Thursday, October 19, 2017, 14:20, Anders Mjos, Assembly/Bench Test, Standard Operation, , , Source tray inspection
|
Two minor chips in the main 60 kV insulators on the source tray was inspected today by Anders, Tom and Aurelia. The chips are small enough that
they should not be a problem. See photos for details. |
Thursday, October 19, 2017, 10:11, David Wang, Conditioning Station, Standard Operation, TM4, , Leak check on TM4 HS line at SHC and TCS.
|
Chad and I leak checked TM4 HS line after new target is installed yesterday. No leak has been found. Also, I helium pressurized the HS line at TCS this
morning. TM4 HS line is good on this test. The TM4 gas line configuration on TM4 top is leak check as well. No problem. |
Wednesday, October 18, 2017, 14:54, Anders Mjos, Assembly/Bench Test, Standard Operation, , , Source tray assembly electrical check
|
Source tray meggered today by Anders and Keith
GND - MSP OL @ 1000V
MSP - EE OL @ 1000V |
Wednesday, October 18, 2017, 10:46, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#37, Module move
|
TM#4 with SiC#37 has been moved from the south hot cell to the conditioning station. |
Wednesday, October 18, 2017, 10:45, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#37, Electrical Check
|
The results of the electrical check of TM#4 with SiC#37, see attached PDF. |
Tuesday, October 17, 2017, 10:56, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#21, Module move
|
TM#4 with UC#21 has been moved from the east target station to the south hot cell. |
Friday, October 13, 2017, 11:14, Keith C Ng, Assembly/Bench Test, Standard Operation, , , source tray alignment/build
|
Source tray is complete for brazing, gas line bracket is currently missing but can be made in parallel with tube bending operations.
Source tray water lines to be fabricated according to ITA6144 drawing set.
- Alignment between target mounting plate and steerer cone is holding within .002" |
Thursday, October 12, 2017, 08:48, Travis Cave, Spent Target Vault, Standard Operation, , , Field measurements of the old source trays
|
Field measurements were taken of the old source trays. The old TM#2 source tray had a minimum field value of 0.50 mSv/hr and a maximum of 1.18
mSv/hr through 360 deg of rotation. The box was rotated around three times and put back in the vault. TM#1 old source tray was also removed and measured
as well the field values for it were a minimum of 0.52 mSv/hr and a maximum of 1.15 mSv/hr through 360 deg of rotation. The box was rotated around three |
Wednesday, October 11, 2017, 15:50, Keith C Ng, Assembly/Bench Test, Standard Operation, , , spare source tray build alignment
|
Spare source tray build continued. |
Tuesday, October 10, 2017, 10:45, David Wang, Conditioning Station, Repair, , , Re-route TCS water lines. 8x
|
TCS cooling polyurethane lines have been re-routed to solve to HV sparking issue on old configuration between lines and bais plate. New re-routed
system is tested to 70KV without spark. No leak has been found on new lines after the test.
ECO 4369, drawings and models IRH1715, IRH1716 have been issued and released for this job. Drawings and Models are located in PDM-ISAC1 -TCS polyurethane |
Tuesday, October 10, 2017, 10:38, David Wang, ITW, Standard Operation, , , 5 shielding blocks have been transferred from ITE to ITW .
|
ITW is configured to take proton beam. |
Friday, October 06, 2017, 13:25, Anders Mjos, Conditioning Station, Repair, , , HV Test
|
HV was brought up to 70 kV for 1 h without sparks to test the new water installation. |
Friday, October 06, 2017, 11:21, Isaac Earle, North Hot-Cell, Development, , , ISAC-1 active sump drain pipe modified
|
The 4" PVC drain line in the ISAC-1 active sump was modified so that the drain pipe terminates below the low level water line of the automatic pump-out
system. This will prevent backflow of sump gasses into the SHC, NHC, or TCS space if the air pressure in any of those rooms are lower than the sump
air pressure. The details of the modification were specified by Mechanical Services Group, and the work was done by Paul Jensen. This system |
Friday, October 06, 2017, 11:12, Isaac Earle, North Hot-Cell, Development, , , NHC module port shield block and TCS vessel shield block installed
|
The NHC module port shield block (IRH1645) and the TCS vessel shield block (IRH1646) were installed yesterday in the target hall according to assembly
drawing IRH1652. No issues were encountered during installation. Vacuum was pulled on the TCS and a leak check was performed on the shield:
no leaks found. |
Thursday, October 05, 2017, 11:04, Anders Mjos, ITW, Maintenance, , , Installation of new valve for module move ventilation
|
David installed the new ball valve and connections for the SAS project module move ventilation. SASP0482. Drawing reference ISK5029B. |
Tuesday, October 03, 2017, 09:29, Travis Cave, ITW, Standard Operation, TM2, Ta#54, Module move
|
TM#2 with Ta#54 has been moved from the conditioning station to the west target station. |
Thursday, September 28, 2017, 17:44, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#54, Conditioning Ta#54
|
Thursday, September 28, 2017
Cooling water not yet connected to TM.
High leakage current still observed. 200 uA at 22 kV. Did not go past 25 kV. |
Thursday, September 28, 2017, 15:34, Anders Mjos, Conditioning Station, Development, TM2, , Changes to MP3 startup
|
Due to problems with the regulating valve WPV1, the VFD (Variable Frequency Drive) for the pump has been programmed to do a slow (2 min) ramp up.
WPV1 has been bypassed and left fully opened. Work was done by Dave Morris |
Thursday, September 28, 2017, 11:59, Travis Cave, Spent Target Vault, Standard Operation, , Ta#53, Spent Target move
|
The spent Ta#53 has been moved to the spent target vault. See attached file for details. |
Thursday, September 28, 2017, 10:50, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 window and HS water lines at TCS.
|
I did helium pressure test on TM2 containment box window and HS line at TCS. @ 70psi helium for 3 minutes, HS:2.2XE-7 atm.cc/sec., Window:1.2XE-7
atm.cc/sec. There is no change on HS. But LR on window is bigger than before that was in E -9atm.cc/sec range. |
|