  367   Monday, May 27, 2013, 16:07 Bevan MossConditioning StationStandard OperationTM4Ta #40HV conditioning The HV conditioning reached a maximum
of 44kV today before a spark took out the
canbus card. I will attach the data once
  
  368   Monday, May 27, 2013, 16:36 Bevan MossConditioning StationStandard OperationTM4Ta#40Argon Venting Started Argon venting has started. It will
be left to vent over night. 
  
  375   Tuesday, June 04, 2013, 15:34 Bevan MossConditioning StationRepair  Relay replacedESC was called out again to inspect the
chiller as it was showing the same problem
as before. This time when started one fan
  
  386   Tuesday, June 25, 2013, 14:56 Bevan MossConditioning StationStandard OperationTM1UCx#6Roughing Pumps Started The roughing pumps have been started
on the conditioning station. As it is late
in the day for David he will make the turbo
  
  398   Friday, July 05, 2013, 10:02 Bevan MossConditioning StationStandard OperationTM3No source trayTM3 module move to TCSTM3 has been moved from the south hot cell
to the conditioning station. David and I
completed the move. All went well.
  
  404   Monday, July 22, 2013, 15:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayHV testing update   I have fallen behind on the
HV testing that has been completed on TM3.
Data can be found on docushare in the TM3
  
  436   Thursday, August 29, 2013, 10:09 Bevan MossSouth Hot-CellRepairTM3 Heat Shield Circuit Leak

    

       
            
  
  438   Thursday, August 29, 2013, 17:16 Bevan MossSouth Hot-CellRepairTM3N/AHeat Shield Repair Today Chad entered the south hot
cell on work permit 2013-08-29-3 to repair
the leaking heat shield line. The heat shield
  
  439   Friday, August 30, 2013, 10:27 Bevan MossSouth Hot-CellRepairTM3N/AHeat Shield Repair

    

       
            
  
  440   Friday, August 30, 2013, 14:55 Bevan MossSouth Hot-CellRepairTM3N/AHeat Shield Repair

    

       
            
  
  441   Wednesday, September 04, 2013, 12:21 Bevan MossSouth Hot-CellRepairTM3 Ante-room work September 3rd
David Wang and myself lowered the
leak testing cart into the Ante room and
 IMG_0983.JPG 
  444   Friday, September 06, 2013, 16:41 Bevan MossSouth Hot-CellDevelopmentTM3 C-Seal crush investigation  Today Maico completed the new leak
testing tool and blank off. He tested  them
with C-seals without springs and all was
 6x 
  450   Wednesday, September 11, 2013, 15:37 Bevan MossSouth Hot-CellRepairTM3 C-Seal leak checking and repair This e-log is to cover the work completed
from September 9th until the 11th. 
September 9th
  
  455   Tuesday, September 17, 2013, 14:36 Bevan MossSouth Hot-CellStandard OperationTM3 Containment Box has been removed The containment box has been removed.
Tomorrow the wiring harness will be installed.
  
  458   Thursday, September 19, 2013, 15:56 Bevan MossSouth Hot-CellRepairTM3 Activities for September 18th and 19thSeptember 18th
The wiring harness was completed
by Maico and Travis today (see pics) and
 IMG_1127.JPGIMG_1134.JPGIMG_1137.JPGIMG_1139.JPGIMG_1143.JPG 
  460   Monday, September 23, 2013, 16:10 Bevan MossSouth Hot-CellRepairTM3 Activities Sept 20 - 23 2013 September 20th
Today was a trying day. When attempting
to make the water line  connections for the
  
  462   Tuesday, September 24, 2013, 14:46 Bevan MossSouth Hot-CellRepair  Right manipulator repair    
  468   Thursday, September 26, 2013, 14:31 Bevan MossSouth Hot-CellRepairTM3NiO#2Activities September 24 - 25September 24
 After the manipulator repair
Maico installed the NiO#2 onto the target
 elec_check.pdf 
  469   Thursday, September 26, 2013, 14:37 Bevan MossConditioning StationStandard OperationTM3NiO#2Leak check / Pressure Test

    

       
            
  
  470   Thursday, September 26, 2013, 14:42 Bevan MossSouth Hot-CellRepairTM3NiO#2Activities September 24 - 25

    

       
            
  