Friday, April 12, 2013, 13:28, Isaac Earle, Standard Operation, Target 1, Cooling, Cooling Packages Leak Tight
|
The T1 and T2 expansion tanks were filled on Monday April 8th. There was no change in the level when inspected today (April 12th). Visual
inspection of the packages also found no leaks. |
Monday, January 30, 2012, 16:44, Isaac Earle, Maintenance, Target 1, Cooling, Completed T1 Cooling Package MRO
|
Replaced all o-rings and filters on the T1 cooling package. Replaced resin can. Refilled package
and restarted.
Can inlet resistivity at 9.8M |
Friday, April 09, 2021, 12:42, Matthew Gareau, Maintenance, Target 2, Cooling, Changed the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 package
|
With the assistance of Maico we changed the paddle wheel, o ring, and shaft in the Collimator A flow meter (Q4) at the T2 package.
Flow meter was wiped clean to ensure o ring surface was clean.
Everything was changed without incident, and ops confirmed that the flow rate is now normal. |
Thursday, March 10, 2022, 11:18, Adam Newsome, Maintenance, Target 2, Cooling, Changed paddle wheel, o-ring, and shaft in flow sensors at T2 cooling package 
|
The paddle wheels, o-rings, and shafts were changed at the T2 cooling package for the following sensors:
B1A:T2:FGCOLA
T2CS:FGTGT
T2CS:FGDEM
T2CS:FGSEC
T2:FGCOLB
No
major issues were noted. Some residue was observed upon cleaning the sensors. No leaks observed when turning water isolation valves back on. |
Thursday, March 10, 2022, 13:57, Adam Newsome, Maintenance, Target 1, Cooling, Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package
|
The paddle wheels, o-rings, and shafts were changed at the T1 cooling package for the following sensors:
B1A:T1:FGCOLA
T1CS:FGTGT
T1CS:FGDEM
T1CS:FGSEC
T1:FGCOLB
No
major issues were noted. Some residue was observed upon cleaning the sensors. No leaks observed when turning water isolation valves back on. |
Tuesday, June 09, 2020, 17:01, Isaac Earle, Development, Other, M9, Cables and helium leak check line installed to M9 service stand
|
The 10-pin thermal switch wire, 2-pin steering wire for Q2, and a 1/4" copper tube for remote helium leak check were installed through the
service chase with the power cables and connected to the M9 service stand. Approximately 10m of extra cable (2-pin and 10-pin) was coiled and left
in the cooler section of the service chase after the first sharp bend. The cables and the tubing are currently run as far as the vertical cable tray |
Friday, January 13, 2012, 17:04, Isaac Earle, Repair, Target 2, Target, Broken Part found on M20 Beam Blocker 
|
While wrapping up vacuum seal bearing replacement on the M20 beam blocker I found a piece of hard black material approximately 3x1x1cm on top of
the hot cell turntable. Checked for contamination and found 480,000cpm on the Ludlum 44-2 probe, and off scale on the pancake monitor. This
piece fell from the transport flask when it was opened above the hot cell after picking up the M20 beam blocker. Upon further inspection, more pieces |
Friday, June 08, 2012, 16:52, Isaac Earle, Repair, Target 1, Target, Broken Manipulator Tape Update
|
The broken tape on the west side hot cell manipulator was found to be one of two "Z motion slave tapes". The manipulator can still
function normally with only one, however the remaining tape will see twice the load as usual. It was decided that repair of the manipulator may be
delayed until after the T1-MK2 target repair job is complete. Lifting of heavy objects using the west side manipulator will be avoided until after |
Wednesday, January 18, 2012, 12:01, Isaac Earle, Repair, Target 2, Target, Broken M20BB Bearing Removed, New Design Complete   
|
The broken M20 beam blocker plastic shaft bearing was removed. Measurements of the bearing as well as the shielding disc (for which drawings
can't be found) were taken inside the hot cell and a brass replacement bearing has been designed based on these measurements.
Photos of the removed bearing, measured dimensions of bearing and shielding disc, and a PDF drawing of the new design are attached. |
Tuesday, August 06, 2024, 11:35, Albert Kong, Standard Operation, Other, BL1A Holding Tank, BL1A and RH Active Sump Draining  
|
The RH active sump was drained (over Jul 31-Aug 01), in total approximately 5500 L of water was sent to city sewage.
We also tried to divert water from the BL1A holding tank to the active sump, and learned that we cannot run back-flow through the sump pump. The
valving configuration used here was V10, V1, SV1, V6 open - V2, V3 closed. (Note solenoid valve SV1 does not serve a purpose and energizing/powering-down |
Wednesday, April 04, 2012, 15:51, Isaac Earle, Repair, Target 2, Target, BL1A Update
|
Vacuum interlock defeat jumpers were removed for T1 and T2. The interlock was tested by venting the T1 and T2 volumes. Both packages registered
a vacuum trip, however only the T1 package shut off. A fault report has been filed to investigate this.
|
Friday, January 11, 2013, 15:48, Isaac Earle, Standard Operation, Target 1, Target, BL1A Tunnel Accessed 
|
The BL1A tunnel was accessed to drain and sample T2 cooling package water. A puddle of water was noticed in the South TNF area around the
drain by the boot-box. No water was found in the BL1A tunnel. Photos attached. |
Monday, July 09, 2012, 17:17, Isaac Earle, Standard Operation, Target 1, Target, BL1A Start-Up Prep
|
- T1 & T2 targets switched to "remote" control
- Both target ladders were moved to Position 3 (12mm Be)
- T2 Q1 flow interlock defeat was removed (only required when target ladder is in position zero) |
Tuesday, June 23, 2015, 10:24, Isaac Earle, Standard Operation, Other, Other, BL1A Holding Tank Water Released
|
The water in the BL1A holding tank was released to the city sewer. This water was sampled, tested, and approved for release by RPG two weeks
ago. The total volume was 510L, a combination of water from the T2 and TNF systems. The total time required to pump out the water with all
valves fully open was 1hr2m. Paperwork for the water release was completed and returned to RPG. |
Wednesday, April 03, 2024, 10:48, Adam Newsome, Other, Other, BL1A Holding Tank, BL1A Holding Tank - water level check
|
As of 2024-04-03, the BL1A Holding Tank water level is approximately 580L. It is recommended to drain the tank prior to the start of the operating year.
|
Tuesday, August 23, 2022, 14:36, Adam Newsome, Standard Operation, Other, Other, BL1A Holding Tank - Level Check
|
The water level inside the BL1A active water holding tank was checked today (Aug. 23, 2022). The tank is essentially empty at this time. |
Friday, May 08, 2015, 09:48, Isaac Earle, Standard Operation, Other, Other, BL1A Blocks Restored
|
Replacement of the BL1A blocks was completed yesterday (May 8, 2015) in preparation for first beam down 1A on May 12th. The attached PDF shows
a photograph of the current arrangement, and also the block arrangement at the beginning of the 2014 running period for comparison. |
Tuesday, January 08, 2013, 09:27, Isaac Earle, Standard Operation, Target 2, Target, BL1A Air Amplifier turned off for duration of shutdown.
|
The BL1A air amplifier has been shut down by closing the air supply valve on the device. The
air amplifier supplies high pressure air (110psi) to the following devices: M9BB, M20BB, T1 Profile Monitor, T2 Profile Monitor, T2 Collimator, Septum
Polarity Switch |
Tuesday, June 03, 2025, 11:39, Aaron Tam, Standard Operation, Other, BL1A Holding Tank, BL1A Active Water Holding Tank   
|
June 3, 2025 - Albert Kong, Aaron Tam
RPG finished analysis of the water sample and given approval for the contents of the holding tank to be released to city sewer
Procedure following Document-64834 Release No. 3 performed |
Wednesday, March 04, 2020, 13:42, Ron Kuramoto, Repair, Other, Other, B/L 1A vacuum air leak repair
|
A 4” Marmon aluminum blank-off flange and o-ring were replaced on the south port of the T1 target monolith vacuum vessel. This port
was accessed from the 1A Service Tunnel were the repair took place.
|
|