Message ID: 709     Entry time: Friday, February 22, 2019, 11:11
Author: Aaron Schmidt 
Target/No.#:  
Source: LP-FEBIAD 
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status:  
Subject: Gas line backing pump tests 

Backing "mini pump" testing.

-Open gas lines & auto ramp (If using HV, close up the back)

-HV on

-Close SV5, SV4, SV3 when ready. Wait until stable. Take measurement (1/2 hr approx)

-Turn down HV. Interlock, leave heaters on.

-Turn on mini pump.

-Open, SV4, SV3 carefully.

-Open MP valve. Wait 15 min. Close MP valve

-Carefully open SV5. Quick open & shut. Monitor vacuum 7.0e-06T trip limit.

-Monitor / record. Carefully open & close until stable.

-Close up TS w/ interlock

-HV on again & test.

 


Friday, February 22, 2019, 11:06: Auto-ramping TGHT / TBHT to 100 / 75 A. Gas lines open.

Friday, February 22, 2019, 11:31: HV on. BIAS / EZL / EE @ 5 / 1 / 0.1 kV. Anode @ 25 V - Low settings to check for trip and practice.

Friday, February 22, 2019, 11:43: HV unstable. Bump up. BIAS / EZL / EE @ 10 / 5 / 0.2 kV. Anode @ 25 V - Low settings stable.

Friday, February 22, 2019, 12:36: SV3 closed (Neon)

Friday, February 22, 2019, 12:46: SV4 (Argon), SV5 closed.

Friday, February 22, 2019, 12:57: HV off.

Friday, February 22, 2019, 13:00: Interlock complete. Mini pump on.

Friday, February 22, 2019, 13:10: MP valve opened manually.

Friday, February 22, 2019, 13:16: SV3 open. SV4 open.

Friday, February 22, 2019, 13:19: MP valve closed. pump off. SV5 opened / closed fast & intermittent.

Friday, February 22, 2019, 13:22: SV5 open fully. Gas lines all open.

Friday, February 22, 2019, 13:24: HV on. Interlock out.

Friday, February 22, 2019, 13:27: BIAS / EZL / EE @ 10 / 5 / 0.2 kV. Anode @ 25 V - Low settings stable.

Friday, February 22, 2019, 13:30: Setting reset, including optics. TGHT / TBHT did not trip.TEST 1 SUCCESS!.


Monday, February 25, 2019, 07:36: Auto-ramping TGHT / TBHT to 580 / 290 A. Gas lines open. 

Monday, February 25, 2019, 11:04: BIAS / EZL / EE @ 30 / 13 / 1.5 kV. Anode @ 200V

Monday, February 25, 2019, 13:38 : SV3 closed.

Monday, February 25, 2019, 14:25: SV5 closed.

Monday, February 25, 2019, 14:45: HV off. 

Monday, February 25, 2019, 14:50: Mini-pump on.

Monday, February 25, 2019, 14:53: Open MP valve

Monday, February 25, 2019, 14:57: Open SV3 & SV4

Monday, February 25, 2019, 14:59: Close MP valve.

Monday, February 25, 2019, 15:00: Open / Close SV5 intermittently until stable.

Monday, February 25, 2019, 15:01: SV5 Open.

Monday, February 25, 2019, 15:04: Locked up. Power back to HV. Optics switched on. FC0 closed. Ready for HV


Wednesday, February 27, 2019, 08:11: Auto-cooling @ 2 A per min 

Wednesday, February 27, 2019, 13:23: gas lines closed.


Friday, March 01, 2019, 10:35: IV4 reset

Friday, March 01, 2019, 10:42: Ion gauge 1 & the turbo pumps off.

ELOG V2.9.2-2455