Week of Jan 23 to 27:

 

- Uncovered shielding around T2 M9 area.

- Initially set up remote handling bridge thing but stopped because of the stacked 12 x 2 x 3 blocks, looks precariously tall, wobbly. Suggested to postpone leak checking work and configure bridge to a more usual setup for safety.

 - Moved some bridges around, put some lights in cable tray area.

- Beamlines tied in M9 floor markings to the meson hall grid on the 18th

- Beamlines tied in B1 alignment to meson hall grid on 26th

- He leak checked around T2 area with Dimo and Edi, nothing found. Suspicious leak at M20 scraper area but cannot rule out drift toward the collimator joint. Will need to reassess later on in the shutdown when we go to that area.

- Doug and electricians looked around the cable tray feeding to M9, via tunnel and mezzanine.