38
|
Tuesday, February 25, 2014, 15:00 |
Travis Cave | Shielding | Standard Operation | shields | Started on the removal of shields. |
|
39
|
Wednesday, February 26, 2014, 14:55 |
Travis Cave | Shielding | Standard Operation | shields | More shields have been removed from the
cyclotron only 16 remain. I was also noted
that the lift trolley is making an odd noise |
|
40
|
Monday, March 03, 2014, 13:09 |
Travis Cave | Cyclotron | Standard Operation | shields | all shields, porthole covers and ladder
out and copper blockers in. Some conmination
was found on the pads of the ladders (about |
|
41
|
Monday, March 03, 2014, 15:07 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Down Report Monday 3-March-2014 | The Cyclotron Lid Down was successfully
completed today on Work Permit C2014-03-03-6.
The system only tripped twice on |
|
42
|
Tuesday, April 08, 2014, 10:45 |
Travis Cave | Shielding | Standard Operation | Large shield door on the RH B2 level | The large shield door on the RH B2 level
of the remote handling building has been
shut. |
|
44
|
Wednesday, July 02, 2014, 16:46 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up Report for 27 June 2014 | The cyclotron lid was raised on June 27th,
2014. Start time was 1:05pm end time
was 2:17pm (good!) Dan McDonald collected |
|
45
|
Friday, July 04, 2014, 07:21 |
Dan McDonald | Elevation Jack | Standard Operation | Cyclotron lid down July-2- 2014 | Cyclotron lid down was successfully completed
on July 2 2014. Lid went partially down before
jack nine had to be jogged to catch up to |
|
49
|
Tuesday, January 27, 2015, 11:39 |
Grant Minor | Elevation Jack | Standard Operation | Lid-Up Report 26 Jan 2015 |
Normal
0
|
|
50
|
Tuesday, January 27, 2015, 14:40 |
Travis Cave | Cyclotron | Standard Operation | Day one of in tank work | Day one of RH in tank work for the cyclotron
(shields and blockers stuff like that) many
pictures were taken. |
|
51
|
Wednesday, January 28, 2015, 14:33 |
Travis Cave | Cyclotron | Standard Operation | Day two of in tank work | All copper blocker removed from the cyclotron
and first radiation survey done. Shields
start tomorrow. |
|
52
|
Thursday, January 29, 2015, 14:53 |
Travis Cave | Cyclotron | Standard Operation | Day three of in tank work | Over 50% of the shields are in some 700's
left and the monitor box covers. |
|
53
|
Friday, January 30, 2015, 15:02 |
Travis Cave | Cyclotron | Standard Operation | Day four of in tank work | All shields, ladders and pothole covers
are in. One rad survey left to do. |
|
54
|
Monday, February 02, 2015, 14:28 |
Travis Cave | Cyclotron | Standard Operation | Day five of in tank work | Final Radiation Survey done. All in tank
work completed bridge removed from the tank. |
|
55
|
Wednesday, February 04, 2015, 13:57 |
Travis Cave | Cyclotron | Standard Operation | 2C removal | 2C has been removed from the cyclotron. |
|
57
|
Tuesday, February 17, 2015, 11:28 |
Travis Cave | Cyclotron | Standard Operation | 2C Installation | 2C extraction probe has been re-installed
in the cyclotron. After some problems on
the first install attempt, do to a busted |
|
58
|
Friday, March 06, 2015, 14:38 |
Travis Cave | Cyclotron | Standard Operation | Shield Removal | All shields and ladders have been removed
from the tank, all the port holes have been
uncovered, the tank seal has been vacuumed, |
|
59
|
Friday, March 06, 2015, 16:42 |
Grant Minor | Elevation Jack | Standard Operation | Lid-Down Report 6-March-2015 | Lid down started around 2:30 pm today (March
6th, 2015)
Master Start: 47422 |
|
63
|
Thursday, March 19, 2015, 13:14 |
maicodallavalle | Shielding | Standard Operation | Remote Handling B2 level Shielding door | The Remote Handling B2 level Shielding
door has been closed. |
|
64
|
Thursday, March 26, 2015, 15:48 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up 26 March 2015 | Lid was raised today (2nd time during 2015
shutdown) for additional inflector work.
Dan and Maico report that the lid |
|
66
|
Friday, March 27, 2015, 11:25 |
Travis Cave | Cyclotron | Standard Operation | Copper Blockers | Copper Blockers have been removed from
the cyclotron and one ladder has been installed. |
|