Removed existing service stand and associated cable and water services. Legacy b1 water services still need to be removed for future magnet installation.
Old service stand is currently in warm cell waiting for disposal.
Entry  Tuesday, February 26, 2019, 10:55, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 MRO work and solenoid valve change summary 
The following work was completed between Jan 16 - Feb 19, 2019:

    T1 and T2 cooling packages drained to South TNF holding tank, water sampled and tested, released after approval from RPG
    T1
resin can swapped
    All Cuno filters changed at T1 (3 total)
    T1 inlet (T1CSPGIN) and outlet (T1CSPGOUT) pressure gauges replaced
Entry  Friday, January 25, 2019, 10:53, maicodallavalle, Repair, Other, Cyclotron electrical, Cyclotron Elevating system Motor electrical wire repairs 
2018 Cyclotron lid up problem. Station #9 was  found to  have the motor wires along the beam plain had damaged wire insulation. There were
bare wires in the conduit resulting in the wires shorting out. The wires were repaired with a quick short replacement. Lid went up for in tank work. After
lid down the problem was investigated. We checked the radiation levels   at all  of the stations to come up with a plan to determine witch of
Entry  Thursday, January 10, 2019, 13:51, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 cooling packages inspected 
The T1 and T2 cooling packages were inspected today while running.  No water leaks were observed at either package including the high-active loops
and copper active. 
The T1 pump was fairly noisy (video was taken to record the sound).  This is the new pump installed in August 2018 (see E-Log #242). 
Entry  Thursday, November 01, 2018, 13:57, Keith C Ng, Other, Other, Other, nuclear venillation in hot cells not working 
Randomly checked on the nuclear ventilation for the Meson Hall Hotcells and discovered they were not running again (both magnahelic gauges displayed
zero). Attempted to restart the fan manually and the control box seems to not be working. Matt McClean has been contacted and they will look into the problem.

The nuclear ventilation is currently not running in the RHMH hot cells.
Entry  Thursday, October 25, 2018, 08:58, Keith C Ng, Repair, Other, Other, T1 collimator valve solenoid coil replaced again 
On 23rd October we restarted the T1 and T2 water packages after the mini shutdown and after the site power outage.
The rotary collimator was reporting no water flow and it was assumed the valve coil (