132
|
Tuesday, April 20, 2021, 15:02 |
Adam Newsome | Carrier | Development | Emergency Trolley Rescue Winch: Installed and Tested | An emergency trolley rescue winch (TRH1527)
was developed for the purposes of retrieving
trolleys from the cyclotron tank whose radial |
|
133
|
Wednesday, May 05, 2021, 12:20 |
Adam Newsome | Infrastructure | Development | Cyclotron RH Control Room: Outlets Installed | The following outlets were installed by
Electrical Services Group in order to facilitate
upgrading power supplies for Cyclotron Remote |
|
134
|
Wednesday, June 16, 2021, 09:59 |
Adam Newsome | Service Bridge | Development | Bridge Lift Mechanism Refurbishment (Phase 1 of 2) - Complete | The following items from Phase 1 of 2 of
Bridge Lift Mechanism Refurbishment (O504)
are complete: |
|
135
|
Tuesday, August 31, 2021, 14:28 |
Adam Newsome | Trolleys serviced | Development | Upper Resonator Trolley - Finger Cylinders Replaced | The two support fingers on the upper resonator
trolley were bent due to excessive loading
during cylinder toggling. |
|
138
|
Tuesday, February 08, 2022, 11:39 |
Adam Newsome | Cyclotron | Development | Radiation Survey - sampling rate error | When attempting to perform the radiation
survey, the program displayed an error at
startup stating that the software was not |
|
141
|
Wednesday, May 04, 2022, 12:07 |
Adam Newsome | Trolley | Development | Tool Trolley: Brass air fittings replacement complete | All of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are |
|
145
|
Wednesday, June 29, 2022, 12:12 |
Adam Newsome | Probe | Development | LE1/LE2 Probe Frame - Updates | The LE1/LE2 Probe Frame was mounted on
the Upper Resonator Trolley in the mockup
with the intention of confirming functionality |
|
147
|
Friday, January 27, 2023, 12:12 |
Adam Newsome | Infrastructure | Development | Vault crane - inspection, remote pendant installation | The vault crane annual inspection was completed
by Tom Kauss.
|
|
154
|
Friday, July 28, 2023, 12:05 |
Adam Newsome | Cyclotron | Development | Maintenance ladders: end caps added | The original end feet and end caps were
removed from the maintenance ladders and
replaced by new end caps (TRH1637). |
|
155
|
Thursday, August 03, 2023, 10:43 |
Adam Newsome | Trolley | Development | Previous generation video trolley decommissioned | The "old" video trolley featuring
scissor mechanism and DSLR camera has officially
been decommissioned. Going forward, Video |
|
156
|
Thursday, September 07, 2023, 13:21 |
Jason Zhang | Service Bridge | Development | Outrigger #1 and #2 individual testing complete | Outrigger #1 and #2 have had their controls
system overhauled as part of the O503 project.
The previous controls enclosure and the elements |
|
159
|
Wednesday, October 18, 2023, 12:35 |
Jason Zhang | Service Bridge | Development | O503 Bridge and Outrigger integration testing | Service bridge, Outrigger #1, and
Outrigger #2 have had the controls system
migrated to PLC controls. The 5069-AENTR |
|
191
|
Wednesday, October 16, 2024, 11:37 |
Adam Newsome | Service Bridge | Development | Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete | See previous e-log for phase 1: e-log
134
|
6x |