Wednesday, October 23, 2019, 09:51, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak in Magnet PS
|
Wednesday, October 23, 2019, 09:50:
Fault: 12797
WP: C2019-10-23-2 |
Friday, November 08, 2019, 14:21, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-9, In progress, Nitrogen Bottle leak test
|
Friday, November 01, 2019, 14:00: Nitrogen bottle installed. Purged waterlines HS / FS#5. Purge done in conjunction with SiC#38
4.8 Purity
35-40 PSI pressure. |
Friday, November 15, 2019, 10:35, Aaron Schmidt, , , , , , , , Pump down empty Chamber
|
Friday, November 15, 2019, 09:35: Roughing.
Friday, November 15, 2019, 10:34: Turbo pumps on.
Wednesday, November 20, 2019, 09:19: Turbo pumps off. Ion gauge off. |
Friday, December 20, 2019, 07:59, Aaron Schmidt, , , , , , , , Holiday TS shut down
|
Friday, December 20, 2019, 07:58: Turn off ion gauges. Shut off turbo pumps TP6, TP2, TP1A, & TP1B. Close backing valves.
Friday, December 20, 2019, 08:06: PV1 & PV2 off. RP1 & RP2 off.
Monday, January 06, 2020, 09:35: Restarting TS. RP1 & RP2 on. (BIAS PS upgraded / Note: https://elog.triumf.ca/TIS/Test-Stand/776 ). |
Tuesday, January 21, 2020, 09:38, Aaron Schmidt, SiC#40, LP-SIS, , , 43044-8, 43515-8, In progress, Conditioning SiC#40 HS  
|
Was intended for UC#31 - Now used for SiC#40*
PEEK SEAL Test piece attached.
Tuesday, January 21, 2020, 09:34: BV1A open Roughing. |
Tuesday, January 21, 2020, 13:45, Aaron Schmidt, , , , , , , Problems/Solutions, RGA Communications error
|
Tuesday, January 21, 2020, 13:42: The RGA was unable to connect. Typically connects on COM4, however it did not register. RGA Offline.
Brought in a separate RGA. Was able to connect & see the 2nd RGA ID on COM4. Removed 2nd RGA.
We likely need to replace / repair our communication chip again. |
Thursday, January 30, 2020, 15:25, Aaron Schmidt, C(#1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C(#1) HS
|
Was for UC# 32* - Schedule change, now for C#1
Thursday, January 30, 2020, 15:13: Roughing.
Thursday, January 30, 2020, 15:46: Turbo pumps on. |
Friday, February 07, 2020, 14:02, Aaron Schmidt, C#(1), LP-SIS, , , 43044-8, 43515-3, In progress, Conditioning C#(1) HS
|
Was for UC# 32* - Schedule change, now for C#1* - Last HS conditioning revealed a TGHT to HS lid short. Milled the lid back 1/8" - Aaron S.
Friday, February 07, 2020, 14:00: Roughing.
Friday, February 07, 2020, 14:33: Turbo pumps on. |
Tuesday, February 11, 2020, 14:27, Aaron Schmidt, , , , , , , , Pump down empty Chamber
|
Tuesday, February 11, 2020, 14:27: UC#32 HS removed.
Tuesday, February 11, 2020, 14:27: Roughing.
Wednesday, February 12, 2020, 09:05: Venting. |
Wednesday, February 12, 2020, 11:04, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-1, In progress, Conditioning HS
|
Using a broken LP-FEBIAD oven for out gassing. Tentative UC#31*
Wednesday, February 12, 2020, 10:57: Roughing.
Wednesday, February 12, 2020, 11:30: Turbo pumps on. |
Thursday, February 20, 2020, 11:41, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing  
|
Ta#60 (Unconditioned) - Salts in.
Thursday, February 20, 2020, 14:04: Roughing.
Thursday, February 20, 2020, 14:38: Turbo pumps on (Leak check in am). |
Thursday, February 27, 2020, 07:20, Aaron Schmidt, , , , , , , , FS#3 - Fitting change out
|
Thursday, February 27, 2020, 07:10: Swapped out an old brass fitting on the supply line going into FS#3 - Line K.
Replaced w/ SS fitting for interchangeability w/ other lines in case a bypass is needed. |
Monday, March 02, 2020, 14:42, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Full TS testing w/ HV using Ta#60
|
Monday, March 02, 2020, 14:36: Roughing.
Monday, March 02, 2020, 15:08: Turbo pumps on.
Remove HV cage (top). Reroute FS#3 back to cool EE |
Wednesday, March 11, 2020, 13:31, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing - 2
|
Thermocouples installed on EE. Double checked continuity & used a heat gun.
Wednesday, March 11, 2020, 13:30: Roughing.
Wednesday, March 11, 2020, 15:03: Turbo pumps on, interlocks by-passed (No water at |
Tuesday, March 17, 2020, 11:40, Aaron Schmidt, SiC#40, HP-SIS, ITW, TM2, 42218-8, 43515-8, In progress, Conditioning SiC#40    
|
Tuesday, March 17, 2020, 11:37: Roughing.
FS# 3 re-connected. All waterlines re-opened except FS#5 (HS cooling).
Tuesday, March 17, 2020, 12:08: Turbo pumps on. |
Friday, March 27, 2020, 11:30, Aaron Schmidt, , , , , , , , Vacuum loss / spike / Shutdown
|
The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday, March, 23, 2020.
Check daily
Thursday, March 26, 2020, 13:25: Vacuum ok at 3.2e-07T. All status ok. |
Tuesday, May 19, 2020, 06:01, Aaron Schmidt, , , , , , 42972-8, Problems/Solutions, Leak check / Troubleshoot   
|
https://elog.triumf.ca/TIS/Test-Stand/791
https://elog.triumf.ca/TIS/Test-Stand/792
Tuesday, May 19, 2020, 06:01: Venting. |
Wednesday, June 10, 2020, 08:23, Aaron Schmidt, C#1, LP-SIS, ITW, TM2, 43044-8, 43515-3, In progress, Conditioning C#1 7x
|
Salts:
Li - 10 uL
Na - 10 uL |
Tuesday, June 16, 2020, 11:03, Aaron Schmidt, Ta#60, LP-SIS, ITW, TM2, 44139-13, 43515-5, In progress, Conditioning Ta#60   
|
Tuesday, June 16, 2020, 11:01: Turbo pumps on.
Wednesday, June 17, 2020, 07:49: HS waterlines opened. Vacuum stable @ 2.07e-06T.
Wednesday, June 17, 2020, 07:51: Power / Sources on. |
Monday, June 22, 2020, 07:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, Test FEBIAD (Fernando) 
|
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
Monday, June 22, 2020, 08:45: Roughing.
Monday, June 22, 2020, 09:17: Turbo pumps on. |
|