ID Date Author Category Typedown Module Target/Number Subject Text Attachments
  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule 2016 Winter shut down target hall schedule.
See attachments1,2.
 update the schedule weekly.
 6x 
  1156   Thursday, February 25, 2016, 06:48 David WangITEStandard Operation  4 Shielding blocks have been transferred from ITE to block storage area.Dan and I transferred 4 shielding blocks
from ITE to block storage area. The ITE pit
is opened now.
  
  1157   Thursday, February 25, 2016, 06:52 David WangConditioning StationStandard Operation  stop CS vacuum pumps.I stopped the conditioning station vacuum
pumps. The CS is still under vacuum without
venting.
  
  1158   Thursday, February 25, 2016, 09:27 David WangITWStandard OperationTM2 TM2 has been disconnected in ITWTM2 has been disconnected in ITW (except
vacuum lines). The vacuum system is still
operating.
  
  1159   Thursday, February 25, 2016, 09:29 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.TM4 has been disconnect in ITE(except 
vacuum lines). The ITE vacuum system is still
operating.
  
  1160   Wednesday, March 02, 2016, 09:51 David WangITWStandard OperationTM2 all water lines on TM2 and TM4 are purged.All water lines on TM2 and TM4 are purged
for upcoming water lines helium pressure
test.
  
  1161   Wednesday, March 02, 2016, 10:04 David WangITWStandard OperationTM2 Leak check on ITW and TM2.Dan and I leak checked TM2 and ITW primary
vacuum vessel. It was found a 1X E-7 atm.cc/sec
leak on top T flange seal between TM2 and
  
  1162   Friday, March 04, 2016, 12:34 David WangITEStandard OperationTM4 TM4 ITE annual leak checkDan and I finished TM4 and ITE annual leak
check on primary and secondary vacuum vessel.
We found one leak on a KF25  blank off
  
  1163   Friday, March 04, 2016, 13:58 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall ScheduleUpdate Schedule according to changes.See
attachment1, 2.
 Re-post it after some minor
 8x 
  1165   Monday, March 14, 2016, 15:22 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall Scheduleupdate schedule according to change. See
attachment 1,2
 
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1166   Wednesday, March 16, 2016, 09:20 Travis CaveITEStandard OperationTM2SiC#32module movedTM#2 with SiC#32 has been moved from the
west station to the south hot cell.
  
  1167   Wednesday, March 16, 2016, 14:23 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 removal Target Module InspectionSiC#32 has been removed from TM2. Quick
inspection shows some troubling discoloration
on the water cooled connection blocks of
 20160316_141127.jpg20160316_141146.jpg 
  1169   Friday, March 18, 2016, 08:34 Travis CaveConditioning StationStandard OperationTM2no targetmodule movedTM#2 with no target has been moved to the
conditioning station from the south hot cell.
  
  1170   Friday, March 18, 2016, 09:34 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)I would like to post the spreadsheet of
target hall schedule for beam schedule 130(Apr
to Sep) first. The MS project of TH schedule
 Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf 
  1171   Friday, March 18, 2016, 09:42 David WangConditioning StationStandard OperationTM2 TM2 vacuum sysytem has been connected at TCSTM2 vacuum system has been connected at
TCS. Started roughing pump. Everything is
good so far.
  
  1172   Friday, March 18, 2016, 11:43 chad fisherSouth Hot-CellStandard Operation  SiC#32 dissectionSiC#32 has been open for inspection.  20160318_105519_1.jpg20160318_105311.jpg20160318_105248.jpg20160318_105428.jpg 
  1173   Friday, March 18, 2016, 13:13 Travis CaveConditioning StationStandard OperationTM2SiC#32Electrical CheckElectrical checks of the TM#2 with the
old SiC#32 and without the target. See attached
PDFs.
 TM2_SiC32_postbeam.PDFTM2_elec_chk_notgt_CS.PDF 
  1177   Tuesday, March 22, 2016, 10:27 Travis CaveSpent Target VaultStandard Operation SiC#32Spent Target moveSiC#32 has been moved from the south hot
cell to the spent target storage. See attached
PDF for details.
 Vault_Storage_March_22_2016.pdf 
  1178   Wednesday, March 23, 2016, 11:00 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule movedTM#2 was moved into the south hot cell
by 08:30.
  
  1180   Thursday, March 24, 2016, 13:15 David WangConditioning StationStandard OperationTM1 TM1 and TCS vacuum system has been connected TM1 and TCS vacuum system have been connected.
All turbo-pumps are started. The pumping
down is fine.
  