  825   Wednesday, December 02, 2020, 16:18 Fernando Maldonado      DoneGas delivery system upgradeYesterday, December 1st, I successfully
installed and tested the gas system inside
the faraday cage.
  
  824   Wednesday, December 02, 2020, 08:32 Carla Babcock       Modifications to test stand for TM3 testsWednesday, December 02, 2020, 08:31 :
Added copper wire connection to multipin
screw terminals in HV cage to make sure they
  
  823   Tuesday, December 01, 2020, 17:04 Carla Babcock      Problems/SolutionsFound another burned jumper cableBetween feedthroughs F (magnet coil) and
B (tube heater negative), I found a jumper
with two resistors that has been burned up.
 20201201_115557.jpg 
  822   Tuesday, December 01, 2020, 11:56 Carla Babcock      In progressModifications to test stand for TM3 testsTuesday, December 01, 2020, 11:56 :
TSG:BIAS unplugged and controls pigtail
(made by Ray) added in order to connect controls
  
  821   Monday, November 23, 2020, 10:03 Aaron Schmidt      Problems/SolutionsRP2 Check / pump down issueTMSRP2 has been struggling since the power
bump occurred Nov 18, 2020
Monday, November 23, 2020, 09:48:
 20201123_114110.jpg20201123_120204.jpg20201123_120208.jpg20201123_131124.jpg20201123_131127.jpg 
  820   Tuesday, November 10, 2020, 12:13 Aaron Schmidt    43044-1344378-1In progressPump down empty chamber / Leak.U-Loop installed on FS#5
Tuesday, November 10, 2020, 12:13:
Roughing.
  
  819   Friday, November 06, 2020, 12:53 Aaron SchmidtNb#9LP-SISITWTM244508-243515-4In progressConditioning Nb#9 w/ P/S Target & BracketAttached end plate parasitic / symbiotic
target & PEEK assembly bracket.
Friday, November 06, 2020, 12:24:
 7x 
  818   Monday, November 02, 2020, 08:52 Aaron Schmidt      Problems/SolutionsLeak check / TroubleshootMonday, November 02, 2020, 08:46:
Large Vacuum spike noted 5:30 approx.
Tripped TS. On tail end of the Nb#9 conditioning
 Nov-2-2020_Leak.docx 
  817   Tuesday, October 27, 2020, 08:54 Aaron SchmidtNb#9 LP-SISITWTM244508-243515-4In progressNb#9 ConditioningTuesday, October 27, 2020, 08:40: Roughing.
Tuesday, October 27, 2020, 09:13:
TP1B on.
 Nb#9_Conditioning.docxER-580-230-30kV-M133.txtER-580-230-30kV-M23.txt 
  816   Friday, October 16, 2020, 11:33 Aaron SchmidtTa#61LP-SISITETM444508-143515-1In progressConditioning Ta#61Friday, October 16, 2020, 11:11: Roughing.
Friday, October 16, 2020, 11:39:
TP1B on.
 Ta#61.docxITE-TM4-Ta#61-LP-SIS_Test_Stand.docxER-580-230-30kV-M133.txtER-580-230-30kV-M28.txt 
  815   Tuesday, October 13, 2020, 12:34 Aaron Schmidt HP-FEBIAD  38295-842752-5In progressMB1 Check.He & Ar calibrated leak bottles in.
Tuesday, October 13, 2020, 12:33:
Roughing.
 MB1_Check_Oct_-_2020.docx 
  814   Wednesday, September 30, 2020, 06:23 Aaron SchmidtC#2LP-SISITWTM244139-943515-2In progressConditioning C#2Wednesday, September 30, 2020, 06:14: Power
/ sources on.
Wednesday, September 30, 2020, 06:17:
 C#2_-_Short_-_EZL.docxC#2_Conditioning.docxITW-TM2-C#2-LP-SIS_Test_Stand.docx 
  813   Tuesday, September 29, 2020, 11:56 Aaron Schmidt LP-SIS    Problems/SolutionsLeak check 3.0Installed Indium gasket on FS#2 - (C) water
block / R- TGHT.
Tuesday, September 29, 2020, 11:23:
  
  812   Thursday, September 03, 2020, 11:28 Aaron Schmidt-HP-FEBIAD  38295-842752-5In progressLeak check 2.0Out Gas & MB1 check (Or leak check
2.0)
Ref: https://elog.triumf.ca/TIS/Test-Stand/809
  
  811   Tuesday, September 01, 2020, 14:01 Aaron Schmidt      DoneNew tubing installed on loopsTuesday, September 01, 2020, 14:00: 
New tubing installed.
Blue on FS#4 loop (A)(B)
  
  810   Tuesday, August 25, 2020, 07:23 Aaron Schmidt      Problems/SolutionsBeam line side vacuum tripTuesday, August 25, 2020, 07:07: Beam line
side of the TS appears to have tripped? Open
BV6 & BV2.
  
  809   Wednesday, August 19, 2020, 08:52 Aaron Schmidt       Leak check / TroubleshootWednesday, August 19, 2020, 08:52: Purging
all lines, except FS#5, It was already purged
/ closed.
 Aug_19_-_2020_Leak_Check..docx 
  808   Tuesday, August 18, 2020, 12:07 Aaron SchmidtTest FEBIADHP-FEBIAD  38295-842752-5In progressRP check & Mass magnet check.Tuesday, August 18, 2020, 12:05: RP1 on
Tuesday, August 18, 2020, 12:10:
RP1 off
  
  807   Tuesday, August 18, 2020, 10:00 Aaron Schmidt       IDP15 Scroll pump installed - RP1 replacedPN: X3815-64000
SN: MY2005SA02
Description: IDP15 Scroll pump, Std.
  
  806   Tuesday, August 11, 2020, 12:04 Aaron SchmidtUCxLP-SIS  44139-1043515-4In progressUCx HS conditioning with PEEK assemblyHS target leg openings were milled. Short
from previous test by the look of it. TBHT
insulator on source side is cracked.
  