Entry  Thursday, July 12, 2018, 08:24, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Power outage / restart 
Power outage (07/11/2018 @ approx 21:53) shut down the test stand.
Entry  Thursday, July 12, 2018, 10:11, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Coil Test #5 
 *** REVIEW Elog entry #673 Power outage & restart ***
Thursday, July 12, 2018, 10:10: Opened IV4
Thursday, July 12, 2018, 10:20: Attempt auto-ramp cancelled. Max increment values reached. Wait on Vacuum.
Entry  Tuesday, October 02, 2018, 13:39, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps w/ stoppage FEBIAD_Coil_Test_6_-_POS_Cathode.docxTS-2018-10-11-10-37.rga
Silver bolts used on Coil, TGHT, & TBHT.
End caps in target
Tuesday, October 02, 2018, 13:36: Roughing.
Entry  Monday, October 15, 2018, 14:23, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps  FEBIAD_Coil_Test_6-2_-_Neg_Cathode.docxTS-2018-10-15-14-15.rga
Anode / Cathode BIAS PS polarity reversed by John Chow. PS: Negative
Monday, October 15, 2018, 14:12: Power/sources on
Monday, October 15, 2018, 14:17: RGA on.
Entry  Monday, October 22, 2018, 11:07, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps  epics-plot-whiteout-181028_1322.PNGepics-whiteout-181028_1322.PNGFEBIAD_COIL_Test_6-3_Caps_in.docxTS-2018-10-22-09-47.rga
Restarted post power outage.
Water & Turbos on.
Monday, October 22, 2018, 10:55: Power / sources on. MB1?
Entry  Monday, October 29, 2018, 10:56, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Problems/Solutions, TS communications issues. 
Sometime around 00:30 Sunday, October 28, 2018, the ISAC test stand lost communication to the PLC and shut down abruptly.
Monday, October 29, 2018, 09:00: PLC communications issues.
Rod N. was contacted this morning& the issues fixed by controls group.
Entry  Monday, October 29, 2018, 11:03, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Done, Test FEBIAD w/ Silver bolts & sealed end caps 
Restarting FEBIAD
Monday, October 29, 2018, 10:56: Restart roughing & Turbo pumps.
Monday, October 29, 2018, 11:03: Ion gauges on.
Entry  Thursday, November 08, 2018, 10:54, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, In progress, Test FEBIAD w/ Silver bolts & sealed end caps 
Silver bolts used on Coil, TGHT, & TBHT. Back panel opened for new gas bottles.
Thursday, November 08, 2018, 10:52: Roughing
Thursday, November 08, 2018, 10:53: Doors sealed.
Entry  Wednesday, December 12, 2018, 13:22, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, In progress, Anode leak current check. 
Wednesday, December 12, 2018, 13:15: Power / Sources on.
Wednesday, December 12, 2018, 13:20: RGA on / set.
Wednesday, December 12, 2018, 13:29: BIAS / EZL / EE @ 30 / 13.5 / 1.5 kV.
Entry  Monday, December 17, 2018, 12:03, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, , Anode leak current check. 
Monday, December 17, 2018, 12:01: Connected Multimeter through feedthroughs J & L. Blue wire removed.
To run TGHT, TBHT, Anode ONLY. HV will remain locked with yellow tape over the keyhole. Currently locked out.

Tuesday, December 18, 2018, 08:37: Power / sources on
Entry  Thursday, December 20, 2018, 13:55, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, , Holiday shut down. 
High winds caused a brief power outage that completely shutoff the ISAC test stand.
Locked out the power.
RGA checked & shutoff complete
Entry  Tuesday, January 08, 2019, 08:11, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, In progress, TS restart  
Tuesday, January 08, 2019, 08:00: Epics white out fixed. Ref: Fault report 11981.
Tuesday, January 08, 2019, 08:10: IV4 reset. Turbo Pumps on
TMS:IG6 & TSG:IG1 not responding. Timing out. Edi contacted
Entry  Friday, February 22, 2019, 11:11, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas line backing pump tests 
Backing "mini pump" testing.
-Open gas lines & auto ramp (If using HV, close up the back)
-HV on
Entry  Friday, March 01, 2019, 14:51, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas lines test & Emissions measurement prep gas-lines-changes.jpgGas_line_backing_pump_test_2019.docxTS-2019-03-05-09-45.rgaTS-2019-03-06-08-00.rga
Friday, March 01, 2019, 14:50:
SV5 replaced with a new valve.
SV1 disconnected from the He line and linked to the mini pump line.
Entry  Thursday, March 07, 2019, 07:55, Aaron Schmidt, , LP-FEBIAD, , , , , Problems/Solutions, TS restart - Troubleshoot BIAS spark BIAS_spark_out_issue_-_2019.docxTS-2019-03-07-07-51.rga
Thursday, March 07, 2019, 07:48: IV4 reset, BV6 & TMS TP6 reset.
Turbo pump restarted.
Auto cooling @ 2A per min.
Entry  Friday, April 05, 2019, 07:02, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, In progress, TS operation test - LP FEBIAD TS_-_New_BIAS__EZL_Testing_-_2019.docxTS-2019-04-05-07-00.rga
Due to previous issues, a full run / test should be performed on the ISAC Test Stand.
Friday, April 05, 2019, 07:00: RGA on.
Friday, April 05, 2019, 07:03: Begin opening / closing gas lines until they can be opened & stable.
Entry  Saturday, May 25, 2019, 12:43, Aaron Schmidt, Test FEBIAD / TM4, LP-FEBIAD, , TM4, 395530-3, 42752-5, In progress, Installed TM4 Source Tray TM4_Source_Tray_-_2019_-_Leak_Check.docxTM4_Source_Tray_-_2019.docxTS-2019-05-27-07-08.rga
Silver bolts on TGHT & Coil Lines. Oxide steel bolts on TBHT. Filed target to suit / fit (Previously heated). Rubber O-rings used instead of C-seals
on the water blocks.
Saturday, May 25, 2019, 12:38: Leak check ok. 0.0E-07 Torr-I/sec. He @ 30 PSI. Carla checked the multi-pin connection. OK.
Entry  Tuesday, May 28, 2019, 15:05, Aaron Schmidt, Test FEBIAD / TM4, LP-FEBIAD, , TM4, 395530-3, 42752-5, In progress, TM4 Source Tray - Episode II TM4_Source_Tray_-_2019_-_2.docxTS-2019-05-29-07-08.rgaTM4_Source_Tray_-_2019_-_3_-_HV_-_1.docxTM4_Source_Tray_-_2019_-_4_-_HV_-_2_-_Heat_on.docxTM4_Source_Tray_-_2019_-_5_-_HV_over_50_-Heat_on.docx
SEE ELOG 724
Tuesday, May 28, 2019, 15:02: Roughing
Tuesday, May 28, 2019, 15:32: Turbos on.
Entry  Tuesday, June 11, 2019, 14:33, Aaron Schmidt, Test FEBIAD, LP-FEBIAD, , , 395530-3, 42752-5, In progress, ISAC Source tray re-installed w/ optics tray. 
Tuesday, June 11, 2019, 14:33: Roughing.

Wednesday, June 12, 2019, 08:18: Venting to install FEBIAD.
Wednesday, June 12, 2019, 09:13: LP-FEBIAD installed. Roughing.
Entry  Thursday, August 08, 2019, 09:12, Aaron Schmidt, , LP-FEBIAD, , , , 42752-7, In progress, P2N Setup - LP-FEBIAD target 8x
Inserted a used (heating) LP-FEBIAD target with a basic heat shield assembly with no end plate foil on the window side to observe heating. The P2N Coil
/ TGHT connections were added.
Test whether the TS connections are affecting the P2N heating or if it's the P2N target itself.