  1157   Thursday, February 25, 2016, 06:52 David WangConditioning StationStandard Operation  stop CS vacuum pumps.

I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting.

  1158   Thursday, February 25, 2016, 09:27 David WangITWStandard OperationTM2 TM2 has been disconnected in ITW

TM2 has been disconnected in ITW (except vacuum lines). The vacuum system is still operating.

  1159   Thursday, February 25, 2016, 09:29 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.

TM4 has been disconnect in ITE(except  vacuum lines). The ITE vacuum system is still operating.

  1160   Wednesday, March 02, 2016, 09:51 David WangITWStandard OperationTM2 all water lines on TM2 and TM4 are purged.

All water lines on TM2 and TM4 are purged for upcoming water lines helium pressure test.

  1161   Wednesday, March 02, 2016, 10:04 David WangITWStandard OperationTM2 Leak check on ITW and TM2.

Dan and I leak checked TM2 and ITW primary vacuum vessel. It was found a 1X E-7 atm.cc/sec leak on top T flange seal between TM2 and dump module in first time check. But it is not a repeatable leak. I checked the same spot and around area two more times with increased helium volume.It did not show up again. The first response could  be a helium drift to dry scroll pump. I will check it again later. The primar vacuum vessel on ITW and TM2 are leak free. 

Dan and I found a small  leak on ITW dump module  top flange seal. The leak detector got a response  to 7xE-9 atm.cc/sec when I spray the helium to west side of dump module top flange. We tested again, and got same result. The o-ring which seals ITW dump module top flange is deteriorating. It need to be replaced at a proper time. This is the only air to vacuum leak we confirm so far on primary and secondary vacuum vessel on TM2 and ITW. The module and station no other air to vacuum leak.

The TM2 water lines helium pressure tested started in ITW. The helium pressure 70psi. The result so far is: Window: good, GE: huge leak directly shoot over E-7 atm.cc/sec( need to be confirmed tomorrow), HS: good, EE: good, MSP: tiny leak which is response to 3-4xE-9 atm.cc/sec. Coil 1 : small leak which is response to 1.3XE-8 atm.cc/sec. Tomorrow, We will test the rest water lines on TM2which are TA+, TA-, Tube+, Tube-, and coil 2. And We will confirm the GE huge leak at the last.

Finished the helium pressure test on TM2 water line.70 psi helium, The result of the rests 5 circuits: coil 1: leak 7.2xE-8atm.cc/sec,Ta(+): small leak 1.7XE-8 atm.cc/sec, Ta(-) small leak 8.7xE-9atm.cc/sec,Tube(-) 1.5 x E-8 atm.cc/sec. Tube(+)small leak 3.7xE-8 atm.cc/sec.    We repeated the helium pressure test on GE. There is a huge leak on TM2 GE circuit. The leak detector shoot up to E-7  atm.cc/sec right after the helium was applied.It went up to E-6 range in less than 1 minutes.

 

 

  1162   Friday, March 04, 2016, 12:34 David WangITEStandard OperationTM4 TM4 ITE annual leak check

Dan and I finished TM4 and ITE annual leak check on primary and secondary vacuum vessel. We found one leak on a KF25  blank off which is located on the top of the service cap. It is a low E-7 atm.cc/sec range leak. But, it is very close to turbo-pumps so ITE IG1 and other gauges are not affected by it very much. It is an easy fix. TheKF -25 center ring on the blank off  will be replaced  after vent . It be will leak checked again at CS after replacement.  That is only leak we found on TM4 and ITE primary and secondary vessel air to vaccum leak check.

Dan and I also finished the helium pressure test on all TM4 using water circuits. 70 psi helium. base LR 0.0xE-9 atm.cc/sec. All of them are leak free. No any response has been found on leak detector during test.

  1163   Friday, March 04, 2016, 13:58 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

Update Schedule according to changes.See attachment1, 2.

 Re-post it after some minor correction See attachment 3,4.

Update schedule according changes. See attachments 5,6

 update schedule according to changes. See attachment 7,8

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 5: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 6: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 7: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 8: 2016_winter_shut_down__target_hall_schedule.mpp
  1164   Monday, March 14, 2016, 11:24 David WangITE/ITW CoolingMaintenance  HALCW resin tank filter cartridges are changed today

Two of resin tank filter cartridges(supply and return) are changed today. Old cartridges and bagged and tagged. The contact field on them are 650usv/hr. The new cartridges are fiber-glass, Triumf store item. After replacement, the field on contact with the filter case are about 10 usv/hr. But the field on contact with top resin tank  has been increased from 45usv/hr  to 225 usv/hr

 The flow rate is relatively stable before and after change. See attachment

Attachment 1: 002.JPG
002.JPG
Attachment 2: 003.JPG
003.JPG
Attachment 3: 006.JPG
006.JPG
  1165   Monday, March 14, 2016, 15:22 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall Schedule

update schedule according to change. See attachment 1,2

 

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
  1168   Thursday, March 17, 2016, 14:57 David WangSouth Hot-CellRepairTM2 TM2 first round leak check in SHC

Chad and I finished the first round check on Tm2 water lines. The lines and spots checked are: Target oven + and - (front side braze joints) , Tube heater+and -(front side braze joints and water blocks), coil2 and coil 1(front side braze joints and area close to water blocks),. No leak has been found on all above of them.  The last, we checked   the GE which has the biggest leak so far. The leak detector base leak rate only can get to 4XE-9 atm.cc/sec. Chad sprayed helium very close to GE water block, and I got a quick response on leak detector. The leak rate climbed from 4Xe-9 atm.cc/sec to 1.4 atm.cc/sec. We confirmed the GE is leaking now. The exact location need to be pinpointed later once the containment box is out after the module is back to SHC. The module will be moved to TCS tomorrow morning and pressurized again there. Anders will use RGA to monitor the helium response during the check.  

  1170   Friday, March 18, 2016, 09:34 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)

I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule 130 is under construction, and will be posted later.

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.xlsx
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
  1171   Friday, March 18, 2016, 09:42 David WangConditioning StationStandard OperationTM2 TM2 vacuum sysytem has been connected at TCS

TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.

  1172   Friday, March 18, 2016, 11:43 chad fisherSouth Hot-CellStandard Operation  SiC#32 dissection

SiC#32 has been open for inspection.

Attachment 1: 20160318_105519_1.jpg
20160318_105519_1.jpg
Attachment 2: 20160318_105311.jpg
20160318_105311.jpg
Attachment 3: 20160318_105248.jpg
20160318_105248.jpg
Attachment 4: 20160318_105428.jpg
20160318_105428.jpg
  1174   Monday, March 21, 2016, 10:25 David WangConditioning StationRepairTM2 TM2 Helium pressure Test Result in TCS and ITW

TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes. 

The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr  for both ITW and TCS. The test results are:

 

 

 

 

circuit TCS Test Result (atm.cc/sec) 2016-03-021  ITW Test Result (atm.cc/sec) 2016-03-02

TCS Test Result (atm.cc/sec)

2116-11-24

Target Oven + 5.2 X E-9 1.7 X E-8 2.0 X E-9
Target Oven - 5.6 X E-9 8.7 X E-9 2.2 X E-8
Tube Heater + 3.7 X E-8 1.7 X E-8 2.3 X E -8
Tube Heater - 1.9 X E-8 1.5 X E-8 8.2 X E-8
Coil 2 (P-Q) 7.2 X E-8 6.7 X E-8 5.4 X E-9
Coil 1 (R-U) 1.4 X E-8 1.3 X E-8 2.4 X E-9
MSP 2.3 X E-7, SECOND TIME 2.5 X E-7 4 X E-9 2.4 X E-7
HS NO TEST, LINE IS OPEN TO VACUUM. GOOD, NO RESPONSE ON LD Good, 0.0 X E-9
EE 4.3 X E-9 GOOD, NO RESPONSE ON LD

3.7 X E-8

 

window 4.5 X E-9 GOOD, NO RESPONSE ON LD Good , 0.0 X E-9
GE NO TEST, CONFIRMED IN SHC MIDDLE OF E-6 RANGE No test. Blanked
       

 2016-11-24: Checked again and added result into this elog.  No essential change has been found. MSP still has the biggest leak rate. David

  1175   Monday, March 21, 2016, 11:30 David WangConditioning StationRepairTM2 TM2 and TCS vacuum pumps are stopped

I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow  moving.   

  1176   Monday, March 21, 2016, 15:27 David WangConditioning StationRepairTM2 TM2 has been disconnected at TCS

TM2 vacuum system has been disconnected at TCS. Venting is in process now.

  1179   Wednesday, March 23, 2016, 11:32 David WangSouth Hot-CellRepairTM2 TM2 Helium spray leak check on GE and MSP lines at SHC

  Chad and I did the helium spray leak check on TM2 GE and MSP water lines at SHC this morning. We confirmed the GE leak on water blocks. We can not found the MSP leak by using the helium spray since its leak rate in TCS is much smaller than GE leak.  The leak check process are as below:
Leak detector are calibrated before the check.
GE lines : Base leak rate 0.0 X E-9 atm.cc/sec, base pressure 0.0 XE-4 torr.
Chad sprayed 5 psi helium to GE lines soldering joints  for 5 second, no response on leak detector.
Chad sprayed 5 psi helium to GE lines water blocks( between blocks seal surface) for 5 seconds, Leak detector response to 8 XE-9 atm.cc/sec right away.
Chad sprayed  5 psi helium to GE lines soldering joints for 5 seconds again, No response on leak detector.
Chad sprayed 5 psi helium around the source tray and to vacuum duct for 5 seconds more, No response on leak detector.
MSP lines: Base leak rate 0.0X E-9 atm.cc/sec, base pressure 0.0 X E-4 torr.  Chad did same thing as he did on GE lines. no response on LD. Chad repeated the test and prolonged the spray time to 10 seconds, No response.
The conclusion: It is pretty clear we have a leak on GE line water blocks seal.  MSP lines leak could not be found by helium spray in SHC since it is a small leak.
 

  1180   Thursday, March 24, 2016, 13:15 David WangConditioning StationStandard OperationTM1 TM1 and TCS vacuum system has been connected

TM1 and TCS vacuum system have been connected. All turbo-pumps are started. The pumping down is fine.

  1182   Tuesday, March 29, 2016, 08:38 David WangConditioning StationStandard OperationTM1 TM1 water lines helium pressure check at TCS

TM1 water lines helium pressure check at TCS is done. 70 psi helium was applied to water circuits. Leak detector base leak rate 0.0 x E-9 atm.cc/sec, base pressure 0.0 x E-4 torr. The result shows as below:

 

 

Ta+   0.0 X E-9 atm.cc/sec 3minutes stabilizing
Ta-  0.0 X E-9 atm.cc/sec 3minutes stabilizing
Tube-  0.0 X E-9 atm.cc/sec 3minutes stabilizing
Tube+  0.0 X E-9 atm.cc/sec 3minutes stabilizing
MSP   0.0 X E-9 atm.cc/sec 3minutes stabilizing
EE   0.0X E-9 atm.cc/sec 3minutes stabilizing
HS  not tested without caps.  
Window  E-5 range,leak on stem as we knew before.  10seconds to E-5

The results is good so far as we know the window line is leak on stem in service cap. The HS will be tested later with target on.

 The service cap air to vacuum seals also have been checked. The PNG1 panel and side round panel close to shutter are leak. The o-rings on them need to be replaced.

On March 30th -2016, I doubled checked the air to vacuum seal on the TM1 service cap. The side round panel is leak free actually. The PNG1 panel is leak at the bottom side. Confirmed.

On march 31th-2016, The o-ring(1-1/ 2275) on TM1 PNG1 side panel has been replaced today. The o-ring slot and mating surfaces are cleaned, and new  o-ring is installed. The panel is put back to TM1 and all bolts are tightened.

See attachments.

Attachment 1: TM1_PNG1_panel_o-ring_replacement_001.JPG
TM1_PNG1_panel_o-ring_replacement_001.JPG
Attachment 2: TM1_PNG1_panel_o-ring_replacement_002.JPG
TM1_PNG1_panel_o-ring_replacement_002.JPG
Attachment 3: TM1_PNG1_panel_o-ring_replacement_004.JPG
TM1_PNG1_panel_o-ring_replacement_004.JPG
Attachment 4: TM1_PNG1_panel_o-ring_replacement_005.JPG
TM1_PNG1_panel_o-ring_replacement_005.JPG
Attachment 5: TM1_PNG1_panel_o-ring_replacement_006.JPG
TM1_PNG1_panel_o-ring_replacement_006.JPG
  1183   Wednesday, March 30, 2016, 08:40 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

update the schedule according to changes.See attachment1, 2.

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp