  288   Thursday, April 04, 2013, 12:07 Bevan MossConditioning StationStandard OperationTM1Ta #39Roughing started Roughing started at 12:06. It was
believed there was a problem with the compressed
air but there was none, TM1 doesn't leak
  
  287   Thursday, April 04, 2013, 11:06 Travis CaveSouth Hot-CellStandard OperationTM1Ta#39module moveTM#1 with Ta#39 has been moved from the
south hot cell to the conditioning station
move went well.
  
  286   Wednesday, April 03, 2013, 14:39 Travis CaveSouth Hot-CellStandard OperationTM1Ta#39Electrical checkElectrical check on TM#1 with Ta#39 installed
at the south hot cell. Target passed the
electrical checks, see attached pdf for details.
 TM1_Ta39_SHC_ELEC_CHK.PDF 
  285   Wednesday, April 03, 2013, 13:28 chad fisherSouth Hot-CellStandard OperationTM1Ta#39Ta#39 installedTa#39 has been installed onto TM1.   
  284   Wednesday, April 03, 2013, 12:26 David WangITEMaintenanceTM4Sic LIS/RFQLeak check on ITE TM4.TM 4 had been leak check in ITE due to
  relatively high PNG1 and IG1 readings.All
TM4 primary and secondary  vessel air
  
  283   Wednesday, April 03, 2013, 10:59 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moveTM#1 has been moved from the south west
silo to the south hot cell, move went well.
  
  282   Tuesday, April 02, 2013, 10:07 chad fisherSouth Hot-CellStandard OperationTM1Ta#39Ta#39 inserted into hot cellTa#39 has been inserted into the hot cell
in preparation for TM1 target change.
  
  281   Wednesday, March 27, 2013, 12:08 David WangSouth Hot-CellStandard OperationTM4Sic LIS-RFQTM4 heat shield circuit leak check with SiC LIS-RFQ targetChad and I did the TM4 heat shield leak
check yesterday at SHC. The leak detector
was pumped to 4.6 xE-9atm.cc/sec, and 0.0xE-4
  
  280   Wednesday, March 27, 2013, 11:49 David WangITEStandard OperationTM4Sic LIS-RFQ Connected TM4 in ITETM4 has been reconnected to ITE after the
module moving. The roughing is started .
The water will be supplied to ITE after 
  
  279   Wednesday, March 27, 2013, 10:44 Travis CaveITEStandard OperationTM4SiC#28 (RFQ Target)module moveTM#4 with SiC#28 has been moved from the
south hot cell to the east target station
move went well.
  
  278   Tuesday, March 26, 2013, 14:17 Travis CaveSouth Hot-CellStandard OperationTM4SiC#28 (RFQ Target)Electrical checkElectrical check of TM#4 SiC#28 (RFQ Target)
has been completed. It passed the standard
electrical checks for the target part, but
 TM4_SiC28_RFQ_SHC_ELEC_CHK.PDF 
  277   Monday, March 25, 2013, 14:19 Travis CaveConditioning StationStandard OperationTM4CS Test Target #1module moveTM#4 with the CS Test target has been moved
from the conditioning station to the south
hot cell. Move went well.
  
  276   Monday, March 25, 2013, 10:59 Bevan MossConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 Completed

    

       
            
 IRH1511.pdfISK4574D-rev7.pdf 
  275   Monday, March 25, 2013, 09:35 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Cooling Package and Vacuum Stopped The cooling package and vacuum was
stopped today at 9:26 so the module can be
move.
  
  274   Saturday, March 23, 2013, 18:14 Aurelia LaxdalConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 CompletedAfter few hickups the TCS was successfuly
commissioned.
In the morning, in the middle of
  
  273   Friday, March 22, 2013, 18:49 Aurelia LaxdalConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 1Today, the commissioning of the TCS went
well. The water/vacuum interlocks were checked
OK. Then, the TCS was HV conditioned up to
  
  272   Wednesday, March 20, 2013, 08:19 David WangConditioning StationRepairTM4 Leak check new installed TM4 TP1 at conditioning station.I leak checked new installed TM4 TP1 at
conditioning station. The CS vacuum gauges
reading were at 1.0-1.5xE-6 torr . Leak detector
  
  271   Tuesday, March 19, 2013, 13:49 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Tubros Started Turbo Pumps have been started and
are in normal operation. TP1 which has recently
been replaced was started in soft start and
  
  270   Tuesday, March 19, 2013, 09:55 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Turbo pump 1 replaced roughing started David replaced the broken turbo pump
this morning and I have started roughing
at 9:54.
  
  269   Monday, March 18, 2013, 15:28 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Vented With Argon The conditioning station has been
vented with argon. Time taken is not known
but it is less than 3 hours. See attached
 Vented_with_Argon.JPG 