Message ID: 1148     Entry time: Thursday, December 10, 2015, 13:17
Author: Anders Mjos 
Category: Conditioning Station 
Type: Standard Operation 
Module:  
Target/Number:  
Subject: Blank off flange 

Thursday, December 10, 2015, 13:17: Roughing

Thursday, December 10, 2015, 14:56: Started TP1S

Thursday, December 10, 2015, 15:59: Bypass applied on IG2

Thursday, December 10, 2015, 15:59: IG2 / IG1S 5.5E-5 T

Thursday, December 10, 2015, 16:01: RGA ON


Friday, December 11, 2015, 09:24 : IG2 / IG1S 7.5E-6 / 5.4E-6 T

Friday, December 11, 2015, 16:54: IG2 off for the weekend. Vacuum at 6.5 and 4.4E-6 Torr


Monday, December 14, 2015, 08:57: IG2 switched on.


Friday, December 18, 2015, 11:40: IG2 off for the weekend. Vacuum at 2.0E-6 and 8.9E-7 Torr 


Tuesday, December 22, 2015, 15:11: RGA off


Monday, January 11, 2016, 10:13: RGA on

Monday, January 11, 2016, 12:50: RGA off

Attachment 1: TCS_Blank_Off.png  622 kB  Uploaded Friday, December 11, 2015, 09:27  | Show | Hide all