Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Beamlines, Page 2 of 7  Not logged in ELOG logo
Entry  Friday, January 18, 2013, 14:40, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 20130118_tripletrepair_RHB_5431-web_m.jpg
Completed uncovering shielding and RH setup over 1A Q14 triplet area, see photo for RH setup.
Entry  Tuesday, January 22, 2013, 16:02, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 20130122_tripletrepair_IMG_0018_webm.jpg
1.5 day work delay due to plant group unavailable on the 21st of January. Gardner air compressor was being moved.
 
Today:
Entry  Wednesday, January 23, 2013, 15:51, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130123_tripletrepair_P1020666.JPG20130123_tripletrepair_P1020664.JPG20130123_tripletrepair_P1020669.JPG
Continued work on finding ground fault in 1A triplet magnets;
 
D. Preddy connected ohmeters to 1AQ14 & 15 power supplies with power leads disconnected. Ohmmeters were connected from magnet power leads to
Entry  Thursday, January 24, 2013, 17:05, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130124_tripletrepair_IMG_0047.JPG20130122_tripletrepair_IMG_0011.JPG20130124_tripletrepair_IMG_0040.JPG
Continued with work on finding ground fault on 1A triplet;
 
Uncovered Q15 & 16 to 1AS1 area. See photo below for setup.
Entry  Friday, January 25, 2013, 15:15, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130125_tripletrepair_IMG_0071.JPG20130125_tripletrepair_IMG_0067.JPG
Today: Uncovered 1A triplet cable chase and reconfigured shielding. D. Preddy will continue with diagnosing ground fault on Monday.
Entry  Monday, January 28, 2013, 16:28, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 6x
Rad survey map from last Friday (25 January) here.
 
Found exposed thermal switch cable in triplet service chase.
Entry  Tuesday, January 29, 2013, 16:28, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 
Restored shielding over 1A triplet chase.
 
Uncovered Q16 and set up RH bridge with lead blankets over Q16. 
Entry  Wednesday, January 30, 2013, 16:46, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130130_tripletrepair_P1020683.JPG20130130_tripletrepair_IMG_0123.JPG20130130_tripletrepair_P1020686.JPG20130130_tripletrepair_IMG_0118.JPG20130130_tripletrepair_P1020697.JPG
Cut and removed asymmetric steering cables from Q14 and 16, cables are no longer resting on magnet power bus bars.
 
Cut short sections left on magnet and connector block. North connector block left in place. Short cable section on magnet insulated with fiber
Entry  Friday, February 01, 2013, 14:15, Keith C Ng, Primary Beamlines, Maintenance, M9 Q1 Q2; storage pit assessment 20130201_radwastepit_P1020704.JPG20130201_radwastepit_P1020720.JPG20130201_radwastepit_P1020736.JPG20130201_radwastepit_RHB_5449.JPG
Uncovered radioactive waste storage pit to see contents. Assessing viability of moving contents inside to facilitate storage of M9 Q1 Q2 magnet. See
below for some photos.
Entry  Monday, February 04, 2013, 16:04, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130204_tripletrepair_IMG_0129.JPG20130204_tripletrepair_IMG_0130.JPG20130204_tripletrepair_IMG_0132.JPG20130204_tripletrepair_IMG_0134.JPG20130204_tripletrepair_IMG_0133.JPG
Restored 1A triplet shielding and removed RH shielding.
 
1. Moved severed asymmetric steering cable on Q14 so as not to touch the coils underneath and the cover plate above it.
Entry  Tuesday, February 05, 2013, 16:12, Keith C Ng, Primary Beamlines, Maintenance, 1A triplet repair (ground fault) (Completed) 
Today: D. Preddy completed another power test on 1A Q14, 15, 16 after all iron/steel shielding was restored. Magnet power and steering supplies were
checked and O.K.ed. R. Kuramoto deems triplet repair job completed.
 
Entry  Wednesday, February 06, 2013, 16:33, Keith C Ng, Primary Beamlines, Maintenance, t2 monolith measurements 20130206_t2alignmeas_IMG_0140.JPG20130206_t2alignmeas_IMG_0139.JPG
Beam lines took measurements of top of T2 using Leica Total Station. Required no crane activities over 1A blocks.
Entry  Thursday, February 07, 2013, 16:02, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, site prepration 20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG20130207_m9q1q2remove_IMG_0165.JPG20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG
Started work on removing M9 Q1 Q2 magnets; area clean up and preparation, removing shielding above Q1 and Q2 and remote handling setup over magnet (moving
blocks).
 
Entry  Friday, February 08, 2013, 15:31, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, site prepration 20130208_m9q1q2remove_IMG_0172.JPG20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG
Completed remote handling/shielding setup over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were 1.2 mSv/h. Shielding was built up to 20' level, same as the opposite side to minimize exposure.
Entry  Wednesday, February 13, 2013, 15:49, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 
Local and remote leak checks on M9 T2 area were done today to confirm leak; Leak was still present at T2 M9 joint. M9 Q1 and Q2 power supply leads were
disconnected (C. Yee). Next task is to find the ground fault on the Q1 magnet.
Indium one piece blank off plate (TB22267) for blanking off assembly (TB22265) was submitted into shop today.
Entry  Thursday, February 14, 2013, 15:43, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG
Removed 8" rubber test rings from M9 T2 joint. Rings moved to RH warm cell. Radiation levels were 70 µSv on contact 1.7 µSv @ 1/2 m.
Entry  Friday, February 15, 2013, 14:29, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG
Beam lines group purged M9 Q1 Q2 magnets and water lines in preparation of disconnecting water services to those magnets, done in morning.
- Note: Q15 protueus paddle wheel was replaced after finding it was worn
 
Entry  Monday, February 18, 2013, 16:24, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, electrical and water disconnected 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG
Today, re-arranged electrical wiring on Q1 Q2 magnet away from Q2 indium joint. Cable bundles were bundled as neatly as possible.
- One of the klixon thermal switch wires broke off while the cable bundles were being organized. See photo.
 
Entry  Tuesday, February 19, 2013, 16:46, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 20130219_m9q1q2remove_IMG_0206.JPG
Determined M9 Q2 service stand supply connector was slowly leaking.
- Ball valve to the supply was leaking through allowing trace amounts of water through.
- System was bled again and pressure relieved, leak appears to have stopped.
Entry  Thursday, February 21, 2013, 17:02, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, joint dissassembly 
CUALCW system water loss was not from 1A triplet. Q15 Q16 held static  pressure at 90 psi since 9 am until 17:00. Holding with very minimal  change in
pressure. Q14 reading 64 psi as of 17:00. D. Preddy informs all other systems leak tight.
 
ELOG V2.9.2-2455