  RH-Meson Hall, Page 5 of 18  Not logged in ELOG logo
ID Date Author Category Typedown Specific Subject Text Attachments
  187   Wednesday, February 03, 2016, 17:35 Isaac EarleStandard OperationTarget 2CoolingT2 MRO WorkThe following work was performed at the
T2 cooling package and target between Jan
25 - Feb 3, 2016:
  
  190   Wednesday, March 16, 2016, 16:50 Isaac EarleDevelopmentTarget 2ControlsPreliminary Testing of T2 Control System CompletePreliminary testing of the new
PLC control system and EPICS interface was
 T2_Testing_Checklist_-_Complete_-_March_16_2016.pdf 
  196   Monday, April 11, 2016, 13:54 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Transported from BL to HCThe T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask.  The target was measured to be
  
  197   Friday, April 15, 2016, 14:54 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Changes & Return to BeamlineOn April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure.  The target ladder
 T2-MK2_Position_4_Entrance_Side_-_April_14_2016.JPGT2-MK2_Position_4_Exit_Side_-_April_14_2016.JPGIMG_7024.JPGIMG_7026.JPG 
  200   Friday, May 13, 2016, 15:04 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Position 4 Adjusted to +1.5mm OffsetThe T2-MK2 target at Position 4 has been
adjust to approximately +1.5mm offset.  This
causes the ladder to be moved downwards,
  
  201   Wednesday, June 15, 2016, 11:00 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Moved to Position #1 Position #4 on the T2-MK2 target
has now reached the maximum beam time.  The
target was moved to Position #1 at the nominal
  
  211   Thursday, November 17, 2016, 17:58 Isaac EarleRepairTarget 2CoolingT2 Heat Exchanger Secondary Side Solenoid Valve Failure At approximately 11am today the T2
cooling package heat exchanger secondary
side water flow suddenly dropped from ~11gpm
  
  212   Monday, January 09, 2017, 15:07 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Moved from BL to HC The T2-MK2 target assembly was moved
from the beam line to the hot cell today.
 A maximum field of 203mSv/hr was measured
  
  213   Thursday, January 12, 2017, 09:21 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Position 1 Beam Spot The beam spot on the 10cm beryllium
target in Position 1 on T2-MK2 (Target ID:
"OCT.06#3") was measured and photographed
 T2-MK2_Posn_1_Beam_Spot_-_Jan_11_2017.jpgT2-MK2_Position_1_Beam_Spot_Measurements_-_Jan_11_2017.pdf 
  219   Tuesday, April 11, 2017, 17:02 Isaac EarleMaintenanceTarget 2CoolingT2 Cooling System MRO The following work has been completed
on the T2 cooling package:
- T2 system drained to South TNF
  
  220   Tuesday, April 11, 2017, 17:31 Isaac EarleDevelopmentTarget 2TargetT2-MK2 target MRO and alignment of T2 devicesThe following work was performed on
the T2-MK2 target assembly and the T2 Protect
assembly for maintenance purposes and to
 T2-MK2_-_2017.pdf 
  221   Friday, May 05, 2017, 15:09 Isaac EarleDevelopmentTarget 2TargetT2-MK2 beam spot check in hot cell On May 5th the T2-MK2 target was
moved to the hot cell for the purpose of
checking the beam spot on the Position 2
 T2MK2_Position_1_and_2_Exit.JPGT2MK2_Position_2_Entrance.JPGT2MK2_Position_2_Exit.JPGT2-MK2_profile_monitor_dislodged.JPG 
  222   Tuesday, May 09, 2017, 16:35 Isaac EarleRepairTarget 2CoolingT2 target water flow gauge paddle wheel changed During the target move on Thursday
May 4th the paddle wheel and paddle wheel
shaft for the T2CS:FGTGT sensor were changed
 T2CS_FGTGT_strip.jpg 
  223   Monday, May 15, 2017, 16:55 Isaac EarleOtherTarget 2TargetT2 profile monitor actuation issue On Thursday May 11th operators attempted
to move the T2 profile monitor (T2-MK2) to
the IN position but were unsuccessful.  The
  
  224   Monday, July 10, 2017, 16:20 Keith C NgRepairTarget 2TargetT2 Heat Exchanger Secondary Side Solenoid Valve Failure The T2 heat exchanger secondary side solenoid
failed on July 9 at approximately 19:30 (EPICS
ID: B1A:T2CS:SVSEC).  The valve was
 20170710_t2_water_package_repair.pdf 
  225   Tuesday, July 25, 2017, 19:23 Isaac EarleRepairTarget 2CoolingT2 Heat Exchanger Secondary Side Solenoid Valve Failure (again) At approximately 13:50 today the
T2 cooling system secondary side solenoid
valve (T2CS:SVSEC) failed to a closed position.
  
  226   Thursday, July 27, 2017, 08:57 Isaac EarleOtherTarget 2CoolingFailed T2CS:SVSEC valves investigation The three failed T2 cooling system
secondary side solenoid valves were tested
yesterday to try to determine the problem.
  
  229   Tuesday, October 10, 2017, 12:09 Isaac EarleStandard OperationTarget 2TargetT2-MK2 position 4 target changedThe following work was performed on
the T2-MK2 target assembly during the 2017
fall shutdown:
 20171005_t2target_0010.jpg20171005_t2target_0015.jpg20171005_t2target_0016.jpg 
  232   Wednesday, January 10, 2018, 17:45 Isaac EarleStandard OperationTarget 2TargetT2-MK2 beam spot photos, M20BB moved to storage pit The T2-MK2 target was moved from
the beamline to the hot cell on January 8th. 
The field at 0.5m was 130mSv/hr.  Photographs
 T2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018.jpgT2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018_s.jpg 
  235   Friday, April 06, 2018, 15:05 Isaac EarleStandard OperationTarget 2TargetT2-MK2 target MROThe following is a summary of MRO work
done on the T2-MK2 target during the 2018
shutdown:
  