Entry  Thursday, February 14, 2013, 15:43, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG
Removed 8" rubber test rings from M9 T2 joint. Rings moved to RH warm cell. Radiation levels were 70 µSv on contact 1.7 µSv @ 1/2 m.
Entry  Friday, February 15, 2013, 14:29, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG
Beam lines group purged M9 Q1 Q2 magnets and water lines in preparation of disconnecting water services to those magnets, done in morning.
- Note: Q15 protueus paddle wheel was replaced after finding it was worn
 
Entry  Tuesday, February 19, 2013, 16:46, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130219_m9q1q2remove_IMG_0206.JPG
Determined M9 Q2 service stand supply connector was slowly leaking.
- Ball valve to the supply was leaking through allowing trace amounts of water through.
- System was bled again and pressure relieved, leak appears to have stopped.
Entry  Monday, March 04, 2013, 16:48, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 6x
Preparing for M9 Q1,2 move:
1. Re-arranged/organized cables on top of magnet.
Entry  Thursday, February 21, 2013, 17:02, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, joint dissassembly 
CUALCW system water loss was not from 1A triplet. Q15 Q16 held static  pressure at 90 psi since 9 am until 17:00. Holding with very minimal  change in
pressure. Q14 reading 64 psi as of 17:00. D. Preddy informs all other systems leak tight.
 
Entry  Monday, February 18, 2013, 16:24, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, electrical and water disconnected 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG
Today, re-arranged electrical wiring on Q1 Q2 magnet away from Q2 indium joint. Cable bundles were bundled as neatly as possible.
- One of the klixon thermal switch wires broke off while the cable bundles were being organized. See photo.
 
Entry  Monday, February 25, 2013, 16:37, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, Q2 seal disassembly 7x
Removed Q2 15" indium seal ring, discovered seal contained rubber on both sides instead of indium.
- Some kind of oil residue seen at the bottom of the sealing ring and inside of the Q2 vacuum box. (Note: Oil residue was from downstream vacuum
roughing pumps. They were connected when T2 M9 joint was leaking. Oil got into the vacuum pump back streamed into the beam line.)
Entry  Friday, February 22, 2013, 17:27, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, Q2 joint dissassembly 20130222_m9q1q2remove_P1020840.JPG20130222_m9q1q2remove_P1020832.JPG20130222_m9q1q2remove_P1020831.JPG
M9 Q2 15" pin drive was removed and disconnected.
- Pin drive retention screw had to be completely removed to be able to remove pin drive completely.
- Had to make tools to remove pin drive and retention screw, see photos.
Entry  Tuesday, June 11, 2019, 14:56, Keith C Ng, M9, Development, M9 B1 seal notes from 1988 m9_b1_seal_deans_notes_page_1.pdfM9_B1_seal_Deans_Notes_Page_2.pdf
 Found original installation notes for the initial installation of M9 Q1Q2 generation 2 in 1988.

Dated May 17th there is a notation that the 15 inch indium ring was loaded with "Gummy Mag". Note that the rationale for using an elastomer
Entry  Friday, March 06, 2020, 13:36, Keith C Ng, M9, Repair, M9 B1 moved to warm cell 2020_M9_B1_field_survey_out_of_channel.pdf
 The M9 B1 was removed from the M9 channel surveyed and moved to the remote handling warm cell for refurbishment.
The warm cell is currently locked. Remote Handling should be contacted if access is needed to B1.
A field map of B1 is attached as a pdf file.
Entry  Thursday, May 24, 2012, 18:59, Grant Minor, M20, Repair, M20 front-end leak vacuum check T2/Q1/Q2/Scraper 6x


Normal
0




false
false
false

EN-CA
X-NONE
X-NONE

Entry  Thursday, April 25, 2019, 11:13, Keith C Ng, M20, Repair, M20 Q2 repair notes 2019_shutdown_m20_q2_repair_notes.pdf
See attached scan for repair notes regarding M20 Q2 during the 2019 winter shutdown. The repair method for M20 Q2 was instigated by Doug Preddy and Beamlines
group. Cooling line was blanked off during the 2019 winter shutdown in order to keep the M20 beamline running without removing the magnet and doing a complete
repair on the leaking coil. 
Entry  Tuesday, February 17, 2015, 16:02, Keith C Ng, Primary Beamlines, Development, M13Q1Q2 vacuum box anchor (part of UCN work) 
The replacement pin drive anchor (see TB22300) for M13 Q1Q2 vacuum box lowered into initial position. The original B1 base plate was able to rock when
weight was placed upon it; A concrete block was used to counterweight the base while the new pin drive was being installed. The pindrive has not been adjusted
into final position.
Entry  Friday, February 20, 2015, 16:28, Keith C Ng, Primary Beamlines, Development, M13Q1Q2 vacuum box anchor (part of UCN work) 
Installed Q1Q2 pin drive and attempted to align it to the vacuum box. Spent majority of the day trying to align the pin drive/anchor.
- Pneumatic drive does not actuate smoothly, appears to be binding/catching, possibly due to some kind of misalignment, issues with the pneumatics.
A 1" space between T1 and Q1 flanges has been set but has a slight taper, starting 1" wide on the north east side tapering down by ~1/16 (to
Entry  Monday, February 23, 2015, 15:57, Keith C Ng, Primary Beamlines, Development, M13Q1Q2 blank off (part of UCN work) 
"Hector" shield block installed into place, Q1Q2 Vacuum box still actuates normally. It does not appear that the position of the pin drive
has shifted. Some additional shielding steel is to be placed on top of the shield block once RH setup is removed.
Remote handling equipment installed around T1 ready to install indium blanking plate between T1 and M13Q1.
Entry  Thursday, February 26, 2015, 16:22, Keith C Ng, Primary Beamlines, Development, M13Q1Q2 blank off (part of UCN work) 
He leak checked T1M13Q1 joint, is leak tight.
 - Detected a small leak in nearby M15 slits box. 4.3x10E-9 atm cc/sec was highest leak rate recorded (Vac group says is small leak, okay
to run).
Entry  Tuesday, October 16, 2012, 19:47, Grant Minor, M9, Repair, Inspection of failed double-indium thru-ring TB22148 TB22148_thru_ring_inspT2_15oct2012.pdfTB22148_thru_ring_inspQ1_15oct2012.pdf
See inspection notes attached for failed M9T2 double-indium thru-ring TB22148, inspected on Oct 15th 2012.
Ring was approximately 3 mSv/hr on contact and 100 uSv/hr at 0.5 m.
Total dose accumulated during inspection on dosimeter 122 was 0.1 mSv
Entry  Friday, February 13, 2015, 15:10, Keith C Ng, Primary Beamlines, Development, IVM3-IVQ4 indium joint section (WR #2686) 20150213_ucnbuild_IMG_1304.JPG20150213_ucnbuild_IMG_1305.JPG20150213_ucnbuild_IMG_1308.JPG
Installed 4" indium seal at 1VM3 to IVQ4. No real problems with installation.
 
Entry  Friday, October 19, 2012, 18:21, Grant Minor, M9, Development, 8" double-ring test samples of EPDM and BUNA-N (Nitrile) BC_RUBBER_SUPPLY_PS_VA-B18799.pdf20121019_RH2_02_0025.JPG20121019_RH2_02_0027.JPG20121019_RH2_02_0029.JPG20121019_RH2_02_0031.JPG
Today I picked up two 2FT x 4Ft x 0.125" thick strips of stock EPDM and BUNA-N (Nitrile) material from BC Rubber Supply.  A copy of the Packing
Slip is attached.  Here is the information from the Sample Sheet:
 
Entry  Friday, January 29, 2016, 17:08, Keith C Ng, Primary Beamlines, Maintenance, 4VVR1 Removal 
Today:
Disconnected and removed 4VVR1 gate valve and removed from beamline.
- Pin drives removed and stored in bags near by