Entry  Tuesday, January 21, 2020, 13:45, Aaron Schmidt, , , , , , , Problems/Solutions, RGA Communications error 
Tuesday, January 21, 2020, 13:42: The RGA was unable to connect. Typically connects on COM4, however it did not register. RGA Offline.
Brought in a separate RGA. Was able to connect & see the 2nd RGA ID on COM4. Removed 2nd RGA.
We likely need to replace / repair our communication chip again.
Entry  Thursday, January 30, 2020, 15:25, Aaron Schmidt, C(#1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C(#1) HS C#1_-_Short.docx
Was for UC# 32* - Schedule change, now for C#1
Thursday, January 30, 2020, 15:13: Roughing.
Thursday, January 30, 2020, 15:46: Turbo pumps on.
Entry  Friday, February 07, 2020, 14:02, Aaron Schmidt, C#(1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C#(1) HS C#1_-_2.docx
Was for UC# 32* - Schedule change, now for C#1* - Last HS conditioning revealed a TGHT to HS lid short. Milled the lid back 1/8" - Aaron S.
Friday, February 07, 2020, 14:00: Roughing.
Friday, February 07, 2020, 14:33: Turbo pumps on.
Entry  Tuesday, February 11, 2020, 14:27, Aaron Schmidt, , , , , , , , Pump down empty Chamber 
Tuesday, February 11, 2020, 14:27: UC#32 HS removed.
Tuesday, February 11, 2020, 14:27: Roughing.

Wednesday, February 12, 2020, 09:05: Venting.
Entry  Wednesday, February 12, 2020, 11:04, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-1, In progress, Conditioning HS UC#31.docx
Using a broken LP-FEBIAD oven for out gassing. Tentative UC#31*
Wednesday, February 12, 2020, 10:57: Roughing.
Wednesday, February 12, 2020, 11:30: Turbo pumps on.
Entry  Thursday, February 20, 2020, 11:41, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing 20200221_134828.jpg20200221_134939.jpgTa#60_-_TS_Pre-condition_-_EE_test_-_1.docx
 Ta#60 (Unconditioned) - Salts in.
Thursday, February 20, 2020, 14:04: Roughing.
Thursday, February 20, 2020, 14:38: Turbo pumps on (Leak check in am).
Entry  Thursday, February 27, 2020, 07:20, Aaron Schmidt, , , , , , , , FS#3 - Fitting change out 
Thursday, February 27, 2020, 07:10: Swapped out an old brass fitting on the supply line going into FS#3 - Line K. 
Replaced w/ SS fitting for interchangeability w/ other lines in case a bypass is needed.
Entry  Monday, March 02, 2020, 14:42, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Full TS testing w/ HV using Ta#60 
Monday, March 02, 2020, 14:36: Roughing.
Monday, March 02, 2020, 15:08: Turbo pumps on.

Remove HV cage (top). Reroute FS#3 back to cool EE
Entry  Wednesday, March 11, 2020, 13:31, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing - 2 Ta#60_-_TS_Pre-condition_-_EE_Test_-_2.docx
Thermocouples installed on EE. Double checked continuity & used a heat gun.
Wednesday, March 11, 2020, 13:30: Roughing.
Wednesday, March 11, 2020, 15:03: Turbo pumps on, interlocks by-passed (No water at
Entry  Tuesday, March 17, 2020, 11:40, Aaron Schmidt, SiC#40, HP-SIS, ITW, TM2, 42218-8, 43515-8, In progress, Conditioning SiC#40 SiC#40_-_Conditioning.docxER-580-230-30kV-m7.txtER-580-230-30kV-m23.txtER-580-230-30kV-m38.txtITW-TM2-SiC#40-HP-SIS_Test_Stand.docx
Tuesday, March 17, 2020, 11:37: Roughing.
FS# 3 re-connected. All waterlines re-opened except FS#5 (HS cooling).
Tuesday, March 17, 2020, 12:08: Turbo pumps on.
Entry  Friday, March 27, 2020, 11:30, Aaron Schmidt, , , , , , , , Vacuum loss / spike / Shutdown Mar_27_-_2020_-_Vacuum_Trip.docx
The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday, March, 23, 2020.
Check daily

Thursday, March 26, 2020, 13:25: Vacuum ok at 3.2e-07T. All status ok.
Entry  Tuesday, May 19, 2020, 06:01, Aaron Schmidt, , , , , , 42972-8, Problems/Solutions, Leak check / Troubleshoot May_19-20_Leak_check_-_FS#3.docxMess_inside_TS_-_1.jpgMess_inside_TS_-_2.jpgBlock_water_leak_visible.jpg
 https://elog.triumf.ca/TIS/Test-Stand/791
https://elog.triumf.ca/TIS/Test-Stand/792
Tuesday, May 19, 2020, 06:01: Venting. 
Entry  Wednesday, June 10, 2020, 08:23, Aaron Schmidt, C#1, LP-SIS, ITW, TM2, 43044-8, 43515-3, In progress, Conditioning C#1 7x
Salts: 
Li - 10 uL
Na - 10 uL
Entry  Tuesday, June 16, 2020, 11:03, Aaron Schmidt, Ta#60, LP-SIS, ITW, TM2, 44139-13, 43515-5, In progress, Conditioning Ta#60  Ta#60_Conditioning.docxITW-TM2-Ta#60-LP-SIS_Test_Stand.docxER-580-230-30kV-m8.txtER-580-230-30kV-m40.txt
Tuesday, June 16, 2020, 11:01: Turbo pumps on.

Wednesday, June 17, 2020, 07:49: HS waterlines opened. Vacuum stable @ 2.07e-06T.
Wednesday, June 17, 2020, 07:51: Power / Sources on.
Entry  Monday, June 22, 2020, 07:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, Test FEBIAD (Fernando) FEBIAD_Testing_-_June_22_-_23.docxER-580-280-30kV-m28.txt
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
Monday, June 22, 2020, 08:45: Roughing.
Monday, June 22, 2020, 09:17: Turbo pumps on.
Entry  Monday, July 13, 2020, 14:52, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 43515-2, , UCx HS conditioning.  
Broken LP-FEBIAD used to out gas.
Monday, July 13, 2020, 14:52: Roughing.
Monday, July 13, 2020, 15:29: Turbo pumps on. 
Entry  Monday, July 20, 2020, 11:40, Aaron Schmidt, (Empty-Test), , , , 44160-1, 43822-2, In progress, Conditioning Test P2N P2N_-_1_-_July-20-22-2020.docx
Salts added: 
Cs - 15 uL
Li - 10 uL
Entry  Tuesday, July 28, 2020, 13:27, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak on magnet PS 
 Fault: 13334
Tuesday, July 28, 2020, 12:00: Leak discovered in ISAC Test Stand MB1 PS. Appears
to be coming from hose barb soldered connection to heat sink of pass bank. Pass bank will need to be disassembled and heat sink soldered on a workbench.
Entry  Tuesday, August 04, 2020, 15:07, Aaron Schmidt, UCx, LP-SIS, , , 44139-10, 43515-4, In progress, UCx HS conditioning with PEEK assembly UCx_-_HS_w-PEEK_Assy_-_43515-4.docx
 Tuesday, August 04, 2020, 15:04: Roughing.

Wednesday, August 05, 2020, 06:08: Turbo pumps on. 

Thursday, August 06, 2020, 06:58: Vacuum @ 1.52e-06T
Entry  Wednesday, August 05, 2020, 10:01, Aaron Schmidt, , , , , , , Problems/Solutions, Roughing pump swap out. 
Wednesday, August 05, 2020, 10:00: TP6 & TP2 off. IG6 off.
Wednesday, August 05, 2020, 12:20: RP2 swapped with a smaller roughing pump from the hot lab.
Wednesday, August 05, 2020, 12:25:  Roughing.