  23   Friday, January 18, 2013, 14:40 Keith C NgPrimary BeamlinesRepair1A triplet repairCompleted uncovering
shielding and RH setup over 1A Q14 triplet
area, see photo for RH setup.
 20130118_tripletrepair_RHB_5431-web_m.jpg 
  24   Tuesday, January 22, 2013, 16:02 Keith C NgPrimary BeamlinesRepair1A triplet repair1.5 day work delay due to plant group unavailable
on the 21st of January. Gardner air compressor
was being moved.
 20130122_tripletrepair_IMG_0018_webm.jpg 
  25   Wednesday, January 23, 2013, 15:51 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued work on finding ground fault
in 1A triplet magnets;
 
 20130123_tripletrepair_P1020666.JPG20130123_tripletrepair_P1020664.JPG20130123_tripletrepair_P1020669.JPG 
  26   Thursday, January 24, 2013, 17:05 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued with work on finding ground fault
on 1A triplet;
 
 20130124_tripletrepair_IMG_0047.JPG20130122_tripletrepair_IMG_0011.JPG20130124_tripletrepair_IMG_0040.JPG 
  27   Friday, January 25, 2013, 15:15 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Today: Uncovered 1A triplet cable chase
and reconfigured shielding. D. Preddy will
continue with diagnosing ground fault on
 20130125_tripletrepair_IMG_0071.JPG20130125_tripletrepair_IMG_0067.JPG 
  28   Monday, January 28, 2013, 16:28 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Rad survey map from last Friday (25 January)
here.
 
 6x 
  29   Tuesday, January 29, 2013, 16:28 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Restored shielding over 1A triplet chase.
 
Uncovered Q16 and set up RH bridge
  
  30   Wednesday, January 30, 2013, 16:46 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Cut and removed asymmetric steering cables
from Q14 and 16, cables are no longer resting
on magnet power bus bars.
 20130130_tripletrepair_P1020683.JPG20130130_tripletrepair_IMG_0123.JPG20130130_tripletrepair_P1020686.JPG20130130_tripletrepair_IMG_0118.JPG20130130_tripletrepair_P1020697.JPG 
  31   Friday, February 01, 2013, 14:15 Keith C NgPrimary BeamlinesMaintenanceM9 Q1 Q2; storage pit assessmentUncovered radioactive waste storage pit
to see contents. Assessing viability of moving
contents inside to facilitate storage of
 20130201_radwastepit_P1020704.JPG20130201_radwastepit_P1020720.JPG20130201_radwastepit_P1020736.JPG20130201_radwastepit_RHB_5449.JPG 
  32   Monday, February 04, 2013, 16:04 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Restored 1A triplet shielding and removed
RH shielding.
 
 20130204_tripletrepair_IMG_0129.JPG20130204_tripletrepair_IMG_0130.JPG20130204_tripletrepair_IMG_0132.JPG20130204_tripletrepair_IMG_0134.JPG20130204_tripletrepair_IMG_0133.JPG 
  33   Tuesday, February 05, 2013, 16:12 Keith C NgPrimary BeamlinesMaintenance1A triplet repair (ground fault) (Completed)Today: D. Preddy completed another power
test on 1A Q14, 15, 16 after all iron/steel
shielding was restored. Magnet power and
  
  34   Wednesday, February 06, 2013, 16:33 Keith C NgPrimary BeamlinesMaintenancet2 monolith measurementsBeam lines took measurements of top of
T2 using Leica Total Station. Required no
crane activities over 1A blocks.
 20130206_t2alignmeas_IMG_0140.JPG20130206_t2alignmeas_IMG_0139.JPG 
  35   Thursday, February 07, 2013, 16:02 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationStarted work on removing M9 Q1 Q2 magnets;
area clean up and preparation, removing shielding
above Q1 and Q2 and remote handling setup
 20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG20130207_m9q1q2remove_IMG_0165.JPG20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG 
  36   Friday, February 08, 2013, 15:31 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationCompleted remote handling/shielding setup
over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were
 20130208_m9q1q2remove_IMG_0172.JPG20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG 
  37   Wednesday, February 13, 2013, 15:49 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationLocal and remote leak checks on M9 T2 area
were done today to confirm leak; Leak was
still present at T2 M9 joint. M9 Q1 and Q2
  
  38   Thursday, February 14, 2013, 15:43 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationRemoved 8" rubber test rings from
M9 T2 joint. Rings moved to RH warm cell.
Radiation levels were 70 µSv on contact
 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG 
  39   Friday, February 15, 2013, 14:29 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationBeam lines group purged M9 Q1 Q2 magnets
and water lines in preparation of disconnecting
water services to those magnets, done in
 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG 
  40   Monday, February 18, 2013, 16:24 Keith C NgM9RepairM9 Q1 Q2 removal, electrical and water disconnectedToday, re-arranged electrical wiring on
Q1 Q2 magnet away from Q2 indium joint. Cable
bundles were bundled as neatly as possible.
 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG 
  41   Tuesday, February 19, 2013, 16:46 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationDetermined M9 Q2 service stand supply connector
was slowly leaking.
- Ball valve to the supply was leaking
 20130219_m9q1q2remove_IMG_0206.JPG 
  42   Thursday, February 21, 2013, 17:02 Keith C NgM9MaintenanceM9 Q1 Q2 removal, joint dissassemblyCUALCW system water loss was not from 1A
triplet. Q15 Q16 held static  pressure at
90 psi since 9 am until 17:00. Holding with
  