ID Date Author Categorydown Type Subject
  84   Friday, April 17, 2015, 15:11 Keith C NgM9Developmentm9 t2 alignment job

Today: Restored filler shielding in T2 M9 Q1Q2 hole.

- Blocks marked with beam direction on this installation. Active faces point toward target monument.

20150417_m9t2_P1030353.JPG20150417_m9t2_P1030354.JPG20150417_m9t2_P1030355.JPG

 

- Checked spring eye spacing after installation under vacuum overnight, appears to be equal on both sides. 1/16" spacing.

20150417_m9t2_P1030366.JPG20150417_m9t2_P1030365.JPG20150417_m9t2_P1030364.JPG

 

- Remote handling equipment has been removed from work area and restoration of shelding around T2 has begun as of 15:00.

  94   Monday, January 30, 2017, 12:01 Keith C NgM9DevelopmentT2 leak check with vac group

Week of Jan 23 to 27:

 

- Uncovered shielding around T2 M9 area.

- Initially set up remote handling bridge thing but stopped because of the stacked 12 x 2 x 3 blocks, looks precariously tall, wobbly. Suggested to postpone leak checking work and configure bridge to a more usual setup for safety.

 - Moved some bridges around, put some lights in cable tray area.

- Beamlines tied in M9 floor markings to the meson hall grid on the 18th

- Beamlines tied in B1 alignment to meson hall grid on 26th

- He leak checked around T2 area with Dimo and Edi, nothing found. Suspicious leak at M20 scraper area but cannot rule out drift toward the collimator joint. Will need to reassess later on in the shutdown when we go to that area.

- Doug and electricians looked around the cable tray feeding to M9, via tunnel and mezzanine.

  95   Wednesday, February 01, 2017, 15:34 Keith C NgM9DevelopmentT2 M9 Setup

Finished setting up work area around T2 M9 front end.

 

Attachment 1: t2m920170201_143714_1032.jpg
t2m920170201_143714_1032.jpg
  96   Friday, February 03, 2017, 14:57 Keith C NgM9DevelopmentRemoving shield blocks and leak check results.

Removed temporary shielding blocks from M9 hole and placed in temporary bunker. Capped with 18' shielding block. Blank off ready to be removed and target jigs ready to be installed, weather permitting.

Raw leak check results from vacuum group attached as pdf.

 

Attachment 1: t2m920170203_140114_0604.jpg
t2m920170203_140114_0604.jpg
Attachment 2: t2m920170203_120314_0686.jpg
t2m920170203_120314_0686.jpg
Attachment 3: Local_leak_check_Jan_27_2017.pdf
Local_leak_check_Jan_27_2017.pdf Local_leak_check_Jan_27_2017.pdf
  97   Tuesday, February 07, 2017, 15:36 Keith C NgM9Developmentt2 m9 job

 - Removed blank off from t2 m9 port, had to pry off with screw driver via spring ears. Clean removal it seems.

- Blank off is 200 uSv @ .5 m, 5000 CPM above bg.

- looks like 2 knife steps all around with oozing on the left and right, 0 and 180 deg positions. 0 and 180 look like 2.5 steps. Looks like it took one turn to remove/loosen blank off.

- Junk indium at bottom of exit port still present, indium knife edge seems clean. Ribbon stayed in blank off.

Attachment 1: 20170207_rh_shutdown_log.pdf
20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf 20170207_rh_shutdown_log.pdf
  98   Thursday, February 09, 2017, 16:14 Keith C NgM9Developmentt2 m9 alignment

Prepared m9 and b1 flanges for accepting their target jigs. The target jigs need to be reset by alignment group, 15" was bumped and 8" lost 2 of the target balls into the beam line. Reflector balls were recovered with a magnet on a stick, contaminated with 250 CPM, need alignment group to decontaminate and clean them before use and reset the two jigs.

Syd installed two springs on the 8" target jig and only one spring is needed.

Attachment 1: 20170209_t2m9alignment_P1030588.JPG
20170209_t2m9alignment_P1030588.JPG
Attachment 2: 20170209_t2m9alignment_P1030586.JPG
20170209_t2m9alignment_P1030586.JPG
  99   Friday, February 10, 2017, 15:53 Keith C NgM9Developmentt2 m9 job

Installed all jigs and Alignment group did their shoots successfully. Used individual pins on the 15" target jig and worked ok. 8" target jig has some previously undiscovered issues from the previous shoot from 2015 but did not affect this shoot.

Attachment 1: 20170210_t2m9alignment_P1030604.JPG
20170210_t2m9alignment_P1030604.JPG
  100   Tuesday, February 14, 2017, 16:08 Keith C NgM9DevelopmentT2 M9 2015 vs 2017 comparison

Attached a quick comparison of M9 exit port flanges WRT indium remnants: looks roughly the same. Will attempt to install blanking plate tomorrow morning.

Attachment 1: 20170214_t2m9alignmentflangecomparison.pdf
20170214_t2m9alignmentflangecomparison.pdf 20170214_t2m9alignmentflangecomparison.pdf 20170214_t2m9alignmentflangecomparison.pdf 20170214_t2m9alignmentflangecomparison.pdf
  101   Wednesday, February 15, 2017, 15:36 Keith C NgM9Developmentt2 m9 blank off

Installed the blank off on the T2 M9 exit port:

Blank off 2013 installation procedure: 2.5 turns of the preload nut, after pins are engaged and springs are at free length.

Blank off 2015 installation procedure: 1.5 turns of the preload nut, after pins are engaged and springs are at free length. (one less turn for insurance?)

2017 (this year) installed blanking plate via hammering/tapping pins into place:

  1. Spring eyes were set at spring free length and then placed down
  2. Pins did not slide through eyes as was expected.
  3. Nuts were then backed off roughly 1 turn, then pins were lightly tapped down into place
  4. Nuts then turned back to zero/starting position
  5. Then alternating east west by .5 turn tightened to 1.5 turns, 1/2 turn indicated by half bar pen marking.

This year different than prior years due to tapping pins into place rather than backing off eyelet nuts and sliding pins into place *then* tightening to zero point and then tightening to preload.

Blank off installed at 11:15, vacuum group not able to pump on T2 until tomorrow.

Attachment 1: 20170215_shutdown_log_photos.pdf
20170215_shutdown_log_photos.pdf 20170215_shutdown_log_photos.pdf 20170215_shutdown_log_photos.pdf 20170215_shutdown_log_photos.pdf
  102   Friday, February 17, 2017, 13:33 Keith C NgM9DevelopmentT2 M9 vacuum

Leak checked the blank off at T2 M9 exit port with Dimo Y. and Edi D.V. (Vac Group) and they confirm it is leak tight. Blank off installed on the 15th, pumping started on morning of the 16th and leak checked today in the morning on the 17th.

Starting to clean up work area.

  103   Monday, February 20, 2017, 15:58 Keith C NgM9Developmentt2 m9 job wrap up

Restored shielding to T2 M9 void, blocks seem more crooked compared to previous years.

Attachment 1: 20170220_t2m9alignment_P1030616.JPG
20170220_t2m9alignment_P1030616.JPG
Attachment 2: 20170220_t2m9alignment_P1030621.JPG
20170220_t2m9alignment_P1030621.JPG
  112   Tuesday, March 13, 2018, 15:36 Keith C NgM9Standard Operationm9 alignment work

Set up shielding canyon for M9 laser tracker job.

dms.jpg

 

Fill shielding blocks are not removed yet, to be done tomorrow.

 

  113   Thursday, March 15, 2018, 15:48 Keith C NgM9Maintenancem9 t2 alignment job

Blank off removed this morning, video recorded the T2 flange,B1 flange and B1 vacuum box interior. Blank off is 150 uSv/h @ .5m, 3 mSv/h on contact at the spring eye ears. Not swiped yet, not tagged. Currently tucked between an 18' shield block and the ME27 block.

Waiting for beam lines to install the target spheres on the target jigs, expecting to install them tomorrow.

  114   Friday, March 16, 2018, 13:39 Keith C NgM9Maintenancet2 m9 port inspection

Video imaged T2 port post blank off removal, looks roughly the same as last year. Knife edge looks clean.

Attached composite photo of flange face, ring is a stand off to maintain focus distance to camera. Also attached partial composite image of 2017 video inspection.

Attachment 1: 2018_t2m9flangeinspection2.jpg
2018_t2m9flangeinspection2.jpg
Attachment 2: 2017_t2m9flangeinspection.jpg
2017_t2m9flangeinspection.jpg
  115   Wednesday, March 21, 2018, 15:22 Keith C NgM9Repairt2 m9 laser tracker jigs

Installed the remaining laser tracker jigs for beam lines. No issues. Made sure 8" target the mounting poles did not interfere with each other and pin drive was engaged with no issues.

 

Attachment 1: 20180321_t2m9_P1030966.JPG
20180321_t2m9_P1030966.JPG
Attachment 2: 20180321_t2m9_P1030967.JPG
20180321_t2m9_P1030967.JPG
Attachment 3: 20180321_t2m9_P1030968.JPG
20180321_t2m9_P1030968.JPG
  116   Monday, March 26, 2018, 15:57 Keith C NgM9Maintenancet2 m9 laser tracker alignment

Removed all Leica tracker targets from M9 pit, I will proceed with blanking off T2 exit port sometime this week. Alignment group has taken possession of their laser equipment and the target jigs.

  117   Tuesday, March 27, 2018, 15:08 Keith C NgM9Standard Operationt2 m9 port blank off

1. Blank off installed 11:40 with Dan McDonald, east spring ear looks 'deeper" than west.

- Reused all hardware from last install, most active hardware was around 10 mSv/h on contact

- Zero point was at the 1/2 turn marker pen mark

- Installed at 1.5 turns from "finger tight" zero.

 

2. Spring eye zero set on a spare flange with spare pins.

- backed off 1/2 turn then mounted to exit port.

- tightened .5 turn to get to zero, then 1.5 turns on east and west sides to seal, in increments of .5 turns alternating.

 

3. Called Edi to start pumping on T2 at 12:50

Attachment 1: 20180327_t2m9_P1030978.JPG
20180327_t2m9_P1030978.JPG
Attachment 2: 20180327_t2m9_P1030979.JPG
20180327_t2m9_P1030979.JPG
  118   Thursday, March 29, 2018, 15:15 Keith C NgM9Maintenancet2 m9 port blank off

Today leak checked the M9 exit port with Edi and we found no leaks. The usual delayed helium response in the M20/Collimator B/ M8(?) area is still persistent, however Edi says the vacuum level at T2 is the same as before.

Shielding should be restored next week.

 

  121   Tuesday, June 11, 2019, 14:56 Keith C NgM9DevelopmentM9 B1 seal notes from 1988

 Found original installation notes for the initial installation of M9 Q1Q2 generation 2 in 1988.

Dated May 17th there is a notation that the 15 inch indium ring was loaded with "Gummy Mag". Note that the rationale for using an elastomer seal in an indium knife application is still unknown.

Attachment 1: m9_b1_seal_deans_notes_page_1.pdf
m9_b1_seal_deans_notes_page_1.pdf
Attachment 2: M9_B1_seal_Deans_Notes_Page_2.pdf
M9_B1_seal_Deans_Notes_Page_2.pdf
  124   Monday, February 24, 2020, 15:13 Keith C NgM9Repairm9 q1q2 repair laser tracker shoot

Beamlines shot the position of the M9 T2 port and B1 flange for setting the M9 test stand flanges today. We removed the target jigs after this was done.

Attachment 1: 20200224_m9project_P1040686.JPG
20200224_m9project_P1040686.JPG
Attachment 2: 20200224_m9project_P1040688.JPG
20200224_m9project_P1040688.JPG