Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Cyclotron, Page 11 of 11  Not logged in ELOG logo
ID Date Author Category Typedown Subject Text Attachments
  191   Wednesday, October 16, 2024, 11:37 Adam NewsomeService BridgeDevelopment Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete See previous e-log for phase 1: e-log
134
 
 6x 
  197   Wednesday, February 19, 2025, 15:29 Adam NewsomeCyclotronDevelopmentLift Trolley - upgraded controls commissioning completeNewly implemented PLC-based controls hardware
and software for the Lift Trolley was commissioned
between January 30 - February 7, 2025, mostly
  
ELOG V2.9.2-2455