  1170   Friday, March 18, 2016, 09:34 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)

I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule 130 is under construction, and will be posted later.

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.xlsx
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
  1171   Friday, March 18, 2016, 09:42 David WangConditioning StationStandard OperationTM2 TM2 vacuum sysytem has been connected at TCS

TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.

  1172   Friday, March 18, 2016, 11:43 chad fisherSouth Hot-CellStandard Operation  SiC#32 dissection

SiC#32 has been open for inspection.

Attachment 1: 20160318_105519_1.jpg
20160318_105519_1.jpg
Attachment 2: 20160318_105311.jpg
20160318_105311.jpg
Attachment 3: 20160318_105248.jpg
20160318_105248.jpg
Attachment 4: 20160318_105428.jpg
20160318_105428.jpg
  1174   Monday, March 21, 2016, 10:25 David WangConditioning StationRepairTM2 TM2 Helium pressure Test Result in TCS and ITW

TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes. 

The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr  for both ITW and TCS. The test results are:

 

 

 

 

circuit TCS Test Result (atm.cc/sec) 2016-03-021  ITW Test Result (atm.cc/sec) 2016-03-02

TCS Test Result (atm.cc/sec)

2116-11-24

Target Oven + 5.2 X E-9 1.7 X E-8 2.0 X E-9
Target Oven - 5.6 X E-9 8.7 X E-9 2.2 X E-8
Tube Heater + 3.7 X E-8 1.7 X E-8 2.3 X E -8
Tube Heater - 1.9 X E-8 1.5 X E-8 8.2 X E-8
Coil 2 (P-Q) 7.2 X E-8 6.7 X E-8 5.4 X E-9
Coil 1 (R-U) 1.4 X E-8 1.3 X E-8 2.4 X E-9
MSP 2.3 X E-7, SECOND TIME 2.5 X E-7 4 X E-9 2.4 X E-7
HS NO TEST, LINE IS OPEN TO VACUUM. GOOD, NO RESPONSE ON LD Good, 0.0 X E-9
EE 4.3 X E-9 GOOD, NO RESPONSE ON LD

3.7 X E-8

 

window 4.5 X E-9 GOOD, NO RESPONSE ON LD Good , 0.0 X E-9
GE NO TEST, CONFIRMED IN SHC MIDDLE OF E-6 RANGE No test. Blanked
       

 2016-11-24: Checked again and added result into this elog.  No essential change has been found. MSP still has the biggest leak rate. David

  1175   Monday, March 21, 2016, 11:30 David WangConditioning StationRepairTM2 TM2 and TCS vacuum pumps are stopped

I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow  moving.   

  1176   Monday, March 21, 2016, 15:27 David WangConditioning StationRepairTM2 TM2 has been disconnected at TCS

TM2 vacuum system has been disconnected at TCS. Venting is in process now.

  1179   Wednesday, March 23, 2016, 11:32 David WangSouth Hot-CellRepairTM2 TM2 Helium spray leak check on GE and MSP lines at SHC

  Chad and I did the helium spray leak check on TM2 GE and MSP water lines at SHC this morning. We confirmed the GE leak on water blocks. We can not found the MSP leak by using the helium spray since its leak rate in TCS is much smaller than GE leak.  The leak check process are as below:
Leak detector are calibrated before the check.
GE lines : Base leak rate 0.0 X E-9 atm.cc/sec, base pressure 0.0 XE-4 torr.
Chad sprayed 5 psi helium to GE lines soldering joints  for 5 second, no response on leak detector.
Chad sprayed 5 psi helium to GE lines water blocks( between blocks seal surface) for 5 seconds, Leak detector response to 8 XE-9 atm.cc/sec right away.
Chad sprayed  5 psi helium to GE lines soldering joints for 5 seconds again, No response on leak detector.
Chad sprayed 5 psi helium around the source tray and to vacuum duct for 5 seconds more, No response on leak detector.
MSP lines: Base leak rate 0.0X E-9 atm.cc/sec, base pressure 0.0 X E-4 torr.  Chad did same thing as he did on GE lines. no response on LD. Chad repeated the test and prolonged the spray time to 10 seconds, No response.
The conclusion: It is pretty clear we have a leak on GE line water blocks seal.  MSP lines leak could not be found by helium spray in SHC since it is a small leak.
 

  1180   Thursday, March 24, 2016, 13:15 David WangConditioning StationStandard OperationTM1 TM1 and TCS vacuum system has been connected

TM1 and TCS vacuum system have been connected. All turbo-pumps are started. The pumping down is fine.

  1182   Tuesday, March 29, 2016, 08:38 David WangConditioning StationStandard OperationTM1 TM1 water lines helium pressure check at TCS

TM1 water lines helium pressure check at TCS is done. 70 psi helium was applied to water circuits. Leak detector base leak rate 0.0 x E-9 atm.cc/sec, base pressure 0.0 x E-4 torr. The result shows as below:

 

 

Ta+   0.0 X E-9 atm.cc/sec 3minutes stabilizing
Ta-  0.0 X E-9 atm.cc/sec 3minutes stabilizing
Tube-  0.0 X E-9 atm.cc/sec 3minutes stabilizing
Tube+  0.0 X E-9 atm.cc/sec 3minutes stabilizing
MSP   0.0 X E-9 atm.cc/sec 3minutes stabilizing
EE   0.0X E-9 atm.cc/sec 3minutes stabilizing
HS  not tested without caps.  
Window  E-5 range,leak on stem as we knew before.  10seconds to E-5

The results is good so far as we know the window line is leak on stem in service cap. The HS will be tested later with target on.

 The service cap air to vacuum seals also have been checked. The PNG1 panel and side round panel close to shutter are leak. The o-rings on them need to be replaced.

On March 30th -2016, I doubled checked the air to vacuum seal on the TM1 service cap. The side round panel is leak free actually. The PNG1 panel is leak at the bottom side. Confirmed.

On march 31th-2016, The o-ring(1-1/ 2275) on TM1 PNG1 side panel has been replaced today. The o-ring slot and mating surfaces are cleaned, and new  o-ring is installed. The panel is put back to TM1 and all bolts are tightened.

See attachments.

Attachment 1: TM1_PNG1_panel_o-ring_replacement_001.JPG
TM1_PNG1_panel_o-ring_replacement_001.JPG
Attachment 2: TM1_PNG1_panel_o-ring_replacement_002.JPG
TM1_PNG1_panel_o-ring_replacement_002.JPG
Attachment 3: TM1_PNG1_panel_o-ring_replacement_004.JPG
TM1_PNG1_panel_o-ring_replacement_004.JPG
Attachment 4: TM1_PNG1_panel_o-ring_replacement_005.JPG
TM1_PNG1_panel_o-ring_replacement_005.JPG
Attachment 5: TM1_PNG1_panel_o-ring_replacement_006.JPG
TM1_PNG1_panel_o-ring_replacement_006.JPG
  1183   Wednesday, March 30, 2016, 08:40 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

update the schedule according to changes.See attachment1, 2.

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
  1185   Wednesday, March 30, 2016, 15:49 David WangAssembly/Bench TestRepairTM2  TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo.

On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems  for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak rate:0.0 XE-9 atm.cc/sec, base pressure:0.0X E-4 torr. The circuit which I checked are :TA+, Ta-, Tube+, Tube-, PQ (coil 2), RU( coil1), EE, MSP, GE. The HS and window circuit are opened at this moment so they can not be checked.

Attachment 1: leak_check_TM2_016.JPG
leak_check_TM2_016.JPG
Attachment 2: leak_check_TM2_017.JPG
leak_check_TM2_017.JPG
Attachment 3: leak_check_TM2_018.JPG
leak_check_TM2_018.JPG
Attachment 4: leak_check_TM2_021.JPG
leak_check_TM2_021.JPG
Attachment 5: leak_check_TM2_022.JPG
leak_check_TM2_022.JPG
Attachment 6: leak_check_TM2_023.JPG
leak_check_TM2_023.JPG
Attachment 7: leak_check_TM2_025.JPG
leak_check_TM2_025.JPG
  1188   Friday, April 01, 2016, 14:41 David WangConditioning StationStandard OperationTM1 TM1 and TCS vacuum system has been connected. TCS control page white out.

I can not start the TCS pumps due to control page white out. Control group is working on this issue.

Control group fixed the white out problem. I started all turbo-pumps. The pumping down is good so far. The TM1 IG1 is broken. I will check it on next Monday. It could be a broken filament. Then, the filament will be replaced.

  1189   Monday, April 04, 2016, 11:14 David WangConditioning StationStandard OperationTM1 Helium pressure test on TM1 HS line at CS

New UCx target is installed on the module. 70psi helium,3 minutes. NO response on LD.  LD is pumped to bottom LR and LP during test.

  1192   Tuesday, April 05, 2016, 12:36 David WangITWStandard OperationTM1 TM1 vacuum system has been connected in ITW.

 All turbo -pumps are started.

  1193   Tuesday, April 05, 2016, 12:40 David WangITEStandard OperationTM4 I stopped ITE turbo pumps this morning

The ITE and TM4 have been vented with Argon . TM4 vacuum system is disconnected in ITE.

  1198   Friday, April 08, 2016, 07:10 David WangConditioning StationStandard OperationTM4 TM4 vacuum has been connected in ITE.

All turbo pumps are started yesterday. The pumping down is good over night.

  1200   Friday, April 08, 2016, 08:13 Anders MjosITE/ITW CoolingMaintenance  High Active Water Resistivity

The high active water resistivity took a long time to recover after the upgrade to the water cooling circuit. The system needed about a month (from end February to end March) to recover to nominal values. See attached plot of archiver data.

TM1 has now been connected in ITW and the water resistivity remains > 8 MOhm cm, which should allow normal operation. However, the resin is suspected to be approaching end of life. Work is ongoing to get a new replacement resin tank.

Attachment 1: 2016-04-08_ISAC_High_Active_Water_Resistivity.png
2016-04-08_ISAC_High_Active_Water_Resistivity.png
  1201   Friday, April 08, 2016, 08:48 David WangITWStandard Operation  ITW water signal interlock check.

I did a ITW water signals interlock check with ISAC opp. They are checked once a year before first beam on.

2016-04-13 Same test is done on ITE also. Everything is good.

  1202   Friday, April 08, 2016, 13:16 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

Update schedule weekly .see attachment 1,2

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
  1203   Monday, April 11, 2016, 09:42 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at CS with new Lp Ta target

70 psi helium , 2 minutes. Base leak rate 0.0x E-9 atm.cc/sec. base pressure 0.0XE-4 torr. no response on LD.The line is good.